Difference between revisions of "CIS Phase 1 work plans"

From Ciswikidb
Jump to navigation Jump to search
 
(953 intermediate revisions by 2 users not shown)
Line 1: Line 1:
=== Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups ===
+
;5/21/21 AIPINJ Phase I Installation and HCO Complete.
 +
 
 +
=2020 Weeks 1 through 13 =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
== Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups ==
 +
<div class="mw-collapsible mw-collapsed">
 
* Updated schedule [[media:200914_AIPINJ_Weeks_Sep_18_update.docx]]
 
* Updated schedule [[media:200914_AIPINJ_Weeks_Sep_18_update.docx]]
 
* High voltage test slides [[media:200902_HV_Plans.pptx]]
 
* High voltage test slides [[media:200902_HV_Plans.pptx]]
 
* Gun and Wien tasks [[Media:High Voltage Work Gun2 & Wien filters.xlsx]]
 
* Gun and Wien tasks [[Media:High Voltage Work Gun2 & Wien filters.xlsx]]
 +
</div>
  
=== Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects ===
+
== Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects ==
 
+
<div class="mw-collapsible mw-collapsed">
 
; Fri 9/25 - Mon 9/28
 
; Fri 9/25 - Mon 9/28
 
* CIS Gun Jobs
 
* CIS Gun Jobs
Line 65: Line 72:
 
* Pump-down vacuum in front of tee for next week (CIS)  
 
* Pump-down vacuum in front of tee for next week (CIS)  
  
; [[Tue 9/29 – Fri 10/1 Table]]
+
; <u>'''Tunnel Work'''</u>
 +
 
 +
{| class="wikitable"
 +
|-
 +
! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2
 +
|-
 +
| 4a - 8a ||  || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher || I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps || I&C: Norris: Viewer disconnects
 +
|-
 +
| 8a - 10a || CIS + SSG || RadCon: rad probes || SSG: Kicker magnet removal; CIS: Tiny magnet removals || CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru || S&A: Gun
 +
|-
 +
| 10a - 12p || CIS + SSG || DC Power || DC Power: Wire wrap-ups, junction box investigation  ||  || S&A: Gun; SSG: Kicker cable tie-up
 +
|-
 +
| 12p - 2p || CIS + SSG || DC Power || DC Power: Wire wrap-ups, junction box investigation || DC Power || S&A: Gun
 +
|-
 +
| 2p - 4p || CIS + SSG || DC Power || 3p: Moser: Safety Warden checks  ||  || S&A: Gun
 +
|-
 +
| 4p - ?? ||  ||  ||  ||  ||
 +
|}
 +
 
 +
; <u>'''Other Work Occurring When Convenient'''</u>
 +
* Remove suitcase, Tunnel (CIS)
 +
* Harp upgrade, InjSB (I&C)
 +
* ODH Head Replacement, InjSB and Tunnel (SSG)
 +
* PSS Chassis Removals, InjSB (SSG)
 +
 
 +
</div>
  
=== Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network ===
+
== Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network ==
 +
<div class="mw-collapsible mw-collapsed">
 
; Monday Oct 5  
 
; Monday Oct 5  
 
* vacuum tests, disconnects, and pre-removal blank offs (CIS)
 
* vacuum tests, disconnects, and pre-removal blank offs (CIS)
Line 79: Line 112:
 
* Stage/prepare for craning our girders (Mech Install)
 
* Stage/prepare for craning our girders (Mech Install)
 
* Chopper SSA upgrade -- LCW line install, InjSB (Mech Install / RF)
 
* Chopper SSA upgrade -- LCW line install, InjSB (Mech Install / RF)
 +
 +
; Wednesday Oct 7
 +
* S&H cable work for iocinse4, InjSB (Francis)
 +
* Chopper SSA upgrade, InjSB (Farrish)
 +
* Wein PS Work, InjSB (Windham)
 +
* VIP UHV PS Work, InjSB (Windham)
 +
* Harp PC104 upgrade, InjSB (Dela Cruz)
 +
 +
; Thursday Oct 8
 +
* BPM work, InjSB (Francis)
 +
* Chopper SSA upgrade, InjSB (Farrish)
 +
* Harp PC104 upgrade, InjSB (Dela Cruz)
  
 
; Wednesday Oct 7 and Thursday Oct 8 -- Mechanical Install
 
; Wednesday Oct 7 and Thursday Oct 8 -- Mechanical Install
Line 95: Line 140:
 
* 25ft from floor of InjSB to elevated Inj tunnel cable tray
 
* 25ft from floor of InjSB to elevated Inj tunnel cable tray
  
=== Week 4 (Oct 12 - Oct 18) ===
+
; Friday Oct 9
 +
* BPM Work, InjSB (Francis)
 +
* Chopper SSA upgrade, InjSB (Farrish)
 +
* Harp PC104 upgrade, InjSB (Dela Cruz)
 +
* Penetration stone drop -- 57, 86, 108, Tunnel (Mech Install)
 +
** Penetration above laser hut already opened
 +
 
 +
</div>
 +
 
 +
== Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild ==
 +
<div class="mw-collapsible mw-collapsed">
 +
* Laser/Y-Chamber viewer for Y-chamber girder (Marcy)
 +
* Fiducializing Y-chamber girder (S&A)
 +
* Laser window under vacuum evaluations (Phil/Shukui/Caryn)
 +
* Documenting early InjSB racks (Scott)
 +
* Cable pulls through penetrations (EES)
 +
* <strike> Fire pipe demolition? </strike> (Facilities Contractor)
 +
* Wein upgrade (Carlos) --
 +
** Finish new Wien electrodes drawing and sign-offs
 +
** Vacuum chambers to machine shop for mods
 +
** Begin creating new screens
 +
* [[Tunnel Photos Oct14 2020|Injector Tunnel Photos]] from W 10/14
 +
 
 +
 
 +
; Monday Oct 12
 +
Tunnel --
 +
* Hooking up VIPs to new 18V PS for load testing (Marcy/Scott)
 +
* Cable pulls through penetrations (EES)
 +
 
 +
InjSB --
 +
* BPM Cable Pulls through Penetration 86 (Francis)
 +
* Chopper SSA upgrade (Farrish)
 +
* Harp to PC104 upgrade (Dela Cruz)
 +
* Early rack documentation and space optimization (Scott)
 +
* PSS Upgrade work (IN02BNI, B29, B30) (SSG)
 +
 
 +
 
 +
; Tuesday Oct 13
 +
Tunnel --
 +
* Cable pulls through penetrations (EES)
 +
* Resistor box evaluation (Coleman)
 +
 
 +
InjSB --
 +
* BPM Work, IN02B{*} (Francis)
 +
* Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
 +
* Harp to PC104 upgrade, IN03B07  (Dela Cruz)
 +
* Early rack documentation and space optimization, IN01B{02-05} (Scott)
 +
* PSS Upgrade, IN02{BNI, B29, B30} (SSG)
 +
 
 +
 
 +
; Wednesday Oct 14
 +
Tunnel --
 +
* Cable pulls through penetrations (EES)
 +
* Safety warden walk-through (Moser)
 +
 
 +
InjSB --
 +
* BPM Work, IN02B{*} (Francis)
 +
* Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
 +
* Harp to PC104 upgrade, IN03B07  (Dela Cruz)
 +
* Early rack documentation and space optimization, IN01B{02-05} (Scott)
 +
* PSS Upgrade, IN02{BNI, B29, B30} (SSG)
 +
* Determining rack location for Wien magnet PSs, IN02-middle (Coleman, Grames, Moser) 
 +
* Safety warden walk-through (Moser)
 +
* Conduit in penetration 135 (Electricians)
 +
 
 +
 
 +
; Thursday Oct 15
 +
Tunnel --
 +
* S&A Level surveys
 +
 
 +
InjSB --
 +
* BPM Work, IN0{2,3}B{*} (Francis)
 +
* Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
 +
* Harp to PC104 upgrade, IN03B07  (Dela Cruz)
 +
* Early rack documentation and space optimization, IN01B{02-05} (Scott)
 +
* PSS Upgrade, IN02{BNI, B29, B30} (SSG)
 +
* 20A PS Install, Rack re-org, IN02B22 (DC Power)
 +
 
 +
; Friday Oct 16
 +
Tunnel --
 +
* Cable pulls through penetrations (EES)
 +
* Mott cable removals (Scott/Riad, EES)
 +
 
 +
InjSB --
 +
* Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
 +
* Harp to PC104 upgrade, IN03B07  (Dela Cruz)
 +
* Early rack documentation and space optimization, IN01B{02-05} (Scott)
 +
* PSS Upgrade, IN02{BNI, B29, B30} (SSG)
 +
* 20A PS Install, Rack re-org, IN02B22 (DC Power)
 +
* IN02B26 Power Lock-Out, ~915a (DC Power)
 +
 
 +
</div>
 +
 
 +
== Week 5 (Oct 19 - Oct 23)  Prep for Gun to Y Vacuum Installation ==
 +
<div class="mw-collapsible mw-collapsed">
 +
;Non-Tunnel Work
 +
* Build new Y-chamber viewer =>  '''Y-built w/test screen, Laser being built.'''
 +
* Use test screen + laser + S&A to verify position of first viewer => '''This week'''
 +
* Install + align + vacuum seal (2) viewers => '''target this week'''
 +
* Caryn will confirm but identified best ‘mushroom’ window, attach => '''done'''
 +
* ME provide ALL points to S&A for installation (gun table, 2I stand, Y-chamber, 2 peds for Wien, 2 peds A1/A2) => '''???'''
 +
* Carlos' Wien-mania!
 +
 
 +
;Tunnel Work
 +
* Complete remove old keV Mott cables => '''done'''
 +
* Complete remove old gun HV cables => '''done'''
 +
* Jim pulls Wien PS cables? => '''done'''
 +
* Does Wien HV cable pull start? => '''starting this week'''
 +
* Scott will finish tie back of cables on tunnel floor to cable tray => '''done'''
 +
* Refill 86? => '''no, not yet'''
 +
 
 +
; Standing Injector Service Building Work 
 +
* BPM Work, IN0{2,3}B{*} (Francis)
 +
* Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
 +
* Harp to PC104 upgrade, IN03B07  (Dela Cruz)
 +
* Early rack documentation and space optimization, IN01B{02-05} (Scott)
 +
* PSS Upgrade, IN02{BNI, B29, B30} (SSG)
 +
* 20A PS Install, Rack re-org, IN02B22 (DC Power)
 +
 
 +
; Monday Oct 19
 +
Tunnel --
 +
* Cryo u-tube pulls for 0L0{2,3,4}
 +
 
 +
; Tuesday Oct 20
 +
Tunnel --
 +
* Cable pulls and removals
 +
 
 +
InjSB --
 +
* BPM Work, IN0{2,3}B{*} (Francis)
 +
* Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
 +
* Harp to PC104 upgrade, IN03B07  (Dela Cruz)
 +
* Early rack documentation and space optimization, IN01B{02-05} (Scott)
 +
* PSS Upgrade, IN02{BNI, B29, B30} (SSG)
 +
* 20A PS Install, IN02B22, 2p - 4p (DC Power)
 +
 
 +
; Wednesday Oct 21
 +
Tunnel --
 +
* S&A Verify line with new control
 +
 
 +
InjSB --
 +
* PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
 +
* Viewer work, IN03B07, 6a - 9a (Norris)
 +
* Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
 +
* M56 Hardware Removal from IN02B22, (I&C)
 +
 
 +
 
 +
; Thursday Oct 22
 +
InjSB --
 +
* Wien Magnet PS Install, IN02B22, afternoon (DC Power)
 +
* Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
 +
* PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
 +
* Viewer work, IN03B07, 6a - 9a (Norris)
 +
* Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
 +
 
 +
 
 +
; Friday Oct 23
 +
Tunnel --
 +
* Vacuum work clean room craned in 6a - 8a (Mech Install)
 +
* Clean room setup and prepping (Marcy)
 +
* Gun interlock checks in preparation of removal of old HV Interlock Chassis in IN01B02 (Windham, Grames)
 +
* Laser room work (Shukui)
 +
 
 +
InjSB --
 +
* Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
 +
* PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
 +
* Viewer work, IN03B07, 6a - 9a (Norris)
 +
* Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
 +
* 20A PS Install, IN02B22 (DC Power)
 +
 
 +
 
 +
<u>'''Inj Service Building Work'''</u>
 +
 
 +
[[File:InjSB Racks.png|1000px]]
 +
 
 +
{| class="wikitable"
 +
|-
 +
! Time !! Wed 10/21 !! Thu 10/22 !! Fri 10/23
 +
|-
 +
| 5a - 9a || Dela Cruz, Norris, <strike>Francis</strike> || Dela Cruz, Norris, <strike>Francis</strike> || Dela Cruz, Norris, <strike>Francis</strike>
 +
|-
 +
| 9a - 12p || <strike>Francis</strike>, SSG, <strike>Windham</strike> || <strike>Francis</strike>, SSG || <strike>Francis,</strike> SSG, Windham
 +
|-
 +
| 12p - 4p || DC Power, SSG, <strike>Windham, Francis</strike> || DC Power, SSG, Windham, <strike>Francis</strike>  || DC Power, SSG, Windham, <strike>Francis</strike>
 +
|}
 +
 
 +
</div>
 +
 
 +
== Week 6 (Oct 26 - Oct 30)  Remove old Y+NEG & Move Gun2 new location ==
 +
<div class="mw-collapsible mw-collapsed">
 +
;Tunnel work
 +
* Remove NEG filter from HV chamber ✅
 +
* Setup mobile cleanroom over HV chamber ✅
 +
* Vent Gun3 chamber to test Gun3 valve ✅
 +
* Vent Gun2 chamber to test Gun2 valve ✅
 +
* Remove 2I NEG beam line, remove NEG pedestal (temporarily) ✅
 +
* Replace 10” flange + SHV connector + blank off + pump down ✅
 +
* Prep Gun3 & Y-chamber for Install to remove ✅
 +
* Wrap up UHV ion pump power supply power tests ✅
 +
* INSTALL lift and move gun table off feet, & move Gun3 & Y-chamber back to TL-1137 ✅
 +
* S&A may start setting/checking points (gun feet, 2I ped, Y ped, Wien ped, A1/A2 ped) ✅
 +
 
 +
;Non-Tunnel Work
 +
* Finish Y-chamber : add viewers, add laser vacuum window, add NEG towers, add gun valve ''on-going''
 +
* Wien-mania! [[200kV Wien filter - FINAL | (high level schedule)]]
 +
::-Wien magnetic field mapping ''next couple weeks''
 +
::-Bubba assembles the fixtures ✅
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building Work'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|- style="background-color:#E6E6FA"
 +
! '''Location'''<br>Time !! Mon 10/26 !! Tue 10/27 !! Wed 10/28 !! Thu 10/29 !! Fri 10/30
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>5a - 9a || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis
 +
|-
 +
| '''Tunnel'''<br>5a - 9a ||  || ''Gun Vacuum Work'' || ''Gun Vacuum Work'' || Gun2 Table Move <br> Y-Chamber+Gun3 Removal ||
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>9a - 12p || Francis, SSG || Francis, Windham, SSG || Francis, Windham, SSG || Dela Cruz, Norris, Francis, SSG || Francis, SSG
 +
|-
 +
| '''Tunnel'''<br>9a - 12p || ''Gun Vacuum Work'' || ''Gun Vacuum Work'' || 9a CIS+MechInstall Walk-Thru || Wien Cable Pulls || Cryo 0L02 L-tube pull <br> Fire pipe walk thru <br> S&A Point Layouts
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>12p - 4p || SSG || Windham, SSG  || Windham, SSG <br> Trim Rack Checks || SSG ||  SSG
 +
|-
 +
| '''Tunnel'''<br>12p - 4p || ''Gun Vacuum Work'' || ''Gun Vacuum Work'' <br> 3p:Videographer Tour || || || S&A Point Layouts
 +
|}
 +
 
 +
[[File:InjSB Week6.png|1000px]]
 +
 
 +
 
 +
; Mon Oct 26
 +
Tunnel --
 +
* Gun vacuum work, 9a - 4p (CIS)
 +
 
 +
InjSB --
 +
* PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
 +
* Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
 +
* Viewer work, IN03B07, 6a - 9a (Norris)
 +
* BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
 +
* 20A Wien Magnet PS Install, IN02B22 (Coleman)
 +
* LLRF air temperature control system removal from IN01B13? (Plawski?)
 +
 
 +
; Tues Oct 27
 +
Tunnel --
 +
* Gun vacuum work, 9a - 3p (CIS)
 +
* Videographer Tour, 3p+ (K. Carter + two videographers)
 +
 
 +
InjSB --
 +
* PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
 +
* Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
 +
* Viewer work, IN03B07, 6a - 9a (Norris)
 +
* BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
 +
* CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
 +
* 20A Wien Magnet PS Install, IN02B22 (Coleman)
 +
* Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
 +
* LLRF air temperature control system removal from IN01B13? (Plawski?)
 +
 
