Difference between revisions of "MOLLER PQB Meeting May 15, 2024"

From Ciswikidb
Jump to navigation Jump to search
 
(6 intermediate revisions by the same user not shown)
Line 9: Line 9:
 
* '''Beam Studies, Sunday May 19th:'''  
 
* '''Beam Studies, Sunday May 19th:'''  
  
# BLM calibration, 8:00 am - 10:00 am, Hall A access
+
# BLM calibration, 8:00 am - 10:00 am, Hall A access (7 am)
# FFB in Hall A, 25 µA and up, 10:00 am - 1:00 pm
+
# FFB/FF in Hall A, 25 µA and up, 10:00 am - 1:00 pm
 
# Raytrace 1:00 pm - 1:30 pm
 
# Raytrace 1:00 pm - 1:30 pm
# Injector tune for KLong, 1:30 pm - 5:30 pm, SRF cavity field emission test in SLinac, DAQ cal test plan, increase HV on two of the RF zones in SL.
+
# Injector tune for KLong, 1:30 pm - 5:30 pm, in parallel:
# BLA cal, high current push, 5:30 pm - 10:30 pm
+
## SRF cavity field emission test in SLinac
# KLONG test 10:30 pm 5:00 am (Hall C KLong and Hall A 40 μA CW)
+
## Cavity fast DAQ cal test in NLinac
 +
## Increase HV on two of the RF zones in SLinac
 +
# BLA calibration, high current push, 5:30 pm - 10:30 pm
 +
# KLong test 10:30 pm 5:00 am (Hall C KLong and Hall A 40 μA CW)
 
# QTSnyder 5:00 am - 7:00 am
 
# QTSnyder 5:00 am - 7:00 am

Latest revision as of 14:39, 15 May 2024

In person in MCC Conference Room and with Zoom.

https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam

--

Agenda:

  • Beam Studies, Sunday May 19th:
  1. BLM calibration, 8:00 am - 10:00 am, Hall A access (7 am)
  2. FFB/FF in Hall A, 25 µA and up, 10:00 am - 1:00 pm
  3. Raytrace 1:00 pm - 1:30 pm
  4. Injector tune for KLong, 1:30 pm - 5:30 pm, in parallel:
    1. SRF cavity field emission test in SLinac
    2. Cavity fast DAQ cal test in NLinac
    3. Increase HV on two of the RF zones in SLinac
  5. BLA calibration, high current push, 5:30 pm - 10:30 pm
  6. KLong test 10:30 pm 5:00 am (Hall C KLong and Hall A 40 μA CW)
  7. QTSnyder 5:00 am - 7:00 am