Line 7: | Line 7: | ||
# Remove Faraday Cup | # Remove Faraday Cup | ||
# Remove bellow upstream of dump | # Remove bellow upstream of dump | ||
+ | # Remove LDR Harp arm and replace with ion-pump | ||
# Install TE011 Cavity | # Install TE011 Cavity | ||
# Install Deflecting Cavity | # Install Deflecting Cavity | ||
Line 12: | Line 13: | ||
# Move DP can 1 to end of beamline | # Move DP can 1 to end of beamline | ||
# All bellows at least 2.5 inch diameter | # All bellows at least 2.5 inch diameter | ||
+ | # Both gate valves are 2.5 inch-bore and will remain on beamline | ||
+ | |||
+ | |||
+ | * Remove gain-switched laser from GTS to Lab 6 | ||
Line 17: | Line 22: | ||
# Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses | # Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses | ||
# Add 5th solenoid to magnet screen | # Add 5th solenoid to magnet screen | ||
+ | |||
+ | |||
+ | * Modification to HV and Preparation chambers: | ||
+ | # Upgrade anode HV bias feed-through to 5 kV | ||
+ | # Remove anode and clean melted spot | ||
+ | # Fix Transverse Manipulator | ||
+ | # Fix Sb boat | ||
+ | # Clean Sb pellets off chamber |
Latest revision as of 09:15, 28 January 2019
- List of beamline hardware modifications:
- Replace YAG screen on Viewer 1
- Replace Slit on Viewer 2 with holes assembly
- Replace two ion collectors with new ones
- Replace Harp fork (Tony)
- Remove modified DP can
- Remove Faraday Cup
- Remove bellow upstream of dump
- Remove LDR Harp arm and replace with ion-pump
- Install TE011 Cavity
- Install Deflecting Cavity
- Install new 5th solenoid
- Move DP can 1 to end of beamline
- All bellows at least 2.5 inch diameter
- Both gate valves are 2.5 inch-bore and will remain on beamline
- Remove gain-switched laser from GTS to Lab 6
- List of software and controls changes:
- Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses
- Add 5th solenoid to magnet screen
- Modification to HV and Preparation chambers:
- Upgrade anode HV bias feed-through to 5 kV
- Remove anode and clean melted spot
- Fix Transverse Manipulator
- Fix Sb boat
- Clean Sb pellets off chamber