 +
; Wed Oct 28
 +
Tunnel --
 +
* CIS + MechInstall Walk-Through of Gun Table Move, Removal of Gun3 stub and Y-chamber, 9a
 +
 
 +
InjSB --
 +
* PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
 +
* Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
 +
* Viewer work, IN03B07, 6a - 9a (Norris)
 +
* BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
 +
* CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
 +
* Trim Card Checks, IN02B{10+11+26} + IN04B10, 12p-1p (Richardson)
 +
Other Possible Work....
 +
* 20A Wien Magnet PS Install, IN02B22 (Coleman)
 +
* Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
 +
 
 +
 
 +
; Thur Oct 29
 +
Tunnel --
 +
* Gun2 move, 5a - 8a (Mech Install)
 +
* Removal of Gun3 and Y-chamber to Test Lab, 5a - 8a (Mech Install)
 +
* Wien HV and control cable pulls, 9a - 1p (Dela Cruz)
 +
 
 +
InjSB --
 +
* PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
 +
* Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
 +
* Viewer work, IN03B07, 6a - 1p (Norris)
 +
* BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
 +
Other possible work....
 +
* 20A Wien Magnet PS Install, IN02B22 (Coleman)
 +
* Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
 +
 
 +
; '''All Hallows' Eve ''Eve'' 👻''' (Fri 10/30)
 +
Tunnel --
 +
* Cryo L-tube Removal from 0L02, 8a - 12p (Cryo)
 +
* Fire pipe demo job walk-through, 12p (Grames, Suhring, Renzo)
 +
* Point Layouts, after cryo (S&A)
 +
 
 +
InjSB --
 +
* PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
 +
* Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
 +
* Viewer work, IN03B07, 6a - 1p (Norris)
 +
* BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
 +
Other possible work....
 +
* 20A Wien Magnet PS Install, IN02B22 (Coleman)
 +
* Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
 +
 
 +
</div>
 +
 
 +
== Week 7 (Nov 2 - Nov 6)  ==
 +
<div class="mw-collapsible mw-collapsed">
 +
'''Fire pipe removal, viewer design, modify existing pedestals, Wien filter mapping'''
 +
 
 +
;'''Tunnel work'''
 +
;Mon/Tue
 +
#INSTALL crane support (move Y-girder, Gun3 chamber, anything else back to TL1137)
 +
#CIS take opportunity to a) cover your stuff before fire pipe demo, b) clean up cabinets, toolbox
 +
#EES-IC Cable Pulls, Termination, and Routing
 +
;Wed/Thu and maybe Fri
 +
#Fire pipe demolition
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Complete Y-chamber: add viewers, add laser vacuum window, add NEG towers, add gun valve
 +
* Wien-mania! [[200kV Wien filter - FINAL | (high level schedule)]] => H/V-wien magnetic field mapping
 +
 
 +
;'''InjSB Work'''
 +
* Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
 +
** Comm chassis to digiport server
 +
* PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
 +
* Viewer work, IN03B0{6+7} (Norris)
 +
* BPM Work, IN03B{05-08, 23} (Francis)
 +
* CIS Rack Work, IN01B{00-05} (Windham)
 +
Other possible work...
 +
* 20A Wien Magnet PS Install (Coleman)
 +
* Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|- style="background-color:#C3C8D4"
 +
! '''Location'''<br>Time !! Mon 11/2 !! Tue 11/3 <br> Election Day 🇺🇸 !! Wed 11/4 !! Thu 11/5 !! Fri 11/6
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>5a - 9a || BPM, Viewer, Wien Work || BPM, Viewer, Wien Work || BPM, Viewer, Wien Work || BPM, Viewer, Wien Work || BPM, Viewer, Wien Work
 +
|-
 +
| '''Tunnel'''<br>5a - 9a || Wien + viewer cable pulls <br> INSTALL Crane Outs || Wien + viewer cable pulls || Fire pipe demo|| Fire pipe demo || F(riday)
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>9a - 12p || PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work || PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work
 +
|-
 +
| '''Tunnel'''<br>9a - 12p || Wien + viewer cable pulls || Wien + viewer cable pulls || Fire pipe demo || Fire pipe demo || F(loat)
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work
 +
|-
 +
| '''Tunnel'''<br>12p - 4p || M || T || Fire pipe demo || Fire pipe demo || F
 +
|}
 +
 
 +
[[File:InjSB Week7.png|1000px]]
 +
 
 +
</div>
 +
 
 +
== Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher ==
 +
<div class="mw-collapsible mw-collapsed">
 +
;'''Tunnel work'''
 +
# Tue - S&A is queued up to set new(er) gun foot pad points
 +
# Tue/Wed - Shaun predicts 4 pedestals arrive, Jenord inspects them; other peds exist in tunnel - thank you Phil/Shaun!
 +
# Wed/Thu/Fri - Install drills and drops anchors, prepare grout form?, maybe we return gun table (Tom, best guess for the fire pipe install?)
 +
 
 +
;'''ME work'''
 +
* S&A drop revised points for table base pads. ECD 11/10. '''done'''
 +
 
 +
* 2I solenoid –  '''done'''
 +
::SG print full size drill template for Neil.
 +
::Check fit of template.
 +
 
 +
* Neil – Drill holes into top of solenoid stand (existing item and is currently in place) using drill template provided by Shaun. '''done'''
 +
 
 +
* Neil drill anchor holes in floor '''done'''
 +
::HVC table base pads. '''done'''
 +
::Wien Girder Pedestals. '''done'''
 +
::Aperture Girder Pedestals. '''done'''
 +
::Details have been provided to Neil. '''done'''
 +
 
 +
* Y chamber girder
 +
::Design new v-block mounting for Y & ion pump due to angle change of Y.
 +
::Fabricate or modifications.
 +
 
 +
;'''Non-Tunnel Work'''
 +
# Wien-mania! [[200kV Wien filter - FINAL | (high level schedule)]] - Wien magnet mapping, HVPS system controls (ADC/DAC), Switchbox build
 +
# Complete Y-chamber build : laser window + (2) viewers + NEG Tower + Valve (gun3!?)
 +
# A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
 +
# Prebuncher vacuum repair, leak check
 +
::*Did the leak check braze joint happen?
 +
::*Did a final probe port length get decided?
 +
::*Can we resolve these question, repair the probe port, clean, ready for testing by Friday?
 +
# Submit PR for PSS kicker
 +
 
 +
;'''ISB Work'''
 +
# Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
 +
#* Wire HV PS
 +
#* Install Comm chassis
 +
# PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
 +
# Viewer upgrades, IN03B07 (Norris)
 +
# Harp upgrades, IN03B07 (Dela Cruz)
 +
# BPM Work, IN03B{05-08, 23} (Francis) Phase I: ✅; jump-start on Phase II ✅
 +
# CIS Rack Work, IN01B{00-05} (Windham)
 +
# Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
 +
# First Aid Cabinet re-stocks, back wall behind IN02B22ish + bottom of access stairs, (Occ Med + vendor), date TBD
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|- style="background-color:#C3C8D4"
 +
! '''Location'''<br>Time !! Mon 11/9 !! Tue 11/10 !! Wed 11/11 !! Thu 11/12 !! Fri 11/13
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>5a - 9a || BPM, Viewer, Wien Work || BPM, Viewer, Wien, Harp Work || BPM, Viewer, Wien, Harp Work || BPM, Viewer, Wien, Harp Work || Viewer, Wien, Harp Work
 +
|-
 +
| '''Tunnel'''<br>5a - 9a || Viewer Cable Pulls || T || INSTALL Pedestals, base pads, solenoid stand drilling || INSTALL work <br> Viewer Cable Pulls || S&A Survey Pedestals
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>9a - 12p || PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work || PSS Upgrade <br> BPM, Harp, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> BPM, Harp, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> BPM, Harp, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> Harp, Viewer, Wien Work <br> CIS Rack Work
 +
|-
 +
| '''Tunnel'''<br>9a - 12p || Viewer cable pulls || S&A Sets New(er) Points <br> DC Power Resistor Box Button-Up|| INSTALL Pedestals, base pads, solenoid stand drilling || Viewer Cable Pulls <br> 11a: Laser Safety System Audit || S&A Survey Pedestals
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work
 +
|-
 +
| '''Tunnel'''<br>12p - 4p || M || S&A Sets New(er) Points || Cable pulls? || R || S&A Survey Pedestals
 +
|}
 +
 
 +
[[File:InjSB Week8.png|1000px]]
 +
 
 +
</div>
 +
 
 +
== Week 9 (Nov 16 - Nov 20)  ==
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
# Continue preparing new Y-chamber
 +
# A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
 +
# Prebuncher -- RF testing/tuning
 +
# Wien-mania! [[200kV Wien filter - FINAL | (high level schedule)]] =>
 +
#* Review V-wien magnetic field mapping results and determine any remaining desired measurements
 +
#* Finish V-wien field mapping and move to horizontal
 +
#* Wien quad hardware arrivals?
 +
#* Install HV switcher chassis
 +
# 200kV PSS kicker fabrication
 +
 
 +
;'''Tunnel work '''
 +
# INSTALL grouts in pedestals (Mon/Tue) ''done?''
 +
# Fire pipe demo (Wed/Thur/Fri)
 +
 
 +
;'''ISB Work'''
 +
# Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
 +
# PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer)
 +
# Viewer upgrades, IN03B07 (Norris)
 +
# Harp upgrades, IN03B07 (Dela Cruz)
 +
# CIS Rack Work, IN01B{00-05} (Windham)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|- style="background-color:#C3C8D4"
 +
! '''Location'''<br>Time !! Mon 11/16 !! Tue 11/17 !! Wed 11/18 !! Thu 11/19 !! Fri 11/20
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>5a - 9a || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work
 +
|-
 +
| '''Tunnel'''<br>5a - 9a || INSTALL Grout pedestals || T || Fire pipe demo || Fire pipe demo || Lifting Plate Load Test
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>9a - 12p || Viewer, Harp, Wien Work <br> CIS Rack Work || Viewer, Harp, Wien Work <br> CIS Rack Work|| Harp, Viewer, Wien Work <br> CIS Rack Work|| Harp, Viewer, Wien Work <br> CIS Rack Work|| Harp, Viewer, Wien Work <br> CIS Rack Work
 +
|-
 +
| '''Tunnel'''<br>9a - 12p || INSTALL Grout pedestals || Laser room/table work <br> Ceiling Lifting Plate Install || Fire pipe demo || Fire pipe demo || F
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work
 +
|-
 +
| '''Tunnel'''<br>12p - 4p || M || Laser room/table work || Fire pipe demo || Fire pipe demo || F
 +
|}
 +
 
 +
[[File:InjSB Week9.png|1000px]]
 +
 
 +
 
 +
</div>
 +
 
 +
== Week 10 (Nov 23 - Nov 25 🦃)  ==
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
# Complete assembly of new Y-chamber
 +
# Magnetic mapping of spare aperture cube
 +
# A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
 +
# Prebuncher -- RF testing/tuning
 +
# Wien-mania! [[200kV Wien filter - FINAL | (high level schedule)]] =>
 +
#* Horizontal Wien magnetic assembly and field mapping
 +
#* Bake V-wien electrode assembly with vacuum chamber
 +
#* V-wien HV test at UITF
 +
#* Resistor box testing at UITF?
 +
 
 +
;'''Tunnel work '''
 +
# Opportunistic cable pulls -- who wants to do some? Good week for it.
 +
 
 +
;'''ISB Work '''
 +
# Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
 +
# PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer)
 +
# Viewer upgrades, IN03B07 (Norris)
 +
# Harp upgrades, IN03B07 (Dela Cruz)
 +
# CIS Rack Work, IN01B{00-05} (Windham)
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|- style="background-color:#C3C8D4"
 +
! '''Location'''<br>Time !! Mon 11/23 !! Tue 11/24 !! Wed 11/25 !! Thu 🦃 11/26 !! Fri 11/27
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>5a - 9a || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work ||  ||
 +
|-
 +
| '''Tunnel'''<br>5a - 9a || M || T || W ||  || 
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>9a - 12p || Viewer, Harp, Wien Work <br> CIS Rack Work || Viewer, Harp, Wien Work <br> CIS Rack Work|| Harp, Viewer, Wien Work <br> CIS Rack Work|| ||
 +
|-
 +
| '''Tunnel'''<br>9a - 12p || M || T || W ||  ||
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work ||  ||
 +
|-
 +
| '''Tunnel'''<br>12p - 4p || M || T || W ||  ||
 +
|}
 +
 
 +
[[File:InjSB Week9.png|1000px]]
 +
 
 +
 
 +
</div>
 +
 
 +
== Week 11 (Nov 30 - Dec 4)  ==
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* H-Wien
 +
**plate ready at shop, mic and test fit @ MMF
 +
**order (4) Ni plates
 +
* V-Wien
 +
** Start HV tests @ UITF
 +
* MHD
 +
** complete thermal test >2.5A
 +
** measure field profile and BL/I for CED
 +
* DR
 +
** measure DR per Jay's plan
 +
* A1/A2 cubes
 +
** complete assembly (coils + aperture), test motion and shorts
 +
**S&A fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes)
 +
* PSS kicker
 +
** vendor quotes?
 +
** place order
 +
 
 +
;'''Tunnel work'''
 +
* Install
 +
** Y girder + 2I solenoid from 1137 to tunnel
 +
** Gun table to foot pads
 +
 
 +
* S&A
 +
** Pre-align Y girder
 +
** Pre-align gun
 +
 
 +
* PSS/CIS
 +
** Complete laser bypass
 +
** Align laser - test at window, viewer hole, cathode/flange
 +
 
 +
* CIS/S&A
 +
** 2I solenoid on pedestal
 +
** 2I vacuum connection (valve to gun)
 +
** Final align
 +
** Final laser check
 +
 
 +
;'''ISB Work '''
 +
* Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
 +
* PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
 +
* Viewer upgrades, IN03B{06-07} (Norris)
 +
* Harp upgrades, IN03B07 (Dela Cruz)
 +
* CIS Rack Work, IN01B{00-05} (Windham)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|- style="background-color:#C3C8D4"
 +
! '''Location'''<br>Time !! Mon 11/30 !! Tue 12/1 !! Wed 12/2 !! Thu 12/3 !! Fri 12/4
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>5a - 9a || M || T || W || R || F
 +
|-
 +
| '''Tunnel'''<br>5a - 9a || M || INSTALL: Y-chamber, solenoid || PSS Laser Bypass Work || S&A: Pre-align Gun-Y || S&A: Pre-align Gun-Y
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>9a - 12p || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work
 +
|-
 +
| '''Tunnel'''<br>9a - 12p || M || INSTALL: Y-chamber, solenoid || CIS Laser Hut Work || S&A: Pre-align Gun-Y || S&A: Pre-align Gun-Y <br> CIS Laser Alignment Work
 +
|-
 +
| '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work
 +
|-
 +
| '''Tunnel'''<br>12p - 4p || M || T || W || S&A: Pre-align Gun-Y || S&A: Pre-align Gun-Y <br> CIS Laser Alignment Work
 +
|}
 +
 
 +
[[File:InjSB Week11.png|1000px]]
 +
 
 +
</div>
 +
 
 +
== Week 12 (Dec 7 - Dec 11)  ==
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Wien (Test Lab)
 +
** Test voltage divider box, calibrating UITF Matsusada HV PSs '''done, ''' ''opted to use FLUKE 1000:1 V-probe and RMS true-value multimeter''
 +
** U-Wien electrode alignment -- install teflon spacer (CIS) '''first-pass done, ''' ''after discussions, may refine''
 +
** Improve V-wien electrode alignment? (S&A) ''deferred''
 +
** Receive Nickel endplates ''received, returned after finish found scratched, received again?''
 +
 
 +
* A1/A2 cubes (Test Lab)
 +
** Assemble fixture mounting plates '''done'''
 +
** Test motion and shorts '
 +
** Fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) (S&A) ''awaiting cubes''
 +
 
 +
* Prebuncher - high power testing
 +
 
 +
* PSS kicker
 +
** build bids received, choosing one '''done'''
 +
** 12/9: req submitted
 +
 
 +
*MagTest
 +
** Wrapping up A2 measurements
 +
** Wrapping up A1 measurements
 +
 
