Line 26: | Line 26: | ||
# Plan to measure temperature gradient across the glass cell. | # Plan to measure temperature gradient across the glass cell. | ||
# Regarding CO<sub>2</sub>: it is possible to suppress the <sup>12</sup>C(γ,α)2α signal but <sup>13</sup>C(γ,n)<sup>12</sup>C background will be significant - Not an option. | # Regarding CO<sub>2</sub>: it is possible to suppress the <sup>12</sup>C(γ,α)2α signal but <sup>13</sup>C(γ,n)<sup>12</sup>C background will be significant - Not an option. | ||
+ | # Test chamber with C<sub>2</sub>F<sub>6</sub> as the super heated liquid. | ||
* Schedule: | * Schedule: | ||
− | # | + | # Reconfigure bubble chamber beamline in the first two weeks of July. |
+ | # Chamber arrives JLab in middle of July. Move to Injector. Install and align. | ||
+ | # Mercury we be installed in chamber at Argonne. | ||
+ | # Brad arrives on August 3. Cool and pressurize. Complete safety reviews. | ||
+ | # Beam on chamber in the second week of August. |
Revision as of 17:20, 3 June 2015
We will meet in TL 2221 on Wednesday June 3 at 3:30 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
1- Bubble Chamber progress at Argonne
2- Detection features of new bubble chamber: media:Detection_features_new_bubble_chamber.pdf
Notes from this meeting:
- Bubble Chamber:
- Showed bubbles distribution from N2O with mercury as buffer liquid using PuC neutron source.
- Plan to measure temperature gradient across the glass cell.
- Regarding CO2: it is possible to suppress the 12C(γ,α)2α signal but 13C(γ,n)12C background will be significant - Not an option.
- Test chamber with C2F6 as the super heated liquid.
- Schedule:
- Reconfigure bubble chamber beamline in the first two weeks of July.
- Chamber arrives JLab in middle of July. Move to Injector. Install and align.
- Mercury we be installed in chamber at Argonne.
- Brad arrives on August 3. Cool and pressurize. Complete safety reviews.
- Beam on chamber in the second week of August.