− | Andy's proposed run plan, the hard part is scheduling this work before May 2020: | + | (this page was updated November 7, 2019) |
+ | |||
+ | Andy's proposed run plan, the hard part is scheduling this work before May 2020. And lots of rooftop manipulations: | ||
{| class="wikitable" style="text-align: center; color: green;" | {| class="wikitable" style="text-align: center; color: green;" | ||
|Run# | |Run# | ||
+ | |X | ||
+ | |0 | ||
|1 | |1 | ||
|2 | |2 | ||
Line 9: | Line 13: | ||
|- | |- | ||
|Objective | |Objective | ||
− | |Empty Target | + | |IBC installation |
+ | |Booster Commissioning | ||
+ | |Aperture target/Empty Target | ||
|Unpolarized Target | |Unpolarized Target | ||
|Polarized Target | |Polarized Target | ||
Line 15: | Line 21: | ||
|- | |- | ||
|Tiles OFF and ON sequence | |Tiles OFF and ON sequence | ||
+ | |OFF/ON | ||
+ | |not required | ||
|OFF/ON | |OFF/ON | ||
|OFF/ON/OFF/ON | |OFF/ON/OFF/ON | ||
Line 21: | Line 29: | ||
|- | |- | ||
|# times Neil visits the rooftop | |# times Neil visits the rooftop | ||
+ | |2 (done) | ||
+ | |0 | ||
|2 | |2 | ||
|4 | |4 |
Latest revision as of 15:19, 7 November 2019
(this page was updated November 7, 2019)
Andy's proposed run plan, the hard part is scheduling this work before May 2020. And lots of rooftop manipulations:
Run# | X | 0 | 1 | 2 | 3 | 4 |
Objective | IBC installation | Booster Commissioning | Aperture target/Empty Target | Unpolarized Target | Polarized Target | Polarized Target |
Tiles OFF and ON sequence | OFF/ON | not required | OFF/ON | OFF/ON/OFF/ON | OFF/ON/OFF/ON/OFF/ON | OFF/ON/OFF/ON/OFF/ON |
# times Neil visits the rooftop | 2 (done) | 0 | 2 | 4 | 6 | 6 |