 +
 
 +
;'''Tunnel work'''
 +
* Wien cable pulls (Dela Cruz)
 +
* Laser alignment work (CIS) '''complete for this week'''
 +
* Gun -> Y-chamber vacuum connections (CIS) ''Thursday/Friday''
 +
* Viewer cable terminations (Norris)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
 +
* PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
 +
* Viewer upgrades, IN03B{06-07} (Norris)
 +
* Harp upgrades, IN03B07 (Dela Cruz)
 +
* CIS Rack Work, IN01B{00-05} (Windham)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|- style="background-color:#C3C8D4"
 +
! '''Location'''<br>Time !! Mon 12/7 !! Tue 12/8 !! Wed 12/9 !! Thu 12/10 !! Fri 12/11
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>5a - 9a || M || Viewer/Wien/Harp Work || Viewer/Wien/Harp Work || R || Viewer Terminations
 +
|-
 +
| '''Tunnel'''<br>5a - 9a ||  CIS Laser Work || CIS Laser Work || CIS Laser Work || S&A+CIS Drive Laser Alignment || Locking in NEG-tube <br> BPM locations (CIS+S&A)
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>9a - 12p || CIS Rack Work || CIS Rack Work <br> Viewer/Wien/Harp Work || CIS Rack Work <br> Viewer/Wien/Harp Work || CIS Rack Work || CIS Rack Work <br> Viewer Terminations <br> Wien Cabling Work
 +
|-
 +
| '''Tunnel'''<br>9a - 12p || CIS Laser Work || CIS Laser Work-<br>temp Vacuum Window Install <br> Facilities HVAC Investigation || CIS Laser Work || S&A+CIS Drive Laser Alignment || CIS Pump Down Gun <br> S&A Gun/Y-Chamber
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work <br> Viewer Terminations <br> Wien Cabling Work
 +
|-
 +
| '''Tunnel'''<br>12p - 4p || CIS Laser Work || CIS Laser Work <br> Facilities HVAC Investigation || CIS Laser Work || S&A+CIS Drive Laser Alignment || CIS Pump Down Gun <br> S&A Gun/Y-Chamber
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week11.png|1000px]]
 +
 
 +
 
 +
</div>
 +
 
 +
== Week 13 (Dec 14 - Dec 18)  ==
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Wien (Test Lab)
 +
** U-Wien electrode parallelism evaluation after assembly w/teflon spacer block, spacer for hangers added (S&A) '''done'''
 +
** Controls work continues ''yep''
 +
** HV PS calibration measurements, second-pass ''Friday''
 +
** Receive Nickel endplates? '''done'''
 +
 
 +
* A1/A2 cubes (Test Lab)
 +
** Assembling A1/A2 cubes '''done'''
 +
** Test motion and shorts '''done'''
 +
** Fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) (S&A) '''A2 done, A1 completed today'''
 +
 
 +
*MagTest
 +
** Measure DR per Jay's plan ''continues''
 +
** QW (Wien quad) lead reinforcement and field mapping ''4 done, 12 to go''
 +
 
 +
 
 +
;'''Tunnel work'''
 +
* Wien cable pulls (Dela Cruz) (latter half of the week) ''done?''
 +
* Viewer cable terminations? (Norris) ''near complete''
 +
* Gun -> Y-chamber vacuum pumpdown and leak check (Stutzman, Adderley) '''done'''
 +
* CIS Check drive laser -> cathode -> retroreflection alignment w/assembly under vacuum '''done'''
 +
* SSG Backs out of Laser Bypass workaround in support of PSS upgrades ''Friday''
 +
 
 +
 
 +
;'''ISB Work '''
 +
* Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz)
 +
* PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
 +
* Viewer upgrades, IN03B{06-07} (Norris)
 +
* Harp upgrades, IN03B07 (Dela Cruz)
 +
* CIS Rack Work, IN01B{00-05} (Windham)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|- style="background-color:#C3C8D4"
 +
! '''Location'''<br>Time !! Mon 12/14 !! Tue 12/15 !! Wed 12/16 !! Thu 12/17 !! Fri 12/18
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>5a - 9a || Viewer Terminations || Viewer Terminations || W || R || F
 +
|-
 +
| '''Tunnel'''<br>5a - 9a ||  CIS Vacuum Work: <br> heating NEG chambers || CIS Vacuum Work:<br>Leak Checks || Wien HV Cable Pulls? || Wien HV Cable Pulls? || F
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>9a - 12p || CIS Rack Work <br> Viewer Terminations || CIS Rack Work <br> Viewer Terminations || CIS Rack Work || CIS Rack Work <br> PSS Upgrades:<br>Access Room and in Racks || CIS Rack Work
 +
|-
 +
| '''Tunnel'''<br>9a - 12p || CIS Vacuum Work: <br> heating NEG chambers || CIS Vacuum Work:<br> Leak Checks<br>CIS Laser/retroreflection checks || CIS Laser Hut Work <br> Viewer Terminations <br> Wien HV Cable Pulls? || CIS Laser Hut Work <br> Viewer Terminations || SSG Laser Bypass Backout
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrades:<br>Access Room and in Racks <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work
 +
|-
 +
| '''Tunnel'''<br>12p - 4p || CIS Vacuum Work || CIS Vacuum Work<br>CIS Laser/retroreflection checks || CIS Laser Hut Work <br> Viewer Terminations || CIS Laser Hut Work <br> Viewer Terminations || F
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week11.png|1000px]]
 +
 
 +
</div>
 +
 
 +
== Week 13.6 (Dec 21 - Dec 23)  ==
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
<div style="text-align: center">
 +
'''830 toolbox meetings suspended.<br>Have a safe and restful winter break.'''
 +
</div>
 +
 
 +
;'''Non-Tunnel Work'''
 +
 
 +
MagTest --
 +
* DR field mapping continues
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* Neutron detector field cable runs, above 0L03 (Gonzales)
 +
* PSS upgrades -- equipment near Inj-NL gate (SSG)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* CIS Rack Work, IN01B{00-05} (Windham)
 +
* Viewer terminations, IN03B{06, 07} (Norris)
 +
* PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere (SSG)
 +
* Neutron detector system work, IN03+4 (Gonzales, Mock)
 +
 
 +
 
 +
[[File:InjSB Week13.5.png|1000px]]
 +
 
 +
 
 +
</div>
 +
 
 +
</div>
 +
 
 +
= Week 14 (Jan 4 - Jan 8)  =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
'''Happy New Year!!! 🎉🎉🎉''' 
 +
 
 +
;* AIPINJ Phase I Jobs for 2021
 +
* Punchlist from 12/17/20 ME meeting [[media:AIPINJ_2021_Jobs_v3.pdf]]
 +
 
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Wien
 +
** V-Wien (Hernandez-Garcia)
 +
*** remove from UITF test stand
 +
*** re-assemble in ''V''ertical orientation w/new spacers, Ni endplates, and magnet
 +
*** ~Wed deliver to S&A
 +
*** Survey of V-wien, evaluation of electrode parallelism
 +
** Picking up new Ni endplates from machine shop, cleaning and annealing before delivery to MagTest to be used in assembly of H-wien and evaluation during field mapping (Grames)
 +
** Fabrication of HV switcher chassis continues (Dela Cruz)
 +
** Controls work continues (Croke)
 +
* A1/A2 Apertures
 +
** Motor controls work continues (Windham)
 +
** A1/A2 girder build in TL continues (Adderley)
 +
* MagTest
 +
** DR field mapping
 +
** Complete QW coils lead reinforcement and mapping
 +
** Begin H-wien field mapping?
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* Prepping for Gun2 bake (Stutzman)
 +
* Wien HV cable pulls? (Dela Cruz, Norris)
 +
* Laser hut opto-mechanical work (Zhang)
 +
* LCW walkthrough (CIS+I&C+MechInstall)
 +
 
 +
 
 +
 
 +
;'''ISB Work '''
 +
* Wien HV cable pulls?, IN01B{00+01} (Dela Cruz, Norris)
 +
* PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
 +
* CIS Rack Work, IN01B{00-05} (Windham)
 +
* Viewer upgrades, IN03B{06+07} (Norris)
 +
* 15deg dipole interlock panel install, IN01B11 (Windham)
 +
* iocin3 crate upgrade to VME, IN01B{04+14} (Dela Cruz)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|- style="background-color:#C3C8D4"
 +
! '''Location'''<br>Time !! Mon 1/4 !! Tue 1/5 !! Wed 1/6 !! Thu 1/7 !! Fri 1/8
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>5a - 9a || M || T || W || R || F
 +
|-
 +
| '''Tunnel'''<br>5a - 9a ||  M || Wien HV cable pulls? || MechInstall Crane Work <br> Wien HV cable pulls? <br> Viewer Terminations || Wien HV cable pulls? <br> Viewer Terminations || Wien HV cable pulls? <br> Viewer Terminations
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>9a - 12p || CIS Rack Work || CIS Rack Work --<br>15deg Interlocks Panel || CIS Rack Work <br> iocin3 crate upgrade prep || 15deg Interlocks Panel || CIS Rack Work
 +
|-
 +
| '''Tunnel'''<br>9a - 12p || Gun2 Bake Preps || 9a LCW Manifold WalkThru <br> Gun2 Bake Preps <br> Viewer Terminations || Gun2 Bake Preps <br> Viewer Terminations || Gun2 Bake Preps <br> Viewer Terminations || Gun2 Bake Preps <br> Viewer Terminations
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>12p - 4p || CIS Rack Work <br>PSS Upgrades || CIS Rack Work --<br>15deg Interlocks Panel  <br>PSS Upgrades || CIS Rack Work <br> iocin3 crate upgrade prep <br> PSS Upgrades || 15deg Interlocks Panel <br>PSS Upgrades || CIS Rack Work <br>PSS Upgrades
 +
|-
 +
| '''Tunnel'''<br>12p - 4p || Gun2 Bake Preps || Gun2 Bake Preps || Gun2 Bake Preps || Gun2 Bake Preps || Gun2 Bake Preps
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week14.png|999px]]
 +
 
 +
</div>
 +
 
 +
= Week 15 (Jan 11 - Jan 15) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Wien (Hernandez-Garcia)
 +
** Bake V-wien
 +
** V-wien HV soak
 +
** Fabrication of HV switcher chassis (Dela Cruz)
 +
* A1/A2 girder build (Adderley)
 +
* Rectify viewer air cylinder lengths? (Stutzman)
 +
 
 +
* MagTest
 +
** DR field mapping
 +
** Complete QW coils lead reinforcement and mapping
 +
** Begin H-wien field mapping?
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* Photocathode suitcase bake (Stutzman, Adderley)
 +
* Wien HV cable pulls? (Dela Cruz, Norris)
 +
* Laser hut work (Zhang)
 +
* iocin3 job Tuesday
 +
::Gun HV control => no problem
 +
::Some vacuum => no problem
 +
::Some FSD => no problem
 +
::Insertables (viewers etc.) => no problem
 +
::Some Pockels cell & RTP cell controls => i turned off RTP HV PS already
 +
::Chopping aperture (not sure how current this is) => no problem
 +
::Scraper (think this is redundant?) => do we remove now???
 +
::Maybe some old laser controls (ocelot?) => is this really a running app???
 +
::An application called pol_source, which has controls for a number of boards - IP Digital 24, BASIC stepper motor, IpOpto. => => what is this connected to???
 +
::Are the remaining 4-laser apps on iocin3b?  Will that mini-crate be replaced or merged?  Any other apps on iocin3?
 +
 
 +
 
 +
 
 +
;'''ISB Work '''
 +
* ⚡⚡⚡'''Power Outage'''⚡⚡⚡ I-BT Breaker Panel Work -- adding 50A circuit for new chopper SSA along with 225A main breaker <br> Details of what will lose power in [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21696 ATLis 21696], Tunnel and SB racks affected
 +
* PSS Upgrades -- energizing new equipment, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
 +
* CIS Rack Work, IN01B{00-05} (Windham)
 +
* Viewer upgrades, IN03B{06+07} (Norris)
 +
* 15deg dipole interlock panel install, IN01B11 (Windham)
 +
* iocin3 crate upgrade to VME, IN01B{04 + 14} (Dela Cruz)
 +
** iocin3 will be down Monday 1/11 morning
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|- style="background-color:#C3C8D4"
 +
! '''Location'''<br>Time !! Mon 1/11 !! Tue 1/12 !! Wed 1/13 !! Thu 1/14 !! Fri 1/15
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br>'''All Day''' || Safing out equipment for iocin3 work || T || W || Breaker Panel Work || Float for breaker panel work
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br> Morning || M || iocin3 VME upgrade <br> 15deg interlock work || W || Breaker Panel Work || F
 +
|- style="background-color:#F0F8FF"
 +
| '''InjSB'''<br> Afternoon || PSS Upgrades || 15deg interlock work <br> PSS Upgrades || PSS Upgrades || Breaker Panel Work <br> PSS Upgrades || PSS Upgrades
 +
|-
 +
| '''Tunnel'''<br> All Day|| Suitcase bake <br> Safing out equipment for iocin3 work || Suitcase bake || W || Breaker Panel Work || Float for breaker panel work
 +
|-
 +
| '''Tunnel'''<br> Morning ||  M || T || W || Breaker Panel Work || F
 +
|-
 +
| '''Tunnel'''<br> Afternoon || M || T || W || Breaker Panel Work || F
 +
|}
 +
 
 +
[[File:InjSB Week14.png|1000px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 16 (Jan 18 - Jan 22 +weekend) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Wien (Hernandez-Garcia)
 +
** <s>Moving V-wien from UITF test stand to vacuum lab, w/local vac PS</s> Leaving on test stand until need to move
 +
** H-Wien
 +
*** Preparing to receive <s>Wed 1/20</s> Fri 1/22
 +
*** Assemble with Ni end plates
 +
*** UHV cleaning
 +
 
 +
* A1/A2 girder build (Adderley, Stutzman)
 +
** Rectifying viewer air cylinder dimensions
 +
 
 +
* Prebuncher testing/tuning (Wissman)
 +
 
 +
* MagTest
 +
** H-wien field mapping (ETA Fri 1/22)
 +
** DR#2 coil lead reinforcement
 +
** DR#1 upper coil inspection
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* Fire pipe install, pipe delivery 1/22, install begins ''Saturday'' 1/23
 +
* Wien HV cable pulls? (Dela Cruz, Norris)
 +
* Laser hut work (Zhang)
 +
* Vacuum bakes (Stutzman, Adderley)
 +
* FC#1 bellows replacement (Adderley, Stutzman, Grames)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
 +
* CIS Rack Work, IN01B{00-05} (Windham)
 +
* Viewer upgrades, IN03B{06+07} (Norris)
 +
* 15deg dipole interlock panel install, IN01B11 (Windham)
 +
* Chopper SSA upgrade, back of IN01B{10-15} (Farrish)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 1/18 <br> MLK Jr Day !! style="background-color:#CFDCCA" |  Tue 1/19 !! style="background-color:#CFDCCA" |  Wed 1/20 !! style="background-color:#CFDCCA" |  Thu 1/21 !! style="background-color:#CFDCCA" |  Fri 1/22 !! style="background-color:#FFAF9E" | Weekend <br> Sa 23rd + Su 24th
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || ''holiday'' || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work || style="background-color:#FFAF9E" | ''weekend''
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || M || Beam Sync Cabling <br> Check (~IN01B04) ''Francis'' <br> 15deg Interlock <br> Chopper SSA Cabling || W || CIS Rack Work || CIS Rack Work || style="background-color:#FFAF9E" | ''weekend''
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || M || 15deg Interlock <br> PSS Upgrades || Laser chiller checkout <br> PSS Upgrades || CIS Rack Work <br> PSS Upgrades || CIS Rack Work <br> PSS Upgrades || style="background-color:#FFAF9E | ''weekend''
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day || ''holiday'' || Laser Hut Work <br> Vacuum Bakes || FC#1 Bellows Replacement || R ||style="background-color:#FFAF9E"| '''Fire pipe install''' || style="background-color:#FFAF9E" | '''Fire pipe install'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  M || T || W || FC#1 Vacuum Button-Up <br> Viewer Terminations ||style="background-color:#FFAF9E"| Fire pipe install || style="background-color:#FFAF9E" | Fire pipe install
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || M || T || Laser Hut Work || FC#1 Vacuum Button-Up <br> Laser Hut Work ||style="background-color:#FFAF9E"| Fire pipe install || style="background-color:#FFAF9E" | Fire pipe install
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week16.png|999px]]
 +
 
 +
</div>
 +
 
 +
= Week 17 (Jan 25 - Jan 29) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Wien (Hernandez-Garcia)
 +
** H-Wien
 +
*** Receive from MagTest after field mapping
 +
*** Assemble with Ni end plates
 +
*** UHV cleaning
 +
** U-Wien newly fabricated Ni endplates
 +
*** Pick-up after ultrasonic isopropanol clean 1/25
 +
*** Deliver for annealing
 +
** V-Wien
 +
*** Remove from UITF cave and begin assembling on girder?
 +
* A1/A2 girder build (Adderley, Stutzman)
 +
* Rectifying viewer air cylinder dimensions (Adderley, Machie, Gregory)
 +
* Prebuncher testing/tuning (Wissman)
 +
 
