− | ; | + | ;Phase 1 Region |
− | Phase 1 Region | + | * 200 kV gun => building a second 18" gun appropriate for CEBAF, to condition to 300 kV, and operate at 200 kV |
− | * | ||
* (Lakshmi) Replace DR dipole => PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils | * (Lakshmi) Replace DR dipole => PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils | ||
* (Sarin/Riad) Replace noisy Wien 20A SCE => | * (Sarin/Riad) Replace noisy Wien 20A SCE => | ||
− | * (Phil) Repair leaky PCUP LCW fitting | + | * (Phil) Repair leaky PCUP LCW fitting => labor, no M&S |
− | * (Marcy) Remake A2 joint | + | * (Marcy) Remake A2 joint => labor, no M&S |
− | * (Marcy) Replace harp | + | * (Marcy) Replace harp => labor, no M&S |
− | * (Jerry) Install & test 200 kV kicker | + | * (Jerry) Install & test 200 kV kicker => waiting for Jerry's reply |
;Phase 2 Region | ;Phase 2 Region | ||
Line 26: | Line 25: | ||
* (FM) Install bright lighting => Walked area with FM. Waiting for follow-up. | * (FM) Install bright lighting => Walked area with FM. Waiting for follow-up. | ||
− | + | ;Non-AIPINJ Jobs | |
* Test mode-locked laser | * Test mode-locked laser | ||
* Return gold target ladder, w/ larger nipple, original STAC5 | * Return gold target ladder, w/ larger nipple, original STAC5 | ||
* Store tunnel HV cables nicely, like we do now at UITF | * Store tunnel HV cables nicely, like we do now at UITF |
Revision as of 13:58, 14 September 2021
Recent Updates
Planning, planning, planning...
Major Phase 2 Beamline Components
2022 Winter SAD ATLIS Tasks
- Phase 1 Region
- 200 kV gun => building a second 18" gun appropriate for CEBAF, to condition to 300 kV, and operate at 200 kV
- (Lakshmi) Replace DR dipole => PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils
- (Sarin/Riad) Replace noisy Wien 20A SCE =>
- (Phil) Repair leaky PCUP LCW fitting => labor, no M&S
- (Marcy) Remake A2 joint => labor, no M&S
- (Marcy) Replace harp => labor, no M&S
- (Jerry) Install & test 200 kV kicker => waiting for Jerry's reply
- Phase 2 Region
- (Matt) Possibly install solenoid/valve downstream of chopper => MMF mapping solenoids in Sep. Do we have 2-3/4" pneumatic beam line valve?
- (FM) Install bright lighting => Walked area with FM. Waiting for follow-up.
- Non-AIPINJ Jobs
- Test mode-locked laser
- Return gold target ladder, w/ larger nipple, original STAC5
- Store tunnel HV cables nicely, like we do now at UITF