* Emittance Measurements with large laser size (rms=0.423mm) - Yan
+
* Emittance Measurements with large laser size (rms=0.423mm) - Yan: [https://logbooks/entry/3482539]
  
  
Line 11: Line 11:
 
## Replace leaky vent valve
 
## Replace leaky vent valve
 
## Replace bad ion pump
 
## Replace bad ion pump
 +
# Next Shutdown – December 2017:
 +
## Install TE011 cavity

Latest revision as of 09:18, 28 August 2017

  • Emittance Measurements with large laser size (rms=0.423mm) - Yan: [1]


  • New plan:
  1. Finish emittance measurements, including a larger laser size (x4) – August 21-25
  2. Attempt 5 mA (non-magnetized, then magnetized) – August 28-31
  3. Shutdown – September 5:
    1. Install new YAG screen at viewer 3
    2. Fix existing harp and install 20 µm tungsten wire
    3. Add a new CEBAF-style harp with 10 µm tungsten wire (i.e, GTS will have two harps)
    4. Replace leaky vent valve
    5. Replace bad ion pump
  4. Next Shutdown – December 2017:
    1. Install TE011 cavity