 +
* Survey and Alignment
 +
** PCup survey and fiducialization
 +
** FC#1 survey and fiducialization
 +
** <s>H-wien after UHV cleaning and assembly using teflon spacer method</s>
 +
** Individual H-wien electrodes, and U-wien ones for comparison
 +
 
 +
* MagTest
 +
** QW coil thermal tests
 +
** QW coil quality control checks
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* Fire pipe (FML subcontractor)
 +
** Install
 +
** Pressurized air test
 +
** Pressurized water test (hydrotest)
 +
* Laser hut work (Zhang)
 +
* Preps for prep-chamber and HV chamber bakes next week (Stutzman, Adderley)
 +
* 120V front-end outlets walkthru (Windham, Stutzman, Adderley, Grames)
 +
* Cryo relief valve PM, behind 0L02 (Cryo)
 +
* Stowing photocathodes in suitcase for bakes (Grames)
 +
* Gate valve controller checkout/documentation (Windham)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
 +
* CIS Rack Work, IN01B{00-05} (Windham)
 +
* Viewer upgrades, IN03B{06+07} (Norris)
 +
* 15deg dipole interlock panel, IN01B11 (Windham)
 +
* Utility chassis swaps, IN02B{10,11,26} + IN04B10 (Diggs, Kissinger)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 1/25  !! style="background-color:#CFDCCA" |  Tue 1/26 !! style="background-color:#CFDCCA" |  Wed 1/27 !! style="background-color:#CFDCCA" |  Thu 1/28 !! style="background-color:#CFDCCA" |  Fri 1/29
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || M || '''Fire pipe install''' || W || '''Utility chassis swaps''' || F
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || M || Fire pipe install || W || Utility chassis swaps || F
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || PSS Upgrades || Fire pipe install <br> PSS Upgrades || PSS Upgrades || Utility chassis swaps <br> PSS Upgrades || PSS Upgrades
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day||style="background-color:#FFAF9E" | '''Fire pipe install''' || style="background-color:#FFAF9E" | '''Fire pipe install''' || style="background-color:#FFAF9E" | '''Fire pipe install''' || '''Cryo relief valve PM''' || '''Fire pipe hydrotest'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||style="background-color:#FFAF9E" | Fire pipe install || style="background-color:#FFAF9E" | Fire pipe install || style="background-color:#FFAF9E" | Fire pipe install || <s>120V outlets walkthru</s> <br> Fire pipe air test || Fire pipe hydrotest <br> Valve controller
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon ||style="background-color:#FFAF9E" | Fire pipe install || style="background-color:#FFAF9E" | Fire pipe install || style="background-color:#FFAF9E" | Fire pipe install <br> Laser Hut Work || Laser Hut Work || ''Preps for bakes?'' <br> ''Photocathodes->Suitcase?'' <br> Laser Hut Work
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week17.png|1000px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 18 (Feb 1 - Feb 5) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Wien (Hernandez-Garcia)
 +
** H-Wien
 +
*** MS fabricating new frame x4 and <br>new 14mm-spacing teflon spacers for electrode assembly
 +
*** Once MS done, towards end of the week, assemble H-wien w/new frame
 +
*** Assembled H-wien -> S&A
 +
** HV Switcher Chassis (Dela Cruz)
 +
*** 1st chassis hi-potted good
 +
*** 2nd chassis getting overload faults, investigating
 +
* Viewer assembly (Adderley, Stutzman)
 +
* Wien girder assembly (Adderley, Stutzman)
 +
** Wien quads on crosses -- ETA T/W for QW coils from MagTest
 +
* Add pumps, vacuum leak check A1/A2 girder after S&A (Stutzman, Adderley)
 +
* Laser box build (Zhang, Gregory)
 +
* Build spare valve override blackbox, fourth in total (Windham)
 +
 
 +
* Survey and Alignment
 +
** A1/A2 girder 1A pre-alignment
 +
** H-wien assembled on new frame
 +
 
 +
* MagTest
 +
** Finish QC of QW coils -- Tuesday/Wednesday ETA
 +
** Thermal and current-limit tests on assembled spare QW-quad
 +
** Field mapping assembled spare QW-quad
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* Laser hut work (Zhang)
 +
* Viewer upgrades (Norris)
 +
* <s>Prep chamber bake</s> forgoing for now, vacuum sufficiently good
 +
** Setup (in no particular order)
 +
*** photocathodes->suitcase;
 +
*** breakdown unistrut,
 +
*** stow protective plastic barrier;
 +
*** Configure IPs and valves
 +
** <s>Bake for ~3 days @ 🔥🔥🔥C
 +
** Breakdown ~Friday</s>
 +
* Opportunistic preps for HV chamber bake
 +
* 120V front-end outlets walkthru (Windham, Stutzman, Adderley, Grames)
 +
* Laser box enclosure design walkthru (Zhang, Gregory)
 +
* N2 manifold temporary move (Bullard)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
 +
* CIS Rack Work, IN01B{00-05} (Windham)
 +
* Viewer upgrades, IN03B{06+07} (Norris)
 +
* 15deg dipole interlock panel, IN01B11 (Windham)
 +
* Install Wien HV Polarity Switcher Chassis, IN01B0{0,1} (Dela Cruz)
 +
 
 +
;'''Other Service Buildings'''
 +
* Prebuncher testing/tuning in BSY SB (Wissman)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 2/1  !! style="background-color:#CFDCCA" |  Tue 2/2 !! style="background-color:#CFDCCA" |  Wed 2/3 !! style="background-color:#CFDCCA" |  Thu 2/4 !! style="background-color:#CFDCCA" |  Fri 2/5
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work || F(loat)
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || M || 15deg dipole intlk tests <br> Viewer upgrades || 15deg dipole intlk tests <br> Viewer upgrades || R || Viewer Upgrades
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || PSS Upgrades || 15deg dipole intlk tests <br> PSS Upgrades || PSS Upgrades || 15deg dipole intlk tests <br> PSS Upgrades || PSS Upgrades
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day|| '''Prep for Prep Chamber Bake''' || <s>Prep chamber bake</s> <br> Preps for HV Chamber Bake || <s>Prep Chamber Bake</s> <br> Preps for HV Chamber Bake || <s>Prep Chamber Bake</s> <br> Preps for HV Chamber Bake || F(loast)
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  Valve controller || Prep chamber vacuum tests/eval || Viewer Upgrades <br> Engaging Prep RGA <br> ''N2 manifold move?'' || N2 manifold move <br> Laser enclosure walkthru || Viewer Upgrades <br> N2 manifold work
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || Photocathodes->Suitcase <br> Valve controller || Laser hut work || Laser enclosure walkthru <br> Laser hut work || Laser hut work || Laser hut work
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week18.png|999px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 19 (Feb 8 - Feb 12) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Weld Jobs: QW quads on crosses, Wien cube
 +
* A1/A2 Girder (Adderley, Stutzman)
 +
** Final leak check, prep for install in tunnel
 +
* Wien (Hernandez-Garcia)
 +
** H-wien
 +
*** S&A, Monday
 +
*** Bake
 +
*** Vacuum pumpdown
 +
*** HV testing?
 +
** V-wien
 +
*** Unmount from test fixture in UITF
 +
*** Prepare for girder install
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* Viewer upgrades
 +
* A1/A2 girder install
 +
** Vacuum prep work (Stutzman, Adderley), Monday
 +
** Install (Mech Install), Tuesday
 +
** S&A, Tue-Thu
 +
** Associated vacuum work, Tue-Thu
 +
* FC#1 Re-install
 +
** Vacuum prep work (Stutzman, Adderley), Monday
 +
** Re-install + S&A, Tuesday
 +
** Vacuum space pumpdown (Stutzman, Adderley), Tue-Thu
 +
* Laser hut work (Zhang)
 +
* Laser enclosure design/fab (Zhang, Gregory)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
 +
* CIS Rack Work, IN01B{00-05} (Windham)
 +
* Viewer upgrades, IN03B{06+07} (Norris)
 +
* 15deg dipole interlock panel, IN01B11 (Windham)
 +
* Install HV Polarity Switcher Chassis, IN01B0{0,1} (Dela Cruz)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 2/8  !! style="background-color:#CFDCCA" |  Tue 2/9 !! style="background-color:#CFDCCA" |  Wed 2/10 <br> 1p: AIPINJ team photo (zoom)!! style="background-color:#CFDCCA" |  Thu 2/11 !! style="background-color:#CFDCCA" | 🌨️ Fri 2/12
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || 15deg interlock || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || M || T || Viewer Upgrades || R || F
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || PSS Upgrades || PSS Upgrades || PSS Upgrades || PSS Upgrades || PSS Upgrades
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day || '''Preps for FC1+A1/A2 Install''' || '''Vent Gun->0I; <br> FC#1 + A1/A2 Girder <br> Install, Associated Vac Work, S&A''' || '''S&A of A1/A2 Girder,<br> after cartridge swap''' || '''Preps for<br> HV Chamber Bake <br> Prep NEG Activation''' || '''Preps for<br> HV Chamber Bake <br> Prep NEG Activation'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  Pump Cart Staging || 7a: Vent Gun2->0I (CIS) <br> 7a: FC#1 Re-Install (CIS) <br> ~8a: FC#1 S&A, set yaw <br> A1/A2 Girder Install (Mech) || Cartridge Swap (MechInstall) <br> S&A of A1/A2 Girder <br> 0L Viewer upgrades || <s>S&A of A1/A2 Girder</s> <br> '''A1/A2 Cartridge Layout''' <br> 9a-11a: "Tour" (4people) || ''S&A of A1/A2?''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || Laser Hut Work ||  A1/A2 Girder S&A <br> ''Laser hut work?'' || S&A of A1/A2 Girder <br> A1/A2 vac connections <br> Prep Chamber RGA v Heat || Cartridge Layout || ''S&A of A1/A2?''
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week18.png|1001px]]
 +
 
 +
</div>
 +
 
 +
= Week 20 (Feb 15 - Feb 19) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Wien girder assembly (Adderley, Stutzman)
 +
* H-wien HV testing at UITF ''(once bake complete)'' (Hernandez-Garcia, Bullard)
 +
* QW field mapping (MagTest)
 +
* PSS Kicker assembly once parts arrive
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* HV Chamber and NEG tube bake (Adderley, Stutzman)
 +
* Prep chamber NEG activation (Adderley, Stutzman)
 +
* A1/A2 girder cartridge resolution?
 +
* Wien HV cable pulls? (Dela Cruz)
 +
* Viewer upgrades? (Norris)
 +
* UHV patch panel installation (Windham)
 +
* Valve black override box installation (Windham)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
 +
* CIS Rack Work, IN01B{00-12} (Windham)
 +
* Viewer upgrades, IN03B0{6,7} (Norris)
 +
* Install Wien HV Polarity Switcher Chassis, IN01B0{0,1} (Dela Cruz)
 +
** HV cable pulls?
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | 🇺🇸 Monday 2/15 !! style="background-color:#CFDCCA" |  Tue 2/16 !! style="background-color:#CFDCCA" |  Wed 2/17 !! style="background-color:#CFDCCA" |  Thu 2/18 !! style="background-color:#CFDCCA" |  Fri 2/19
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || Switcher chassis install || Switcher chassis install <br> Wien controls test || Switcher chassis install <br> Wien controls tests || R || F
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || PSS Upgrades || PSS Upgrades || PSS Upgrades || PSS Upgrades <br> Lock-Up @ 1600 || PSS Upgrades
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day|| '''HV Chamber + <br> NEG Tube Bake''' || '''HV Chamber + <br> NEG Tube Bake''' || '''HV Chamber + <br> NEG Tube Bake''' || '''HV Chamber + <br> NEG Tube Bake''' || '''HV Chamber Bake <br> NEG Tube Activation <br> Prep Chamber NEG Activation'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  M || T || W || R || 10a: Outlet relocation walkthru
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || M || T || W || R || F
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week20.png|1001px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 21 (Feb 22 - Feb 26) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* H-wien HV evaluation (Hernandez-Garcia, Bullard)
 +
* Wien girder modifications (Machine Shop)
 +
* QW field mapping (MagTest)
 +
* PSS Kicker assembly
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* Breaking down activation and bake equipment (Stutzman, Adderley)
 +
* PSS Injector Segment Certification (SSG) '''Th+F Swing'''
 +
* A1/A2 Girder
 +
** Add SS adapter plates (CIS)
 +
** Re-fiducialize girder, MechInstall staging as needed (S&A)
 +
** Install on pedestals (MechInstall) '''Thursday'''
 +
** S&A of installed girder on pedestals '''Thursday'''
 +
** Vacuum hook-ups (CIS) '''Thursday'''
 +
* Laser hut work (Zhang)
 +
* Outlet Moves / Additions (FML) '''Friday'''
 +
** Move from floor to laser hut wall 120V outlets
 +
** ATLis 21922
 +
* Support Electrical Panel PM
 +
** Vacuum pump reconfigs from EM -> House power and back (CIS)
 +
** ATlis 21882
 +
 
 +
 
 +
;'''ISB Work '''
 +
* PSS Commissioning, IN02B{NI,29,30} +briefly elsewhere, swings (SSG)
 +
* PSS Injector Segment Certification (SSG) '''Th+F swing'''
 +
* CIS Rack Work, IN01* (Windham)
 +
* Viewer upgrades, IN03B0{6,7} (Norris)
 +
* Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)
 +
* Electrical panel PM, ATLis 21882 (FML) '''Friday'''
 +
** Work entails power outages in tunnel and SB
 +
** EM loop and normal power will not be off simultaneously
 +
** Facilities/Operability will coordinate -- see rough sched in table
 +
* Fan tray swap, ATLis 20311, IN02B23 (Greenfield) '''Friday 8a'''
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 2/22  !! style="background-color:#CFDCCA" |  Tue 2/23 !! style="background-color:#CFDCCA" |  Wed 2/24 !! style="background-color:#CFDCCA" |  Thu 2/25 !! style="background-color:#CFDCCA" |  Fri 2/26
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work || '''Electrical Work <br> some power outages'''
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || M || T || W || R || 8a Fan Tray Swap
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || M || PSS Tests, Lock-Up || W || PSS Certification || PSS Certification
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day|| '''Bake and Activation <br> Equipment Breakdown''' || '''A1/A2 re-fiducialization''' || W || '''A1/A2 Install Day''' || '''Electrical Work <br> some power outages'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  Leak checks of <br> *HV Chamber<br>*Prep Chamber<br>*2I beamline || Re-fiducialization of A1/A2 <br> Valve override box work || W || MechInstall adds adapter plates <br> Mounts on pedestals <br> S&A & Vac Hook-Ups|| Floor Outlet Relocation
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || M || PSS Lock-Up || W || A1/A2 S&A <br> 3p PSS Certs Lock-Up <br> Some Preps Beginning ~2p || ~1p: House Circuits PM <br> ~2p: Pump reconfig EM=>HOUSE <br> ~230p: EM Circuits PM <br> ~3p: PM done, Return pump config <br>  ~after: PSS Certs Lock-Up <br> (if needed)
 +
|}
 +
 
 +
[[File:InjSB Week21.png|1001px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 22 (Mar 1- Mar 5) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Wien girder assembly (CIS)
 +
** Mounting modifications '''complete''', ''returned from Hampton MS''
 +
** Additional holes for mounting/anchoring needed? Template from Engineering. (Gregory)
 +
** CIS+S&A Walk-thru identifying which components need alignment during assembly stage
 +
** Add component, survey, align *repeat*
 +
 
