ATLIS
+
===Useful Links===
* Carlos’ gun jobs (Save, 105 days) - [https://tasklists.jlab.org/atlis/tasks/111743 https://tasklists.jlab.org/atlis/tasks/111743]
 
* Matt’s, FX repair – (Save, 42 days?) [https://tasklists.jlab.org/atlis/tasks/110664 https://tasklists.jlab.org/atlis/tasks/110664]
 
* Riad’s RTP HV driver – (Save, 21 days) [https://tasklists.jlab.org/atlis/tasks/111742 https://tasklists.jlab.org/atlis/tasks/111742]
 
* Marcy’s degrader install – (Save, 250 days?) [https://tasklists.jlab.org/atlis/tasks/111706 https://tasklists.jlab.org/atlis/tasks/111706]
 
* (Save, 42 days?) [https://tasklists.jlab.org/atlis/tasks/110526 https://tasklists.jlab.org/atlis/tasks/110526]
 
* (Save, 210 days) Matt’s 5D [https://tasklists.jlab.org/atlis/tasks/111511 https://tasklists.jlab.org/atlis/tasks/111511]
 
* Laser XYZ<br  />
 
  
BSList
+
* Phase 1/2 upgrade - https://wiki.jlab.org/ciswiki/index.php/CEBAF_Injector_Upgrade
* (New) Yan’s commissioning - (176h) [https://tasklists.jlab.org/bslist/tasks/111504
+
* Ken's commissioning schedule - [[media:Inj Commissioning 2024 SAD_rev1.xlsx]]
https://tasklists.jlab.org/bslist/tasks/111504]
+
* [https://jeffersonlab.sharepoint.com/:p:/s/msteams_8f5bd4/ERPDRv67WeZChEiUtXxgoRwBcBp5CHQcu4LxwuVIXWZgzw?e=3LPY7K&nav=eyJzSWQiOjMyNSwiY0lkIjo0Nzc1NDU4MTR9&CID=3dc2b9b1-88fa-c64d-e690-3ff068ae1242 Shawn's restart plan]
* (New) Caryn’s (24h) PQB comprehensive - <a href="https://tasklists.jlab.org/bslist/tasks/109864">https://tasklists.jlab.org/bslist/tasks/109864</a>
+
 
* (New) Max’s R30-4 evaluation (8h) <a href="https://tasklists.jlab.org/bslist/tasks/111191">https://tasklists.jlab.org/bslist/tasks/111191</a>
+
===ATLIS Tasks===
* (New) Max’s FX optics (48h) - <a href="https://tasklists.jlab.org/bslist/tasks/109864">https://tasklists.jlab.org/bslist/tasks/109864</a>
+
 
* (Approved) Riad’s Wien E/B (8h) - <a href="https://tasklists.jlab.org/bslist/tasks/108388">https://tasklists.jlab.org/bslist/tasks/108388</a>
+
* Completed by Max (8/13/24) => Upgrade Mott DAQ VME - https://tasklists.jlab.org/atlis/tasks/111877
* (Approved) Riad’s spin dance (24h) - <a href="https://tasklists.jlab.org/bslist/tasks/108389">https://tasklists.jlab.org/bslist/tasks/108389</a>
+
* Complete by Matt (8/26/24) => FX repair – https://tasklists.jlab.org/atlis/tasks/110664
 +
* Complete by Carlos (9/3/24) => R30-4 gun installation - https://tasklists.jlab.org/atlis/tasks/111743
 +
* Marcy's (last 10/16) => Degrader segment installation - https://tasklists.jlab.org/atlis/tasks/111706
 +
* Matt's (last 9/4) => Irradiation - https://tasklists.jlab.org/atlis/tasks/111511 (5/13/24 - no ePAS yet)
 +
* Shukui's (last 5/21) => Upgrade power meter - https://tasklists.jlab.org/atlis/tasks/111773
 +
* Shukui's (last 5/21) => TMG and SHG PM - https://tasklists.jlab.org/atlis/tasks/111769
 +
* Riad's (last 4/17) => RTP driver - https://tasklists.jlab.org/atlis/tasks/111742
 +
 
 +
===BSList Tasks===
 +
====Injector Characterization and Setup====
 +
 
 +
* Yan's (14 shift?) => 2024 SAD Injector Commissioning - https://tasklists.jlab.org/atlis/tasks/111504
 +
* Ken's (2 shift) => Chopper1 and 2 Set Up: https://tasklists.jlab.org/bslist/tasks/113340
 +
* Ken's (1/2 shift) => Test Procedure steering beam to Pcup: https://tasklists.jlab.org/bslist/tasks/113337
 +
* Ken's (1/2 shift) => Test Procedure to FC1/1D: https://tasklists.jlab.org/bslist/tasks/113349
 +
* Ken's (1 shift) => Test Procedure to FC2: https://tasklists.jlab.org/bslist/tasks/113350
 +
* Ken's (1 shift) => Test Procedure to ILD: https://tasklists.jlab.org/bslist/tasks/113404
 +
* Dennis' (3h) => YAG vs. Harp - https://tasklists.jlab.org/bslist/tasks/24275
 +
* Dennis' (3h) => multiwire emittance - https://tasklists.jlab.org/bslist/tasks/113343
 +
 
 +
====Optics evaluations====
 +
 
 +
* Max’s (1h) => R30-4 evaluation – https://tasklists.jlab.org/bslist/tasks/111191
 +
* Max’s (1 shift) => FX optics - https://tasklists.jlab.org/bslist/tasks/109864
 +
* Alicia's (2h) => FOpts - https://tasklists.jlab.org/bslist/tasks/111605
 +
* Dennis' (2 shift) => Wien Filter Optics - https://tasklists.jlab.org/bslist/tasks/107364
 +
* Max's (5 shifts) => Booster evaluation - https://tasklists.jlab.org/bslist/tasks/113860
 +
* Max's (1/2 shift) => A2 backscattering test - https://tasklists.jlab.org/bslist/tasks/112187
 +
 
