# Tue, August 11: Turn on gun, commission new lasers, beam to FC1 (Joe Grames).
 
# Tue, August 11: Turn on gun, commission new lasers, beam to FC1 (Joe Grames).

Revision as of 14:53, 6 September 2015

Run Plan

  • This is a test of 5D line, the chamber is off.
  1. Tue, August 11: Turn on gun, commission new lasers, beam to FC1 (Joe Grames).
  2. Wed, August 12: Beam to FC2 and 5D dump (Yan, Riad).
  3. Thursday, August 13: Check beam optics to 5D (Chris). Measure beam charge (Riad).
  4. Friday, August 14: Mott and photocathode Analyzing power (Joe ,Riad).
  5. Saturday, August 15: Find maximum energy and measure beam energy (Jay, Riad).