Difference between revisions of "Sep 03, 2020"
Jump to navigation
Jump to search
(One intermediate revision by the same user not shown) | |||
Line 4: | Line 4: | ||
; LERF | ; LERF | ||
+ | : Sep 2 schedule [[media:WAG LERF Schedule Sept 2.docx]] | ||
+ | : Punchlist [[media:200902_August LERF punchlist.docx]] | ||
: power outage | : power outage | ||
: gun status | : gun status |
Latest revision as of 08:59, 2 September 2020
- CEBAF
- On-call
- QE/charge lifetime
- LERF
- Sep 2 schedule media:WAG LERF Schedule Sept 2.docx
- Punchlist media:200902_August LERF punchlist.docx
- power outage
- gun status
- laser status
- UITF
- UITF operations approved, Run 1 started
- Booster => after 7-cell calibration => making 9.5 MeV/c
- GTS
- Student updates
- AIPINJ
- CIS work plans