 +
* PSS Kicker (SSG)
 +
** Coil QA (MagTest)
 +
** Assembly (CIS)
 +
** Coils and fixture in. What other parts needed?
 +
* QW quad field mapping (MagTest)
 +
* Move PIG to InjSB
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* A1/A2 girder anchoring (Adderley, Gregory)
 +
** S&A Alignment check before vacuum hook-ups
 +
* A1/A2 / Region 3 Vacuum Connections, Pumpdown, Leak check (CIS)
 +
* Wien girder pedestal re-positioning (MechInstall)
 +
** Remove pedestals, knock out existing grout
 +
** Pedestals to new positions, templates provided by Engineering
 +
** Grout in
 +
* Crane in PIG HV resistor tank (MechInstall)
 +
* Macropulse chassis checkout (Zhang, Windham)
 +
* Laser hut alignment / opto-mechanical work (Zhang)
 +
* Pockels cell alignment (Zhang, Amali)
 +
* Gun HV Conditioning preparations (Hernandez-Garcia)
 +
* Beam-left S&A monument install (x4), adding to control, ATLis 21991 (S&A) '''Thursday'''
 +
* Lead brick clean-up (Grames)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* Wien HV Polarity Switcher Tests, Control Screens Checkouts, IN01B0{0-6} (Hernandez-Garcia, Windham, Dela Cruz, Croke)
 +
* CIS Rack Work, IN01* (Windham)
 +
* Viewer upgrades, IN03B0{6,7} (Norris)
 +
* Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)
 +
* SCAM Board Investigation, IN03B04 (Windham)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 3/1  !! style="background-color:#CFDCCA" |  Tue 3/2 !! style="background-color:#CFDCCA" |  Wed 3/3 !! style="background-color:#CFDCCA" |  Thu 3/4 !! style="background-color:#CFDCCA" |  Fri 3/5
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || M || T || 930 Wien Switcher Tests || SCAM Board T/S <br> Prebuncher Cable Pulls || F
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || M || T || Macropulse Chassis Checkout || R || F
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day|| '''A1/A2 anchoring''' || '''A1/A2 Vacuum hook-ups <br> pumpdown''' || '''Relocating Wien Pedestals''' || '''A1/A2 Girder Bake Oven Setup''' || '''A1/A2 Girder Bake Oven Setup'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  Wien stand demo <br> A1/A2 Anchoring || A1/A2 Vacuum Hook-Ups <br> 0I02 Harp Re-Install || MechInstall: * Crane in PIG <br> * Set Wien Pedestals <br> S&A: Align || Prebuncher cable pulls <br> S&A Monuments || F
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || A1/A2 Anchoring <br> Alignment Check <br> Pockels Cell Alignment || A1/A2 Pumpdown <br> Pockels Cell Alignment || A1/A2 girder leak check  || Region 3 leak checks <br> Macropulse chassis checkout <br> Pockels cell alignment || Lead brick clean-up
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week22.png|850px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 23 (Mar 8 - Mar 12) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Wien girder assembly, interleaved with component S&A (Stutzman, Adderley)
 +
* PSS Kicker (SSG)
 +
** Coil QA (MagTest)
 +
** Assembly (CIS)
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* A1/A2 Girder bake (Adderley, Bullard, Stutzman)
 +
* Gun HV Processing Setup (Hernandez-Garcia)
 +
** PIG connections
 +
** SF6 tests
 +
** Interlock jumpering/configuration (Grames, Windham)
 +
** PSS Certification of Gun HV (SSG, Forman) '''Wed 9a, lock-up'''
 +
* Wien pedestal grouting ''opportunistic''
 +
* Pockels cell alignment (Zhang, Amali)
 +
* Macropulse chassis modification and checkout (Windham, Zhang)
 +
* Lead brick clean-up (Grames)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* CIS Rack Work, IN01*
 +
* Viewer upgrades, IN03B0{6,7} (Norris)
 +
* Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 3/8  !! style="background-color:#CFDCCA" |  Tue 3/9 !! style="background-color:#CFDCCA" |  Wed 3/10 !! style="background-color:#CFDCCA" |  Thu 3/11 !! style="background-color:#CFDCCA" |  Fri 3/12
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || M || T || W || R || F
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || M || T || W || R || F
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day|| '''A1/A2 Girder Bake''' || '''A1/A2 Girder Bake''' || '''A1/A2 Girder Bake''' || '''A1/A2 Girder Bake''' || '''A1/A2 Girder Bake'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  Gun HV Processing Setup: <br>*Connect PIG<br>*SF6 Tests || Gun Interlocks Config<br> Jumpering || '''9a: Lock-Up for<br> Gun PSS Certs''' || R || F
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || ''Pockels cell alignment'' || ''Pockels cell alignment'' || ''Macropulse chassis mods'' || R || F
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week22.png|1001px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 24 (Mar 15 - Mar 19) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
[[Phase 1 - HCO & Commissioning]]
 +
 
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Complete assembly of Wien girder (CIS)
 +
** Pumpdown and leak check
 +
** Add viewers with modified shafts
 +
** Component 1B alignment (S&A)
 +
* PSS Kicker Assembly (CIS)
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* A1/A2 girder bake disassembly, leak checks (Adderley, Bullard, Stutzman)
 +
* PSS Kicker conduit, kapton insulation, install (SSG)
 +
* UHV system labelling, documentation (Windham)
 +
* Cable tray spec'ing, install, under A1/A2 girder (Windham)
 +
* Wien girder install (in approximate order) --
 +
** Install girder (MechInstall)
 +
** 2A alignment (S&A)
 +
** Vacuum connections, rough pumpdown, leak check (CIS)
 +
** Grout pedestals (MechInstall, S&A)
 +
** 2B alignment (S&A)
 +
* DC Power magnet hook-ups, as possible (Coleman, +1)
 +
* DC Power resistor box work (Coleman, +1)
 +
* Prep chamber activation check (Grames)
 +
* Laser hut work (Zhang)
 +
* Gun HV checkout (Hernandez-Garcia)
 +
** Lock-up on swings ''??''
 +
** DecaRad placement (Windham)
 +
** Anode picoammeter connection (Grames, Stutzman)
 +
** Backfill SF6 into gun, PIG (Bullard)
 +
* Pockels cell alignment (Amali, Zhang)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* CIS Rack Work, IN01* (Windham)
 +
* Viewer upgrades, IN03B0{6,7} (Norris)
 +
* Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 3/15  !! style="background-color:#CFDCCA" |  Tue 3/16 !! style="background-color:#CFDCCA" |  Wed 3/17 !! style="background-color:#CFDCCA" |  Thu 3/18 !! style="background-color:#CFDCCA" |  Fri 3/19
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || CIS Rack Work <br> UHV Sys Doc || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || M || T || W || R || F
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || M || T || W || R || F
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day|| '''A1/A2 Bake Takedown <br> Leak Check''' || '''A1/A2 Bake Takedown <br> Leak Check''' || A1/A2 Bake Takedown <br> Cable Tray Work || R || '''DC Power Inline Resistor Measurements <br> SRF CM Checkout'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  UHV Sys Doc || Backfill SF6 <br> DecaRad placement || Pockels cell alignment || Wien Pedestal Anchor Hole Drilling <br> A1 controls/spacing work <br> ~10a: Pockels cell alignment|| until 10a: A1 aperture work <br> ~9a: Pockels cell alignment <br> 930-11a: Lead brick clean-up <br> 10a DCP Inline Res
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || Pockels cell alignment <br> UHV Sys Doc || Pockels cell alignment<br> DecaRad Placement <br> Gun anode hook-up || Pockels cell alignment <br> 130p: Resistor box work || A1 controls/spacing work <br> Pockels cell alignment || Pockels cell alignment <br> DCP Inline Res
 +
|}
 +
 
 +
[[File:InjSB Week24.png|1000px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 25 (Mar 22 - Mar 26) =
 +
<div class="mw-collapsible mw-collapsed">
 +
[[Phase 1 - HCO & Commissioning]]
 +
 
 +
 
 +
;'''Non-Tunnel Work'''
 +
* PSS Kicker Assembly (CIS)
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* PSS Kicker conduit, kapton insulation, install (SSG)
 +
* Cable tray install, under A1/A2 girder (Windham)
 +
* Wien girder install (in approximate order) --
 +
** Install girder (MechInstall)
 +
** 2A alignment (S&A)
 +
** Vacuum connections, rough pumpdown, leak check (CIS)
 +
** Grout pedestals (MechInstall, S&A)
 +
** 2B alignment (S&A)
 +
* Setting up for Wien girder bake (CIS)
 +
* DC Power magnet hook-ups, as possible (Coleman, +1)
 +
* Survey checks of Wien <=> A1/A2 girder (S&A)
 +
* Laser hut work, pockels/RTP cell alignment (Zhang)
 +
* Helicity board beam sync fiber T/S (Suleiman, Windham, Francis)
 +
* Gun HV Assessment, Injector->Power Permit (Hernandez-Garcia)
 +
* PSS Kicker mounting spool swap (Adderley, Stutzman)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* CIS Rack Work, IN01* (Windham)
 +
* Viewer/Harp upgrades, IN03B0{6,7} (Norris/Dela Cruz)
 +
* Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 3/22  !! style="background-color:#CFDCCA" |  Tue 3/23 !! style="background-color:#CFDCCA" |  Wed 3/24 !! style="background-color:#CFDCCA" |  Thu 3/25 !! style="background-color:#CFDCCA" |  Fri 3/26
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || Craning Wien Girder || T || W || R || F
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || M || T || W || R || F
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day|| '''Wien girder install, S&A, vac hook-up''' || '''Wien girder leak checks <br> Gun HV Assessment Preps''' || '''Kicker spool swap''' || '''A1 Bake Setup''' || '''A1 Bake'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  MechInstall Wien girder <br> and S&A || * Wien girder <=> A1/A2 Girder <br> Flange alignment assessment <br> * Wien girder leak checks <br> * Gun HVPS Lock -> FC#1 Air line || 930a Swapping Kicker Spool <br> A1 Pumpdown || * PSS Kicker Fit Test <br> * A1 Bake Setup <br> * Yellow laser box removal <br> * || Helicity Board T/S
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || Wien girder S&A <br> and vacuum hook-ups, pumpdown <br> Pockels cell alignment || Wien girder leak checks <br> Laser hut work <br> '''5p: Lock-Up -> PP''' || A1 Pumpdown, Leak check <br> Laser hut work <br> '''4p: Lock-Up''' Gun HV assessment || A1 Bake Setup <br> Laser hut work <br> '''4p: Lock-Up''' Gun HV assessment || Laser hut work
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week25.png|1001px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 26 (Mar 29 - Apr 2) =
 +
<div class="mw-collapsible mw-collapsed">
 +
[[Phase 1 - HCO & Commissioning]]
 +
 
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Evaluation of prebuncher options for CEBAF (CIS, RF, Eng)
 +
* Laser enclosure build (Bullard, Machie)
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* 0L02 U-tube installs (Cryo)
 +
* AIPINJ Phase-II As-Found survey (S&A)
 +
* Laser hut work (Zhang)
 +
* Pb brick clean-up (MechInstall, Grames)
 +
* Penetration re-fills (MechInstall)
 +
** Holding off on '''laser hut''' penetration until after Wien bake
 +
* Gun HV Assessment, Injector Lock-up (Hernandez-Garcia)
 +
* Prebuncher install, S&A, vacuum rough down (Stutzman, Adderley)
 +
* Craning out heavy equipment in tunnel (MechInstall)
 +
* Grout Wien pedestals (MechInstall)
 +
* Vacuum Bakes (Adderley, Stutzman)
 +
** Wrap up A1 bake
 +
** Disassemble A1 bake setup
 +
** Setup for Wien girder bake, after prebuncher install
 +
** Wien girder bake
 +
 
 +
 
 +
;'''ISB Work '''
 +
* CIS Rack Work, IN01* (Windham)
 +
** Laser seed lockout walkthru with ES&H (Windham)
 +
* Viewer CAMAC->VME upgrades, IN03B0{6,7} (Norris)
 +
* Harp -> PC104 upgrades, IN03B0{6,7} (Dela Cruz)
 +
* Penetration re-fills (MechInstall)
 +
* Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)
 +
* Helicity board beam sync troubleshooting (Suleiman)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 3/29  !! style="background-color:#CFDCCA" |  Tue 3/30 !! style="background-color:#CFDCCA" |  Wed 3/31 !! style="background-color:#CFDCCA" |  Thu 4/1 !! style="background-color:#CFDCCA" |  Fri 4/2
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || CIS Rack Work  || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || M || T || Craning Out Heavy Equipment || R || '''Penetration Fills: <br> 58, 86, 108'''
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || M || T || W || Laser seed lock-out walkthru || 2p: Helicity Board Beam Sync T/S <br> Mott System Turn On
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day|| A1 Bake Takedown <br> 5D Line removal <br> SS Prebuncher Install || '''Prebuncher S&A, Vacuum Work''' || '''Wien girder bake setup''' <br> S&A Phase II As-Founds || '''Wien girder bake setup/begin'''  || '''Wien girder bake'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning || 0700: 5D line removal <br> Pb brick org walk-thru || 9a: S&A of prebuncher <br> 0L02 U-Tube Install || Penetration Closures <br> Craning Out Heavy Equipment <br> 0L04 U-tube installs || Wien bake controls check <br> Wien bake insulation <br> Penetration Closures || Penetration Closures
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || A1-region leak check <br> Laser hut work <br> RTP Cell Documentation || Prebuncher leak checks <br> Wien girder bake setup <br> Laser hut work || 1p: PSS Conduit WalkThru <br> Laser hut work || Begin Wien girder bake <br> Laser hut work || Laser hut work
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week24.png|1000px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 27 (Apr 5 - Apr 9) =
 +
<div class="mw-collapsible mw-collapsed">
 +
[[Phase 1 - HCO & Commissioning]]
 +
 
 +
 
 +
;'''Non-Tunnel Work'''
 +
* Laser box build (Bullard) ✅
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* Wien girder bake, bake takedown, leak check (Stutzman, Adderley) : '''Tuesday''' ✅
 +
* A1 cable terminations (Windham) ''Tuesday'' ✅
 +
* NEG activations (nine in total) (Stutzman, Adderley) : '''Monday''' ✅
 +
* Install under-girder cable trays (Electricians, Windham) : ''Thur'' ✅
 +
** Job WalkThru ''Tuesday''
 +
* Bond girders (Electricians, Windham) : ''Thur'' ✅
 +
* Move/attach HV patch box for UHV pumps (Adderley) : ''Fri'' ✅
 +
* Install PSS Kicker conduit (Bruhwel) : ''Fri'' ✅
 +
* Grout Wien pedestals (MechInstall) : ''Fri'' ✅
 +
* Laser box install (Bullard, Zhang) : ''next Monday''
 +
* Attach 15deg (DR) Dipole (CIS) : ''next Monday''
 +
* Re-attach Haimson (BH) corrector pairs (Adderley, Grames) : ''next Monday''
 +
* Re-attach Wien-quad (QW) fixtures (Adderley, Grames) : ''next Monday''
 +
* Install second air manifold (Bullard, Adderley) : ''Wed'' ✅
 +
* Complete LCW manifold install work (MechInstall) : ''Tues'' ✅
 +
* Laser hut penetration closure, sealing (no stone), Pb brick shielding (MechInstall) ''Fri'' ✅
 +
* Install Wien filter magnets ''Fri'' ✅
 +
 
 +
 
 +
;'''ISB Work '''
 +
* CIS Rack Work, IN01* (Windham)
 +
* Penetration re-fills, see [https://wiki.jlab.org/ciswiki/index.php/CIS_Phase_1_work_plans#Penetration_Work Penetration Work] below (MechInstall) ✅
 +
* Preps for penetration fills -- as needed, making space for chute to drop stones, IN02B10, IN02B23, IN03B04 (Moser) ✅
 +
* Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)
 +
* Mott DAQ VME crate power T/S, IN02B21 (Suleiman) ✅
 +
* Laser seed chassis safe-operation-lock-up work, IN01B05 (Zhang, Windham) ✅
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 4/5  !! style="background-color:#CFDCCA" |  Tue 4/6 !! style="background-color:#CFDCCA" |  Wed 4/7 !! style="background-color:#CFDCCA" |  Thu 4/8 !! style="background-color:#CFDCCA" |  Fri 4/9
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || Moving heavy items near crane -> TL || T || Preps for Penetration fills || Preps for Penetration fills || Penetration stone fills <br> (58, 86, 108)
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || M || T || W || R || Penetration stone fills <br> (58, 86, 108)
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day|| '''Wien girder bake''' || '''Wien bake takedown''' || CIS Mech Jobs || CIS Mech Jobs <br> Electrician Jobs || MechInstall Jobs <br> SSG Jobs <br> CIS Mech Jobs
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  NEG Activations || Wien/Y Leak Checks <br> A1 Cable Terminations <br> Cable Tray Job WalkThru || HV Patch Box Move <br> Install 2nd air manifold <br> BH, QW re-attachments ||  Cable tray install <br> Bond girders <br> BH, QW re-attachments <br> ''Laser box install'' || Laser hut pene <br> Grout Wien Pedestals <br> 9a: Kicker Conduit Install <br> Install Wien Magnets <br> Mount HV Patch Box
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || Laser hut work || Laser hut work || Laser hut work || Laser hut work || Laser hut work
 +
|}
 +
 
 +
 
 +
[[File:InjSB Week24.png|1000px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 28 (Apr 12 - Apr 16) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
[[Phase 1 - HCO & Commissioning]]
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* ''' ''System Reconnects and HCO'' '''
 +
 
 +
* Attach 15deg (DR) Dipole (Grames) ''Mon''
 +
* Re-attach Haimson (BH) corrector pairs (Grames) ''Mon''
 +
* Re-attach Wien-quad (QW) fixtures (CIS) ''Mon''
 +
 
 +
* UHV HV patch box relocation (Adderley) ''Tues''
 +
 
 +
* Wien pedestals wrap-up -- remove grout forms, cut all threads (MechInstall) ''Tues''
 +
* Under-girder cable tray lowering (Adderley) ''Tues''
 +
* Install laser box (Bullard) ''T+W''
 +
* Remove SS prebuncher bracket interfering with BH corrector placement (CIS?) ''Tues''
 +
 
