(Created page with "In person in MCC Conference Room and with Zoom. https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam -- '''Agenda:''' * '''Beam Study Results:''' # FFB/FF in Hal...")
 
 
Line 17: Line 17:
 
* '''Injector Upgrade Progress:'''  
 
* '''Injector Upgrade Progress:'''  
  
# New gun HV chamber installed, laser retro-reflection and gun alignment start on Monday
+
# New gun HV chamber aligned on laser path. Gun under vacuum this week. Gun bake next two weeks.
# All MFX solenoids were fixed: [[media:MFX_fix.jpg]]
+
# New RTP HV Driver passed EH&S review. Non-NRTL inspection is scheduled for this week
# New RTP HV Driver passed EH&S review. Non-NRTL inspection is scheduled for next this week
 
 
 
 
 
* '''MOLLER new rack in ISB - IN03B25''': [[media:IMG_1695.jpeg]]
 

Latest revision as of 08:07, 31 July 2024

In person in MCC Conference Room and with Zoom.

https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam

--

Agenda:

  • Beam Study Results:
  1. FFB/FF in Hall A:
    1. Hall A BPM signals from BSY have been restored in parity DAQ: [1]
    2. Check FFB ON versus OFF in QWeak data
    3. 2010 QWeak Data: [2]


  • Injector Upgrade Progress:
  1. New gun HV chamber aligned on laser path. Gun under vacuum this week. Gun bake next two weeks.
  2. New RTP HV Driver passed EH&S review. Non-NRTL inspection is scheduled for this week