Difference between revisions of "GTS meeting 1 14 19"
Jump to navigation
Jump to search
(14 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
− | + | = '''List of beamline hardware modifications''' = | |
# Replace YAG screen on Viewer 1 - '''''Done''''' | # Replace YAG screen on Viewer 1 - '''''Done''''' | ||
# Replace Slit on Viewer 2 with holes assembly - '''''Done''''' | # Replace Slit on Viewer 2 with holes assembly - '''''Done''''' | ||
Line 9: | Line 9: | ||
# Remove LDR Harp arm and replace with ion-pump | # Remove LDR Harp arm and replace with ion-pump | ||
# Install TE011 Cavity | # Install TE011 Cavity | ||
− | # Install Deflecting Cavity | + | # Install Deflecting Cavity - '''''Done''''' |
# Install new 5th solenoid | # Install new 5th solenoid | ||
− | # Move DP can 1 to end of beamline | + | # Move DP can 1 to end of beamline - '''''Done''''' |
− | # All bellows at least 2.5 inch diameter | + | # All bellows at least 2.5 inch diameter - '''''Done''''' |
− | # Both gate valves are 2.5 inch-bore and will remain on beamline | + | # Both gate valves are 2.5 inch-bore and will remain on beamline - '''''Done''''' |
− | + | = '''List of hardware support''' = | |
− | # Deflecting Cavity power supply, MO and other parts | + | # Install Deflecting Cavity power supply, MO and other parts |
+ | # Install TE011 Cavity readout cable and electronics | ||
− | + | = ''' List of software and controls changes''' = | |
# Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses | # Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses | ||
# Add 5th solenoid to magnet screen | # Add 5th solenoid to magnet screen | ||
− | + | = ''' Remove gain-switched laser from GTS to Lab 6''' = | |
+ | |||
+ | |||
+ | = ''' Install Brock's Magnetometer Cavity''' = | ||
+ | |||
+ | |||
+ | = ''' Modification to HV and Preparation chambers''' = | ||
# Upgrade anode HV bias feed-through to 5 kV | # Upgrade anode HV bias feed-through to 5 kV | ||
# Remove anode and clean melted spot | # Remove anode and clean melted spot | ||
# Fix Transverse Manipulator | # Fix Transverse Manipulator | ||
# Fix Sb boat | # Fix Sb boat | ||
− | # Clean | + | # Clean Sb pellets off chamber |
− | + | = ''' Install BNL high bunch laser''' = |
Latest revision as of 09:14, 28 January 2019
List of beamline hardware modifications
- Replace YAG screen on Viewer 1 - Done
- Replace Slit on Viewer 2 with holes assembly - Done
- Replace two ion collectors with new ones
- Replace Harp fork (Tony)
- Remove modified DP can - Done
- Remove Faraday Cup - Done
- Remove bellow upstream of dump - Done
- Remove LDR Harp arm and replace with ion-pump
- Install TE011 Cavity
- Install Deflecting Cavity - Done
- Install new 5th solenoid
- Move DP can 1 to end of beamline - Done
- All bellows at least 2.5 inch diameter - Done
- Both gate valves are 2.5 inch-bore and will remain on beamline - Done
List of hardware support
- Install Deflecting Cavity power supply, MO and other parts
- Install TE011 Cavity readout cable and electronics
List of software and controls changes
- Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses
- Add 5th solenoid to magnet screen
Remove gain-switched laser from GTS to Lab 6
Install Brock's Magnetometer Cavity
Modification to HV and Preparation chambers
- Upgrade anode HV bias feed-through to 5 kV
- Remove anode and clean melted spot
- Fix Transverse Manipulator
- Fix Sb boat
- Clean Sb pellets off chamber