 +
* Valve controls work (Ketchum, Windham)
 +
 
 +
* Vacuum work (Stutzman)
 +
** Ion pump cabling / controls checks ''Mon''
 +
** Activating NEGs ''Mon''
 +
** Hi-potting VIP1I07 ''Mon''
 +
** Hi-potting VIP1I02 ''Wed''
 +
** T/S VIP2I00 noise
 +
** De-gas stalk heater (Grames) ''Thur''
 +
 
 +
* Magnet hook-ups (DC Power -- Coleman, Delk, Kumar)
 +
 
 +
* LCW hook-ups (Adderley, Francis)
 +
 
 +
* 5D Line vacuum disconnects (CIS)
 +
 
 +
* A1 EPICS controls (Windham, Higgins)
 +
 
 +
* Gun HV evaluation (Hernandez-Garcia) ''Swings: W+Th''
 +
** Rapid Access probe placement (Washington) ''Wed''
 +
** Clean off gun table (CIS) ''Wed''
 +
** DecaRad placement verification (Hernandez-Garcia) ''Wed''
 +
** Disconnect and remove PIG (SF6 resistor tank) ''Thur''
 +
** Install ceiling plate for HV cable strain relief ''Thur''
 +
** Connect Gun directly to HVPS ''Thur''
 +
 
 +
* Prebuncher and chopper LCW connections (Wissman) ''Thur''
 +
* Prebuncher cabling (Wissman) ''Thur''
 +
 
 +
* 60Hz electrical noise snooping (Suleiman)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* ''' ''System re-connects / associated rack work'' '''
 +
* Wien HV cables pulls, IN01B0{0-8} (Dela Cruz) ''Wed''
 +
* A1 EPICS controls work (Windham, Higgins)
 +
 
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 4/12  !! style="background-color:#CFDCCA" |  Tue 4/13 !! style="background-color:#CFDCCA" |  Wed 4/14 !! style="background-color:#CFDCCA" |  Thu 4/15 !! style="background-color:#CFDCCA" |  Fri 4/16 !! Sa 4/17 !! Su 4/18
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || '''System Reconnects''' <br> CIS Rack Work || '''System Reconnects''' <br> CIS Rack Work || '''System Reconnects''' <br> CIS Rack Work || '''System Reconnects''' <br> CIS Rack Work || '''System Reconnects''' <br> CIS Rack Work || Drone Elevation Survey  || Su
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Early Morning (<9a) || ''Associated Rack Work''  || ''Associated Rack Work'' || '''6a: Wien HV Cable Pulls''' <br> ''Associated Rack Work'' || ''Associated Rack Work'' <br> Terminating Wien HV Cables || ''Associated Rack Work'' || Sa || Su
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning || A1 EPICS controls <br> ''Associated Rack Work'' || ''Associated Rack Work'' || ''Associated Rack Work'' || ''Associated Rack Work'' <br> Terminating Wien HV Cables || ''Associated Rack Work'' || Sa || Su
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || ''Associated Rack Work'' || ''Associated Rack Work'' || ''Associated Rack Work'' <br> A1 EPICS controls || ''Associated Rack Work'' || ''Associated Rack Work'' || Sa || Su
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day|| CIS Vacuum Checkout || CIS Vacuum Checkout || CIS Vacuum Checkout || Air Manifold Plumbing/Install <br> CIS Vacuum Checkout || CIS Vacuum Checkout || Sa || Su
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Early Morning (<9a) || <s>Wien pedestal wrap-up </s> || '''Wien pedestal wrap-up''' || '''Wien HV Cable Pulls''' <br> Air Manifold Install <br> Viewer/Valve Solenoid Layout <br> LCW Hook-ups || Viewer/Valve Connections || Viewer/Valve Connections <br> ''Terminating Wien HV Cables?'' <br> LCW Hook-ups || Sa || Su
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  Laser box fit-test <br> 11a: Re-attach DR, BH magnets <br> Re-attach QW fixtures <br> '''Vacuum work''' <br> LCW Hook-ups <br> A1 EPICS controls || ''' ''Cable Tray Lowering'' ''' <br> Vacuum+Valve work <br> LCW Hook-ups <br> HV patch box remount <br> Laser box install <br> Prebuncher bracket removal || Rapid Access probe <br> Air Manifold Install <br> VIP2I00 T/S <br> Valve controls <br> Finishing laser box install <br> Laser hut work || 9a: Viewer/valve Solenoid Layout <br> Remove PIG <br> De-gas stalk heater <br> Prebuncher LCW and Cabling <br> Valve controls <br> LCW Interlock Checkout || Valve controls <br> Viewer reconnects <br> LCW Hook-ups <br> Laser box sealing || Sa || 9a: '''Magnet Hook-Ups''' <br> 60Hz Snooping
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || '''Vacuum Work''' <br> Laser Hut Work || '''Magnet Hook-Ups''' <br> Laser Hut Work || De-gas stalk heater <br> Gun HV Eval Preps <br> '''Magnet Hook-Ups''' <br> Laser Hut Work <br> '''430p: Lock-up to Power Permit'''  <br> Gun HV Eval || '''Magnet Hook-Ups''' <br> Laser Hut Work <br> 4p: Neilson WalkThru <br> '''430p: Lock-up to Power Permit''' <br> Gun HV Eval || '''Magnet Hook-Ups''' <br> Laser Hut Work || Sa || '''Magnet Hook-Ups''' <br> 60Hz Snooping
 +
|}
 +
 
 +
 
 +
''' ''4/16: Weekend work plans in the Injector?'' '''
 +
 
 +
 
 +
* BPM = Francis
 +
* Valve Controls = Ketchum
 +
* ItoV, Picoammeters, Gun FSD Interlocks = Francis
 +
* Viewers = Norris
 +
* Harps = Dela Cruz
 +
* Magnet / DC Power = Coleman, others in group
 +
* 2B Alignment = S&A, Gould
 +
* PSS = Kowal
 +
 
 +
 
 +
[[File:InjSB Racks no pene.png|1000px]]
 +
 
 +
</div>
 +
 
 +
= Week 29 (Apr 19 - Apr 23) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
[[Phase 1 - HCO & Commissioning]]
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* ''' ''System Reconnects and HCO'' '''
 +
 
 +
* Laser->photocathode alignment, retro-reflection measurement (Zhang, Grames, Windham)
 +
 
 +
* Vacuum work (Stutzman)
 +
** T/S VIP2I00 noise
 +
** Relocating VCG5D01 to main beamline, ATLis 22270 (Stutzman) ''Tues''
 +
** Pumping down 5D "stub" (i.e. remaining 5D beamline) (Stutzman) ''Tues''
 +
 
 +
* Plumbing air lines to viewers (CIS, Norris)
 +
* Air line system-segmentation (viewer, beamline valves) (Stutzman, Bullard)
 +
 
 +
* Magnet hook-ups (DC Power -- Coleman, Delk, Kumar) ''Afternoons''
 +
** MDR1I02 attachment (Grames) ''Tues''
 +
 
 +
* Diagnostics reconnects ''Mornings''
 +
** Viewers (Norris)
 +
** Harps (Dela Cruz)
 +
** BPMs, Picoammeters, ItoV (Francis)
 +
 
 +
* LCW Flow measurement through flow meters that interlock cups and apertures (Francis) ''Mon''
 +
* PCup flowmeter enhanced testing (Francis)
 +
* 2I BPM hook-ups (Francis) ''Tues''
 +
 
 +
* LCW hook-ups (Adderley, Francis)
 +
 
 +
* Wien HV cable terminations (Dela Cruz)
 +
 
 +
* A1 EPICS controls (Windham, Higgins) ''Tues''
 +
 
 +
* Warm RF Work (Wissman, Farrish)
 +
** Chopper, prebuncher, amplifier hook-ups ''Mon''
 +
** Chopper water line leak repair ''Mon''
 +
** LLRF testing and adjustments for prebuncher ''Tues''
 +
** Powering on prebuncher, choppers ''W-F''
 +
** Prebuncher tuning ''Wed''
 +
** Chopper tuning
 +
 
 +
* Mech bracket walkthru (Gregory, Grames) ''Mon''
 +
 
 +
* 60Hz electrical noise snooping (Suleiman) ''Evenings (after 4p)''
 +
 
 +
* PSS Kicker removal (SSG) ''Thur''
 +
* Unlocking FC1, locking in A3/A4 apertures (SSG) ''Thur''
 +
 
 +
* PCup-A1 Region (VBV1I07->0I02) & A2-FC1 Region (VBV0I02->0I07) Bake Prep
 +
** Remove PSS kicker, push back conduit (SSG)
 +
** Remove instrument solenoids from girders (Dela Cruz)
 +
** Move back non-bakable cables, air lines (CIS)
 +
** Staging insulation, oven equipment (Bullard)
 +
** Leak checks (Stutzman)
 +
** Ion pump evaluations
 +
** Gasket swaps ''Fri''
 +
 
 +
 
 +
;'''ISB Work '''
 +
* ''' ''System re-connects / associated rack work'' '''
 +
* A1 EPICS controls work (Windham, Higgins)
 +
* iocin1 VME crate swap, IN03B04 (Dela Cruz), ''Mon 9a''
 +
* Wien HV System, IN01B0{0,1} (Dela Cruz)
 +
* Safety WalkThru (Moser, Fanning, Johnson, Williams) ''Tues 230p''
 +
* Magnet Cabling, IN02B{10,11,22,26}, IN04B10  (DC Power, Coleman)
 +
* Bunchlength amp re-install, IN02B23 (Musson)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color:#CFDCCA" | '''Location'''<br>Time !! style="background-color:#CFDCCA" | Mon 4/19  !! style="background-color:#CFDCCA" |  Tue 4/20 !! style="background-color:#CFDCCA" |  Wed 4/21 !! style="background-color:#CFDCCA" |  Thu 4/22 !! style="background-color:#CFDCCA" |  Fri 4/23
 +
|- style="background-color:#AFDCEA"
 +
| '''InjSB'''<br> All Day || '''System Reconnects''' <br> CIS Rack Work || '''System Reconnects''' <br> CIS Rack Work || '''System Reconnects''' <br> CIS Rack Work || System ~Reconnects <br> CIS Rack Work || System ~Reconnects <br> CIS Rack Work
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Early <br> Morning <br> (<9a) || ''Associated Rack Work'' || ''Associated Rack Work'' || ''Associated Rack Work'' || Wien HV System || Wien HV System
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Morning ||  ''Associated Rack Work'' || '''9a: iocin1 VME Crate Swap''' <br> Wien HV Cable Termination <br> Prebuncher LLRF <br> ''Associated Rack Work'' || Wien HV Cable Terminations <br> ''Associated Rack Work'' || Wien HV System <br> Warm RF Cabling || Wien HV System <br> Bunchlength amp re-install
 +
|- style="background-color:#BFDCDA"
 +
| '''InjSB'''<br> Afternoon || ''Associated Rack Work'' || Prebuncher LLRF <br> ''Associated Rack Work'' || ''Associated Rack Work'' || Magnet Cabling || Magnet Cabling
 +
|- style="background-color:#EFDCAA"
 +
| '''Tunnel'''<br> All Day|| CIS Vacuum Work -- <br> VBV2I01A Solenoid || CIS Vacuum Work -- <br> *Relocating VCG5D01 <br> *5D stub pumpdown || CIS Vacuum Work -- <br> *Valving in CCG <br> to main beamline || '''VBV1I07->0I07 Leak Checks'''<br>'''Bake Prep''' || '''PCup-A1 / A2-FC1 regions <br> Bake Prep - Gasket Swaps'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Early <br> Morning <br> (<9a) || '''Viewer Reconnects''' <br> || '''Viewer Reconnects''' <br> PCup Flowmeter || '''Viewer Reconnects''' <br> ''Wien HV cable terminations?'' || Wien HV cable terminations || Wien HV cable terminations
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Morning ||  915a Mech Bracket Walkthru <br> 2I BPM Connections <br> Viewer air lines <br> Flowmeter flow measurement || Viewer Reconnects <br> 2I BPM Hook-ups <br> Air line system segmentation || Viewer Reconnects <br> ''Wien HV cable terminations?'' <br> Air line system segmentation <br> Prebuncher Tuning/Controls <br> Laser hut work || '''Leak Checks''' <br> VBV2I01A T/S, Repair <br> Unlock FC1, Lock-In A3/A4 <br> '''Bake Prep:''' <br> PSS Kicker Removal <br> Instrument Solenoid Dismounts <br> Oven/insulation staging || '''Bake Prep - Gasket Swaps'''
 +
|- style="background-color:#DFDCBA"
 +
| '''Tunnel'''<br> Afternoon || '''Magnet hook-ups''' <br> Laser Hut Work || '''Magnet hook-ups''' <br> A1 EPICS Controls <br> 230p: Safety WalkThru <br> Laser Hut Work || <s> MDR1I02 attachment <br> '''2p: Laser->cathode alignment''' </s> <br> '''Vacuum Recovery''' || '''Bake Prep''' <br> Prebuncher testing/tuning <br> 5D-VCG cabling || '''Bake prep - Gasket Swaps'''
 +
|}
 +
 
 +
'''WEEKEND WORK PLANS??'''
 +
 
 +
Tunnel Personnel Loading Limits: '''Injector''', upstream of plastic curtain, '''total=8 -> 4 upstream of laser hut, 4 downstream of laser hut'''
 +
 
 +
[[File:InjSB Racks no pene.png|1000px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 30 (Apr 26 - Apr 30) =
 +
<div class="mw-collapsible mw-collapsed">
 +
[[Phase 1 - HCO & Commissioning]]
 +
 
 +
 
 +
[[File:Screen Shot 2021-04-23 at 8.33.33 AM.png | 900px]]
 +
 
 +
 
 +
;'''Tunnel work '''
 +
* '''Re-Bake Work'''
 +
** As-found surveys of A1, A2 (S&A) ''Mon''
 +
** Continue ion pump evaluations
 +
** Vent VBV1I07->0I07 and swap gaskets ''Mon''
 +
*** Decided NOT to swap A2 gaskets at this time
 +
** Re-align A1 (S&A) ''Mon''
 +
** Rough pumpdown of VBV1I07->0I02 region (A1-region) ''Mon''
 +
** Leak checks VBV1I07->0I07 ''Mon/Tues''
 +
** Bake setup ''Tues-Wed''
 +
** Begin A1-region (VBV1I07->0I02) re-bake ''Wed+''
 +
** NEG activations --
 +
*** Unbaked region, A2 (0I02) and 0I07 DP Can ''Tues''
 +
*** Baked A1-region, 0I00 DP Can and A1 (0I01A)
 +
 
 +
* VBV2I01A Position Indication and Solenoid T/S, Documentation, Verification (Windham) ''Mon''
 +
 
 +
* Laser->photocathode alignment, retro-reflection measurement (Zhang, Grames, Windham) ''Tues''
 +
 
 +
* Wien HV cable terminations (Dela Cruz)
 +
 
 +
* Viewer reconnects and HCO (Norris)
 +
 
 +
* Magnet Connections and HCO (Coleman)
 +
** Layout terminal blocks
 +
** Magnet lead reinforcement
 +
** Magnet wiring
 +
** Install MDR1I02 (CIS, Grames)
 +
 
 +
* Warm RF Work (Wissman, Farrish)
 +
** Prebuncher conditioning
 +
** Prebuncher readback calibrations
 +
** Chopper tune-check/tuning
 +
 
