Difference between revisions of "Bubble Chamber Beam Test August 2015"
Jump to navigation
Jump to search
Line 1: | Line 1: | ||
= '''Run Plan''' = | = '''Run Plan''' = | ||
− | + | * '''This is a test of 5D line, the chamber is off.''' | |
# Tue, August 11: Turn on gun, commission new lasers, beam to FC1 (Joe Grames). | # Tue, August 11: Turn on gun, commission new lasers, beam to FC1 (Joe Grames). |
Revision as of 14:53, 6 September 2015
Run Plan
- This is a test of 5D line, the chamber is off.
- Tue, August 11: Turn on gun, commission new lasers, beam to FC1 (Joe Grames).
- Wed, August 12: Beam to FC2 and 5D dump (Yan, Riad).
- Thursday, August 13: Check beam optics to 5D (Chris). Measure beam charge (Riad).
- Friday, August 14: Mott and photocathode Analyzing power (Joe ,Riad).
- Saturday, August 15: Find maximum energy and measure beam energy (Jay, Riad).