 +
====Spin calibration and PQB====
 +
 
 +
* Max's (???) => Mott DAQ with beam checkout - TODO: need to commission new DAQ vs. old data
 +
* Riad’s (1 shift) => Wien E/B @ 200 kV - https://tasklists.jlab.org/bslist/tasks/108388
 +
* Riad’s (3 shift) => Wien spin cal @ 200 keV) - https://tasklists.jlab.org/bslist/tasks/108389
 +
* Caryn’s (6? shift) => PQB comprehensive - https://tasklists.jlab.org/bslist/tasks/109864
 +
* Caryn's (2h) => Pre-check on transmission and helicity pickup to FC2 - https://tasklists.jlab.org/bslist/tasks/113334
 +
* Caryn's (3? shift) => PQB comprehensive to ILD - https://tasklists.jlab.org/bslist/tasks/110921
 +
 
 +
====Degrader====
 +
 
 +
* Dennis' (2 shift) => Degrader checkout and commissioning - https://tasklists.jlab.org/bslist/tasks/111105
 +
 
 +
====Target Irradiation====
 +
 
 +
* Alicia's (8 shift) => Target irradiation line check out and commissioning - https://tasklists.jlab.org/bslist/tasks/113763
 +
 
 +
===Toolbox Meetings===
 +
 
 +
* Daily Toolbox after MCC mtg - Bldg. 87 Rm 101
 +
 
 +
====Round 1====
 +
 
 +
** May 17-24 - Marcy
 +
** May 24-31 - Carlos
 +
** May 31-Jun 7 - Riad
 +
** Jun 7-14 - Mamun
 +
** Jun 14-21 - Gabriel
 +
** Jun 21-28 - Max
 +
** June 28-Jul 5 - Joe
 +
 
 +
====Round 2====
 +
 
 +
****** Jul 5-12 - Marcy
 +
****** Jul 12-19 - Carlos
 +
****** Jul 19-26 - Riad
 +
****** July 26-Aug 2 - Mamun
 +
****** Aug 2-9 - Gabriel
 +
****** Aug 9-16 - Max
 +
****** Aug 16-23 - Joe
 +
 
 +
====Round 3====
 +
 
 +
**************** Aug 23-30 - Marcy
 +
**************** Aug 30-Sep 6 - Carlos
 +
**************** Sep 6-13 - Riad
 +
**************** Sep 13-20 - Mamun
 +
**************** Sep 20-27 - Gabriel
 +
**************** Sep 27 - Oct 4 - Max
 +
**************** Oct 4 - 11 - Joe
 +
 
 +
====Round 4====
 +
 
 +
************************************ Oct 11-18- Marcy
 +
************************************ Oct 18-25 - Carlos
 +
************************************ Oct 25-Nov 1 - Riad
 +
************************************ Nov 1-8 - Mamun
 +
************************************ Nov 8-15 - Gabriel
 +
************************************ Nov 15-22 - Max
 +
 
 +
We should be back to on-call by this time...
 +
 
 +
sharepoint folder with schedules and pptx: https://jeffersonlab.sharepoint.com/sites/CIS/CIS%20Documents/Forms/AllItems.aspx?id=%2Fsites%2FCIS%2FCIS%20Documents%2FPhotoguns%2FR30%2D4%20corrected%20beam%20focal%20length%2FSchedule%20and%20procedures&viewid=9869a715%2D47e0%2D4c6f%2D9087%2Dc95744a725d1

Latest revision as of 13:54, 18 October 2024

Useful Links

ATLIS Tasks

BSList Tasks

Injector Characterization and Setup

Optics evaluations

Spin calibration and PQB

Degrader

Target Irradiation

Toolbox Meetings

  • Daily Toolbox after MCC mtg - Bldg. 87 Rm 101

Round 1

    • May 17-24 - Marcy
    • May 24-31 - Carlos
    • May 31-Jun 7 - Riad
    • Jun 7-14 - Mamun
    • Jun 14-21 - Gabriel
    • Jun 21-28 - Max
    • June 28-Jul 5 - Joe

Round 2

            • Jul 5-12 - Marcy
            • Jul 12-19 - Carlos
            • Jul 19-26 - Riad
            • July 26-Aug 2 - Mamun
            • Aug 2-9 - Gabriel
            • Aug 9-16 - Max
            • Aug 16-23 - Joe

Round 3

                                • Aug 23-30 - Marcy
                                • Aug 30-Sep 6 - Carlos
                                • Sep 6-13 - Riad
                                • Sep 13-20 - Mamun
                                • Sep 20-27 - Gabriel
                                • Sep 27 - Oct 4 - Max
                                • Oct 4 - 11 - Joe

Round 4

                                                                        • Oct 11-18- Marcy
                                                                        • Oct 18-25 - Carlos
                                                                        • Oct 25-Nov 1 - Riad
                                                                        • Nov 1-8 - Mamun
                                                                        • Nov 8-15 - Gabriel
                                                                        • Nov 15-22 - Max

We should be back to on-call by this time...

sharepoint folder with schedules and pptx: https://jeffersonlab.sharepoint.com/sites/CIS/CIS%20Documents/Forms/AllItems.aspx?id=%2Fsites%2FCIS%2FCIS%20Documents%2FPhotoguns%2FR30%2D4%20corrected%20beam%20focal%20length%2FSchedule%20and%20procedures&viewid=9869a715%2D47e0%2D4c6f%2D9087%2Dc95744a725d1