 +
* 60Hz electrical noise snooping (Suleiman) ''Evenings (after 4p)''
 +
 
 +
* System re-connects and HCO (EES, CIS, Ops)
 +
 
 +
 
 +
;'''ISB Work '''
 +
* ''' ''System re-connects / associated rack work'' '''
 +
* CIS Rack Work, IN01* (Windham)
 +
* Viewer Terminations, IN01B04 (Norris, Mock) ''Mon-Tues''
 +
* Harp cabling, terminations, IN01B03, IN03B0{6,7} (Dela Cruz) ''Tues''
 +
* Magnet Cabling, IN02B{10,11,22,26}, IN04B10  (DC Power, Coleman)
 +
* Wien HV System, IN01B0{0,1} (Dela Cruz)
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align:center; background-color:#BFDCDA;"
 +
|- style="font-weight:bold; background-color:#CFDCCA;"
 +
! style="vertical-align:middle; background-color:#CFDCCA" | '''Location'''<br />Time
 +
! style="vertical-align:middle;background-color:#CFDCCA" | Mon 4/26
 +
! style="vertical-align:middle;background-color:#CFDCCA" | Tue 4/27
 +
! style="vertical-align:middle;background-color:#CFDCCA" | Wed 4/28
 +
! style="vertical-align:middle;background-color:#CFDCCA" | Thu 4/29
 +
! style="vertical-align:middle;background-color:#CFDCCA" | Fri 4/30
 +
! style="vertical-align:middle;background-color:#CFDCCA" |Sat 5/1
 +
! style="vertical-align:middle;background-color:#CFDCCA" | Sun 5/2
 +
|- style="background-color:#AFDCEA;"
 +
| style="vertical-align:middle;" | '''InjSB'''<br /> All Day
 +
| style="vertical-align:middle;" | Systems HCO <br /> CIS Rack Work
 +
| style="vertical-align:middle;" | Systems HCO <br /> CIS Rack Work
 +
| style="vertical-align:middle;" | Systems HCO <br /> CIS Rack Work
 +
| style="vertical-align:middle;" | Systems HCO <br /> CIS Rack Work
 +
| style="vertical-align:middle;" | Systems HCO <br /> CIS Rack Work
 +
|
 +
|
 +
|-
 +
| style="vertical-align:middle;" | '''InjSB'''<br /> Early <br /> Morning <br /> <9a
 +
| style="vertical-align:middle;" | Viewer Terminations
 +
| style="vertical-align:middle;" | Viewer Terminations<br />Harp Cabling/Terminations
 +
| style="vertical-align:middle;" | ''Associated Rack Work''
 +
| style="vertical-align:middle;" | ''Associated Rack Work''
 +
| style="vertical-align:middle;" | ''Associated Rack Work''
 +
|
 +
|
 +
|-
 +
| style="vertical-align:middle;" | '''InjSB'''<br /> Morning
 +
| style="vertical-align:middle;" | Viewer Terminations
 +
| style="vertical-align:middle;" | Viewer Terminations<br />Harp Cabling/Terminations
 +
| style="vertical-align:middle;" | ''Associated Rack Work''
 +
| style="vertical-align:middle;" | ''Associated Rack Work''
 +
| style="vertical-align:middle;" | ''Associated Rack Work''
 +
| style="vertical-align:middle;" | Chopper Hook-Ups
 +
|
 +
|-
 +
| style="vertical-align:middle;" | '''InjSB'''<br /> Afternoon
 +
| style="vertical-align:middle;" | Magnet Cabling, HCO
 +
| style="vertical-align:middle;" | Magnet Cabling, HCO
 +
| style="vertical-align:middle;" | Magnet Cabling, HCO
 +
| style="vertical-align:middle;" | Magnet Cabling, HCO
 +
| style="vertical-align:middle;" | Magnet Cabling, HCO
 +
|
 +
| style="vertical-align:middle;" | Magnet Cabling, HCO
 +
|- style="background-color:#EFDCAA;"
 +
| style="vertical-align:middle;" | '''Tunnel'''<br /> All Day
 +
| style="vertical-align:middle;" | '''A1/A2 gasket swaps'''
 +
| style="vertical-align:middle;" | VBV1I07->0I02 = A1-region <br /> '''Bake Setup'''
 +
| style="vertical-align:middle;" | '''A1-region Re-Bake'''
 +
| style="vertical-align:middle;" | '''A1-region Re-Bake'''
 +
| style="vertical-align:middle;" | '''A1-region Re-Bake'''
 +
| '''A1-region Re-Bake<br />Rampdown'''
 +
| '''A1-region Re-Bake<br />Rampdown'''
 +
|- style="background-color:#DFDCBA;"
 +
| style="vertical-align:middle;" | '''Tunnel'''<br /> Early <br /> Morning <br /> <9a
 +
| style="vertical-align:middle;" | '''As-found surveys A1, A2''' <br /> Diagnostics HCO/Reconnects <br /> ''as possible'' <br /> Wien HV Cable Terminations
 +
| style="vertical-align:middle;" | Diagnostics HCO/Reconnects <br /> ''as possible'' <br /> 0I02 Anti-collision/harp
 +
| style="vertical-align:middle;" | Viewer Reconnects <br /> Wien HV terminations
 +
| style="vertical-align:middle;" | Viewer Reconnects<br />  Wien HV terminations
 +
| style="vertical-align:middle;" | Viewer Reconnects<br /> '''7-8a: LCW Tests'''
 +
|
 +
|
 +
|- style="background-color:#DFDCBA;"
 +
| style="vertical-align:middle;" | '''Tunnel'''<br /> Morning
 +
| style="vertical-align:middle;" | '''A1 Gasket Swaps <br /> Re-Alignment <br /> Rough Pumpdown''' <br /> Wien HV Cable Terminations <br /> Ion pump checkout <br /> VBV2I01A Work
 +
| style="vertical-align:middle;" | Final A1-region leak check <br /> VIP0I0{0,1,1A,2} FE Hunt<br />A1-region Bake Setup <br /> 0I02 NEG Activation <br /> Prebuncher conditioning
 +
| style="vertical-align:middle;" | '''930-10a: Hoey Safety WalkThru'''<br />Viewer Reconnects<br /> Wien HV terminations <br /> Prebuncher conditioning<br /> Cable Org/Vert Tray
 +
| style="vertical-align:middle;" | Viewer Reconnects<br />Prebuncher conditioning <br /><br />
 +
| style="vertical-align:middle;" | Viewer Reconnects<br />Prebuncher conditioning<br />0I07 NEG Activation
 +
| 0I0{0,1A} NEG Activations <br> Chopper Hook-Ups
 +
| 11a: Magnet reconnects and HCO
 +
|- style="background-color:#DFDCBA;"
 +
| style="vertical-align:middle;" | '''Tunnel'''<br /> Afternoon
 +
| style="vertical-align:middle;" | A1 rough pumpdown <br /> Leak checks VBV1I07->0I07 <br /> VBV2I01A Work
 +
| style="vertical-align:middle;" | '''Begin A1-region Bake'''<br />Laser alignment/retroreflection<br />Prebuncher conditioning < ~2p<br />Magnet HCO/Reconnects <br /> ''as possible''
 +
| style="vertical-align:middle;" | Prebuncher conditioning<br /> Cable Org/Vert Tray <br /> Magnet HCO/Reconnects <br /> ''as possible'' <br /> Laser Hut Work
 +
| style="vertical-align:middle;" | 1p: PD WalkThru <br /> Prebuncher conditioning<br />Magnet HCO/Reconnects <br /> ''as possible'' <br /> Laser Hut Work
 +
| style="vertical-align:middle;" | Prebuncher Conditioning<br />Magnet HCO/Reconnects <br /> ''as possible'' <br /> Laser Hut Work
 +
|
 +
| Magnet reconnects and HCO
 +
|}
 +
 
 +
Tunnel Personnel Loading Limits: '''Injector''', upstream of plastic curtain, '''total=8 -> 4 upstream of laser hut, 4 downstream of laser hut'''
 +
 
 +
 
 +
[[File:InjSB Week30_1.png|950px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 31 (May 3 - May 7) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Tunnel work '''
 +
* ''' ''System re-connects and HCO'' ''' (EES, CIS, Ops)
 +
 
 +
 
 +
* A1-region bake takedown (Stutzman, Bullard) ''Mon''
 +
* VBV2I01A Solenoid Air Leak T/S (Windham) ''Mon''
 +
* Laser hut work (Zhang)
 +
* Photocathode shuffle (Grames)
 +
** Remove bulk GaAs
 +
** Load in SSL cathodes
 +
** Activate cathode
 +
* Ion pump checkout (Stutzman)
 +
** Set operational voltages
 +
** Hi-pot FE'ing pumps
 +
** Configure system for EPICS
 +
 
 +
 
 +
* Main airline leaky valve swap [[Airline Valve Changeout| (pics)]] (MechInstall) ''Thurs''
 +
 
 +
* Viewer reconnects and HCO (Norris)
 +
* Harp reconnects and HCO (Dela Cruz)
 +
 
 +
* Magnet Connections and HCO (Coleman)
 +
** Layout terminal blocks
 +
** Magnet lead reinforcement
 +
** Magnet wiring
 +
** Install MDR1I02 (CIS, Grames)
 +
 
 +
* Warm RF HCO (Wissman, Farrish)
 +
** Chopper turn-on, conditioning
 +
** Buncher turn-on, conditioning
 +
** Capture turn-on, conditioning
 +
** Prebuncher readback calibrations, GDR operation (Plawski)
 +
 
 +
* 60Hz electrical noise snooping (Suleiman) ''Sat''
 +
* Helicity magnet HCO (Suleiman) ''Sat''
 +
 
 +
;'''ISB Work '''
 +
* ''' ''System re-connects / associated rack work'' '''
 +
* CIS Rack Work, IN01* (Windham)
 +
* Magnet Cabling, IN02B{10,11,22,26}, IN04B10  (DC Power, Coleman)
 +
* Wien HV System, IN01B0{0,1} (Dela Cruz)
 +
* Penetration 78 (IN02B18) and 86 (IN02B23) Stone Top-Off (MechInstall) ''Tues early AM''
 +
 
 +
* VEPCO Automatic Voltage Regulators Test, ATLis 22392 ''Friday''
 +
** Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
 +
** Incoming power voltage variation < +/- 10%
 +
** "Be prepared for a power interruption"
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
{| class="wikitable" style="text-align:center; vertical-align:middle; background-color:#BFDCDA;"
 +
|- style="font-weight:bold; background-color:#CFDCCA;"
 +
! style="background-color:#CFDCCA" | '''Location'''<br />Time
 +
! style="background-color:#CFDCCA" | Mon 5/3
 +
! style="background-color:#CFDCCA" | Tue 5/4
 +
! style="background-color:#CFDCCA" | Wed 5/5
 +
! style="background-color:#CFDCCA" | Thu 5/6
 +
! style="background-color:#CFDCCA" | Fri 5/7
 +
! style="background-color:#CFDCCA" | Sa 5/8
 +
! style="background-color:#CFDCCA" | Su 5/9
 +
|- style="background-color:#AFDCEA;"
 +
| '''InjSB'''<br /> All Day
 +
| Systems HCO <br /> CIS Rack Work
 +
| Systems HCO <br /> CIS Rack Work
 +
| Systems HCO <br /> CIS Rack Work
 +
| Systems HCO <br /> CIS Rack Work<br /> <s>'''⚡VEPCO Voltage Tests'''</s>
 +
| Systems HCO <br /> CIS Rack Work
 +
|
 +
|
 +
|-
 +
| '''InjSB'''<br /> Early <br /> Morning <br /> <9a
 +
| ''Associated Rack Work''
 +
| Chopper/Buncher HCO
 +
| Chopper/Buncher HCO
 +
| Buncher/Chopper HCO
 +
| Viewer/harp HCO
 +
|
 +
|
 +
|-
 +
| '''InjSB'''<br /> Morning
 +
| Chopper/Buncher HCO <br /> Prebuncher Rdbk Cals
 +
| Chopper/Buncher HCO <br /> Wien Sys Walkthru  <br /> '''Pene 78 & 86 Top-Off'''
 +
| Chopper/Buncher HCO <br /> Wien HV Cable Chkout
 +
| Buncher/Chopper HCO
 +
| Chopper Vac Intlk Testing <br> 9-11a: Wien HV Calibrations <br> VBV0I02 UHV Interlocks
 +
| Magnet HCO
 +
| ''Magnet HCO''
 +
|-
 +
| '''InjSB'''<br /> Afternoon
 +
| Chopper/Buncher HCO<br /> Prebuncher Rdbk Cals <br /> Magnet re-connects, HCO
 +
| Chopper/Buncher HCO<br />Magnet re-connects, HCO
 +
| Chopper/Buncher HCO<br />Magnet re-connects, HCO
 +
| Magnet re-connects, HCO <br /> 4p: Capture HCO, Conditioning
 +
| Magnet re-connects, HCO <br> VBV0I02 UHV Interlocks
 +
| Magnet HCO
 +
| ''Magnet HCO''
 +
|- style="background-color:#EFDCAA;"
 +
| '''Tunnel'''<br /> All Day
 +
| CIS Reconnects<br />'''A1-region Bake Takedown'''
 +
| '''CIS Vacuum Work''' <br /> Ion pump checkout <br /> VIP0I01/1A HiPot <br /> Device/line labeling <br /> '''Other CIS Jobs''' <br /> PCup, A1, A2 LCW <br /> PCup, A1 Current Pigtails <br /> Photocathode shuffle
 +
| '''CIS Laser Hut Work:''' <br /> *Laser checks <br /> *1/2 waveplate T/S
 +
| '''System Reconnects & HCO'''<br /> <s>'''⚡VEPCO Voltage Tests'''</s>
 +
| '''System Reconnects & HCO'''
 +
|
 +
|
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Early <br /> Morning <br /> <9a
 +
| Viewers (1 ppl) (away from A1) <br /> A1-region bake takedown
 +
| Viewers (1 ppl)<br />Wien Interlock Cables (1 ppl)<br /> CIS Jobs (1-2 ppl)
 +
| Viewers (1 ppl)<br />Harp / Wien (1 ppl)<br />BPM (1 ppl)<br />Buncher, Capture hook-ups (1 ppl)
 +
| 7a: Main Airline Valve Swap (2ppl)<br />Harp / Wien (1ppl)<br />Waterflow Interlocks /<br />ItoV System HCO (1 ppl)
 +
| * Craning in cage/suitcase  <br> for equipment removal (1-2ppl) <br> * Viewers (1 ppl)<br /> * Harp (1ppl)<br />
 +
|
 +
|
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Morning
 +
| Viewers (1 ppl)  (away from A1)<br /><br />A1-region Leak Checks
 +
| Viewers (1 ppl)<br />11-1130a: Wien Sys Walkthru (2 ppl)<br /> CIS Vac Work (1-2 ppl)
 +
| Viewers (1 ppl)<br />9a-noon: Wien HV Cable Chkout (2ppl)<br />BPM (1 ppl) <br /> A1, A2, PCup LCW (1 ppl)
 +
| Wien HV T/S (1-2 ppl)<br />Waterflow Interlocks /<br />ItoV System HCO (1 ppl)<br />Ion pump T/S (1ppl)<br />MDR1I02 Cabling (1ppl) <br> 1/2 waveplate T/S
 +
| Viewers (1 ppl)<br />9a: Wien HV Cals (1-2 ppl)<br />10a: IPM1I02 Connect/HCO (1-2ppl)<br />NEG Terminations (1ppl) <br> 1/2 waveplate T/S
 +
| Magnet Resistances, Inductances, Mapping (1-2ppl)
 +
| ''Magnet Resistances, Inductances, Mapping (1-2ppl)''
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Afternoon
 +
| A1-region reattachments -- <br />air/water lines, pickups, <br />control boxes/solenoids
 +
| Magnet (2-4 ppl)<br />
 +
| Magnet (3 ppl)<br /> Swings (4p): Lock-up, 0L02 HPA PSS Cert <br /> After: PSS Kicker Install
 +
| Magnet (2-4 ppl)<br /> Laser hut work <br> 4p: Lock-up for Capture HCO
 +
| Magnet (2-4 ppl)<br /> Laser hut work <br> 4p: PSS Kicker install (1-2ppl)
 +
| Magnet Resistances, Inductances, Mapping (1-2ppl) <br> 60Hz Snooping (1ppl) <br> Helicity Mag HCO (1ppl)
 +
| ''Magnet Resistances, Inductances, Mapping (1-2ppl)''
 +
|}
 +
Tunnel Personnel Loading Limits: '''Injector''', upstream of plastic curtain, '''total=8 -> 4 upstream of laser hut, 4 downstream of laser hut'''
 +
 
 +
[[File:InjSB Week30 1.png|1000px]]
 +
 
 +
Points of Contact by system --
 +
* BPM = Francis
 +
* Valve Controls = Ketchum
 +
* ItoV, Picoammeters, Gun FSD Interlocks = Francis
 +
* Viewers = Norris
 +
* Harps = Dela Cruz
 +
* Wien = Dela Cruz
 +
* Magnet / DC Power = Coleman
 +
* Warm RF -- prebuncher, buncher, chopper, capture = Wissman
 +
* 2B Alignment = S&A, Gould
 +
* PSS = Kowal
 +
 
 +
</div>
 +
 
 +
= Week 32 (May 10 - May 14) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
;'''Tunnel work '''
 +
* '''Finish HCO''' ====> '''Beam Commissioning!'''
 +
** First CEBAF beam of 2021
 +
** First ~4m of Injector newly upgraded
 +
 
 +
 
 +
* Equipment crane-out (MechInstall)
 +
 
 +
* Viewer HCO (Norris)
 +
* Harp 0I02 electronics install and HCO (Dela Cruz)
 +
* Magnet HCO (Coleman)
 +
 
 +
* CIS HCO
 +
** Laser alignment optimization (Zhang)
 +
** 1/2 Waveplate T/S (Windham)
 +
** Photocathode activation (Grames)
 +
** Wien system HCO (Hernandez-Garcia, Dela Cruz)
 +
** Ion pump noise investigation (Stutzman)
 +
 
 +
 
 +
* 60Hz electrical noise snooping (Suleiman) ''evenings''
 +
 
 +
 
 +
;'''ISB Work '''
 +
* CIS Rack Work, IN01* (Windham)
 +
* Wien System HCO, IN01B0{0,1} (Dela Cruz, Hernandez-Garcia)
 +
* ItoV System Checkout, FC2 unlock (Francis) ''Mon''
 +
* Magnet HCO, IN02B{10,11,26}+IN04B10 (Coleman)
 +
* Viewer HCO, IN01B04+IN03B0{6,7} (Norris)
 +
* Harp HCO, IN01B03+IN03B06 (Dela Cruz)
 +
 
 +
 
 +
* VEPCO Automatic Voltage Regulators Test, ATLis 22392 ''Tuesday, 1030a - noon (if all goes well)''
 +
** Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
 +
** Incoming power voltage variation < +/- 10%
 +
** "Be prepared for a power interruption"
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
 
 +
:: ''italics = timing less certain''
 +
 
 +
{| class="wikitable" style="text-align:center; vertical-align:middle; background-color:#BFDCDA;"
 +
|- style="font-weight:bold; background-color:#CFDCCA;"
 +
! style="background-color:#CFDCCA" | '''Location'''<br />Time
 +
! style="background-color:#CFDCCA" | Mon 5/10
 +
! style="background-color:#CFDCCA" | Tue 5/11
 +
! style="background-color:#CFDCCA" | Wed 5/12
 +
! style="background-color:#CFDCCA" | Thu 5/13
 +
! style="background-color:#CFDCCA" | Fri 5/14
 +
! style="background-color:#CFDCCA" | Sa <br />5/15
 +
! style="background-color:#CFDCCA" | Su <br />5/16
 +
|- style="background-color:#AFDCEA;"
 +
| '''InjSB'''<br /> All Day
 +
| '''Hot Checkout'''
 +
| '''Hot Checkout'''
 +
| '''⚡VEPCO Voltage Tests<br />9-11a'''<br />'''Hot Checkout'''
 +
| '''Hot Checkout'''
 +
| '''Hot Checkout''' <br> '''Service Building Clean-Up'''
 +
| '''Site Phone Outages<br />8a - 5p'''
 +
|
 +
|-
 +
| '''InjSB'''<br /> Early <br /> Morning <br /> <9a
 +
| Viewer HCO <br /> ItoV/Picoam. HCO
 +
| Viewer HCO<br />Harp HCO
 +
| Viewer HCO<br />Harp Cross-Connect Wiring, HCO
 +
| ItoV System HCO
 +
|
 +
|
 +
|
 +
|-
 +
| '''InjSB'''<br /> Morning
 +
| V-Wien Comm Conn Remedying
 +
| Magnet HCO
 +
| ItoV HCO<br /> Magnet HCO
 +
| Wien HV Interlock<br />Testing and HV Soak
 +
| Wien HV Soak (+B-field?)
 +
|
 +
|
 +
|-
 +
| '''InjSB'''<br /> Afternoon
 +
| Magnet HCO
 +
| Magnet HCO
 +
| Magnet HCO
 +
| Wien HV Soak<br />Magnet HCO
 +
| Wien HV Soak<br />Magnet HCO
 +
|
 +
|
 +
|- style="background-color:#EFDCAA;"
 +
| '''Tunnel'''<br /> All Day
 +
| '''Hot Checkout'''
 +
| '''Hot Checkout''' <br /> CIS Work -- <br /> * Airline->metal <br /> * IP Noise T/S
 +
| '''⚡VEPCO Voltage Tests<br />9-11a'''<br />'''Hot Checkout'''<br />CIS Work
 +
| '''2B Alignment'''<br />'''Hot Checkout'''
 +
| '''2B Alignment'''<br />'''Hot Checkout''' <br> CIS Jobs = Gun Valve T/S <br> TMG shutter T/S
 +
| Wien HV Soak <br> '''Site Phone Outages<br />8a - 5p'''
 +
| Wien HV Soak
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Early <br /> Morning <br /> <9a
 +
| Equipment crane-out (1-2 ppl)<br />Viewer HCO (1 ppl)<br />0I02 harp electronics (1ppl)
 +
| Photocathode activation (1ppl) <br /> Viewer HCO (1ppl)<br />Harp HCO (1ppl)
 +
| Viewer HCO (1 ppl)<br />0I02 anti-collision testing (1 ppl) <br />ItoV/Picoam. HCO (1ppl)
 +
| 2B Alignment (2 ppl)
 +
| 2B Alignment (2 ppl) <br> 0I02 Anti-collision (1 ppl) <br> CIS Jobs (1-2ppl)
 +
|
 +
|
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Morning
 +
| Viewer HCO (1 ppl)<br />Wien interlock (1-2ppl)<br />Ion pump noise (1 ppl)<br />1/2 waveplate T/S
 +
| Viewer HCO (1 ppl)<br />Harp HCO (1 ppl)<br />CIS Work (1-2ppl)<br />1/2 waveplate T/S
 +
| 830-9a: Cryo tour (3ppl)<br />Viewer HCO (1 ppl)<br />0I02 anti-collision testing (1 ppl)<br />ItoV/Picoam. HCO (1ppl)<br />CIS Work (1-2ppl)
 +
| 2B Alignment (2 ppl)
 +
| 2B Alignment (2ppl) <br> 0I02 Anti-collision (1 ppl) <br> CIS Jobs (1-2ppl) <br> Laser Hut Work <br> FML HVAC Reconfig (2 ppl)?
 +
| 60 Hz Snooping (1ppl)
 +
|
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Afternoon
 +
| Laser hut work<br />Magnet HCO (2-4ppl)
 +
| Laser hut work<br />Magnet HCO (2-4ppl) <br /> ''Photocathode activation (1 ppl)''
 +
| Laser hut work<br />Magnet HCO (2-4ppl)<br />'''4p Lock-Up''': PSS Certs -> BP
 +
| Laser hut work<br />Magnet HCO (2-4ppl)<br />'''4p Lock-Up''': PSS Certs -> BP
 +
| Laser hut work<br />Magnet HCO (2-4ppl) <br> QE Scan? (2 ppl)
 +
| 60 Hz Snooping (1ppl)
 +
|
 +
|}
 +
 
 +
Tunnel Personnel Loading Limits: '''Injector''', upstream of plastic curtain, '''total=8 -> 4 upstream of laser hut, 4 downstream of laser hut'''
 +
 
 +
 
 +
[[File:InjSB Week30 1.png|1000px]]
 +
 
 +
 
 +
Points of Contact by system --
 +
* BPM = Francis
 +
* Valve Controls = Ketchum
 +
* ItoV, Picoammeters, Gun FSD Interlocks = Francis
 +
* Viewers = Norris
 +
* Harps = Dela Cruz
 +
* Wien = Dela Cruz
 +
* Magnet / DC Power = Coleman
 +
* Warm RF -- prebuncher, buncher, chopper, capture = Wissman
 +
* 2B Alignment = S&A, Gould
 +
* PSS = Kowal
 +
 
 +
 
 +
</div>
 +
 
 +
= Week 33 (May 17 - May 21) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
 
 +
; HCO to 500keV [https://logbooks.jlab.org/entry/3877755 completed] 5/21
 +
; Beam Authorization [https://logbooks.jlab.org/entry/3877749 granted] 5/21
 +
 
 +
 
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22462?load=Task&task_id=22462&allComments=yes 22462 0I02 Harp Repair]
 +
** Wednesday: beamline component disconnects and vent, begin harp swap
 +
** Thursday: complete harp swap, pumpdown, leak check, verify harp operation, setup and begin overnight bake
 +
** Friday: Bake cool by 8AM. Re-install beamline components, re-HCO components
 +
 
 +
 
 +
* VEPCO Automatic Voltage Regulators Test, ATLis 22392
 +
** Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
 +
** Incoming power voltage variation < +/- 10%
 +
** "Be prepared for a power interruption"
 +
 
 +
 
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
 
 +
{| class="wikitable" style="text-align:center; vertical-align:middle; background-color:#BFDCDA;"
 +
|- style="font-weight:bold; background-color:#CFDCCA;"
 +
! style="background-color:#CFDCCA" | '''Location'''<br />Time
 +
! style="background-color:#CFDCCA" | Mon 5/17
 +
! style="background-color:#CFDCCA" | Tue 5/18
 +
! style="background-color:#CFDCCA" | Wed 5/19
 +
! style="background-color:#CFDCCA" | Thu 5/20
 +
! style="background-color:#CFDCCA" | Fri 5/21
 +
|- style="background-color:#AFDCEA;"
 +
| '''InjSB'''<br /> All Day
 +
| '''Service Building Clean-Up'''<br />'''Hot Checkout'''
 +
| '''Service Building Clean-Up''' <br> '''Hot Checkout'''
 +
| '''Service Building Clean-Up''' <br> '''Hot Checkout''' <br><s>⚡VEPCO Voltage Tests<br />1030a-noon (4th attempt?)</s>
 +
| '''Service Building Clean-Up''' <br> '''Hot Checkout'''
 +
| '''Service Building Clean-Up''' <br> '''Hot Checkout'''
 +
|-
 +
| '''InjSB'''<br /> Early <br /> Morning <br /> <9a
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| '''InjSB'''<br /> Morning
 +
| Magnet HCO
 +
| Magnet HCO
 +
| Magnet Rack HCO
 +
| Magnet Rack HCO
 +
|
 +
|-
 +
| '''InjSB'''<br /> Afternoon
 +
| Magnet HCO
 +
| Magnet HCO
 +
| Magnet Rack HCO
 +
| Magnet Rack HCO
 +
|
 +
|- style="background-color:#EFDCAA;"
 +
| '''Tunnel'''<br /> All Day
 +
| '''Wrapping up HCO'''<br />Wien HV Soak
 +
| '''Wrapping up HCO'''<br />Wien HV Soak<br />Beam Commissioning
 +
| '''0I02 Harp Repair''' <br /><s>⚡VEPCO Voltage Tests<br />1030a-noon (4th attempt?)</s>
 +
| '''Wrapping up Magnet HCO'''
 +
| 0I02-"region" Reconnects <br> ''Beam Commissioning?''
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Early <br /> Morning <br /> <9a
 +
| 0I02 anti-collision (1 ppl)<br />
 +
|
 +
| Turbopump hook-up at 0I06 (1ppl)
 +
|
 +
| 0I02-"region" reconnects <br> Wien Resistor LCW Fittings
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Morning
 +
| Magnet HCO (2-5ppl)
 +
| Magnet HCO <br> 11a: HCO Committee tour (3ppl)
 +
| 830-9a: Cryo tour (3ppl) <br> 0I02 Harp Repair (3ppl) <br> Laser mirror work
 +
| 0I02 NEG Activation <br> Bake Takedown (2ppl) <br> Magnet HCO (2-5ppl) <br> Wien resistor cooling <br>
 +
| 0I02-"region" Reconnects -- <br> Magnets <br> YAG, A2, BPM, Harp <br> PSS Kicker <br> <br> Wien resistor cooling
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Afternoon
 +
| ''Laser hut work?''<br />Magnet HCO (2-5ppl)<br />Evening: 60Hz snooping
 +
|
 +
| 0I02 Harp Repair (3ppl)
 +
| Magnet HCO (2-5ppl) <br> Wien resistor cooling <br>
 +
| '''12p Lock-up: M0 PSS Certs''' <br> Beam Auth <br> Transitioning to Beam Ops
 +
|}
 +
 
 +
Tunnel Personnel Loading Limits: '''Injector''', upstream of plastic curtain, '''total=8 -> 4 upstream of laser hut, 4 downstream of laser hut'''
 +
 
 +
[[File:InjSB Week30 1.png|1000px]]
 +
 
 +
</div>
 +
 
 +
= Penetration Work =
 +
<div class="mw-collapsible mw-collapsed">
 +
 
 +
'''4/9 Update:'''<br> All five penetrations that had been opened are now closed, sealed, and appropriate stone/Pb-brick shielding returned. {58, 86, 108, 135} - re-filled with stone and levels verified by RadCon. Laser hut penetration closed, sealed, and Pb brick shielding re-installed.
 +
 
 +
 
 +
'''4/2 Update:''' <br> Laser hut penetration remains open until conclusion of Wien/Y-chamber bake, early next week. (only gets closed and sealed, no stone) <br> 58, 86, and 108 closed and sealed. May be filled with stones at this point. <br> 135 remains open. To be closed, sealed, and filled next week.
 +
 
 +
 
 +
'''InjSB Penetrations that are open''' (click for pictures, last updated 2/18/21):
 +
'''[[PenetrationALH|above laser hut]], [[Penetration58|58]], [[Penetration86|86]], [[Penetration108|108]], [[Penetration135|135]]'''
 +
* 34ft from floor of InjSB to floor of Inj tunnel
 +
* 25ft from floor of InjSB to elevated Inj tunnel cable tray
 +
 
 +
'''Penetration Cable Pulls/Removals --'''
 +
* <strike>(C. Jones) Dehumidifier wire pull, penetration 135, ETA: end of week of 3/1
 +
* (Wissman) Pulling Prebuncher heater control cables, laser hut penetration, ETA: ~3/4 or 5
 +
* (FML) Add/pull flex conduit to laser hut, 86, and 108 penetrations
 +
** 86 and 108 too full for 2" flex pull
 +
** Laser hut deemed too full as well </strike>
 +
* (Dela Cruz) Pulling new Wien E-field HV cables, through flex conduit, laser hut penetration may be re-filled
 +
* <strike> Norris removing old Cat5 viewer cables </strike>
 +
* <strike> Norris pulling new viewer cables </strike>
 +
* <strike> Riad/Scott removing old Mott HV cables </strike>
 +
* <strike> Coleman pulling new Wien B-field magnet cables </strike>
 +
* <strike>Cole pulling new neutron detector cables (above 0L03) </strike>
 +
* <strike> Scott pulling motor control cables for A1++ </strike>
 +
 
 +
[[File:InjSB Racks.png | 1000px]]
 +
 
 +
 
 +
</div>
 +
 
 +
= Fire System Work =
 +
<div class="mw-collapsible mw-collapsed">
 +
Description of Task: Replacement of tunnel sprinkler piping, fire alarm control panels in B85 & B98, replacement of detection devices.
 +
 
 +
'''update 11/9:''' 25% of demo completed
 +
<br>
 +
'''update 11/23:''' demo completed
 +
<br>
 +
'''update 12/8:''' fire pipe installation in Injector <s>slated for Winter break ~12/21 - 1/3</s> <br> "The drawings needed prior to fabrication of the INJ fire pipe have not gone through the system." No fire pipe install work over winter break.
 +
<br>
 +
'''update 1/7/21:''' Tentative fire pipe install to occur week of 1/18 in tunnel. Should take 3-4 days, so with the holiday on Monday, likely the rest of the week. <br>Further fire pipe work upstairs in the service will also need 3-4 days, but won't be constant (i.e. contractor will be in and out).
 +
<br>
 +
'''update 1/18/21:''' New pipe arriving Fri 1/22. No install work week of 1/18.
 +
<br>
 +
'''update 1/20/21:''' fire pipe installation to begin 1/22 and continue over weekend 1/23+24.
 +
<br>
 +
'''update 2/1/21: fire pipe installation, air pressure and hydro tests complete.'''
 +
</div>

Latest revision as of 15:19, 23 May 2021

5/21/21 AIPINJ Phase I Installation and HCO Complete.

2020 Weeks 1 through 13

Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups

Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects

Fri 9/25 - Mon 9/28
  • CIS Gun Jobs
Wien electrode testing – 9am!!!
Gun HVPS lockout - DONE
Gun HV cable disconnect – DONE
Remove PIG – Coordinate w/ Neil for convenient time
Shukui - Laser outrigger table as-founds, remove components
Scott - Remove yellow box
Scott - Disconnect Decarad
Monday 9/28 Tasks (updated 0915 9/28)
  • Power down Wein system (Scott/Joe)
  • Power down and remove DecaRad system (Scott)
  • Return gun valve config to "normal" (Marcy)
  • Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
  • PSS Kickers and associated chassis removal (SSG)
  • Laser table disassembly (Shukui/Scott)
Tuesday 9/29 Tasks (updated 0930 9/29)
  • (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
  • (Done) Disconnect aperture and cup signal cables (Pete) 5a
  • Disconnect rad probes (Melvin) 8a
  • Tunnel magnet disconnects (Diggs, Delk) 10a
  • (Done) Removal of old chopper amps from rack (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • ODH Head Replacements (SSG)
  • Document existing Wein cabling and power off PS (Scott)
Wednesday 9/30 Tasks (updated 0900 9/30)
  • RF Prebuncher disconnects (Farrish) 6a
  • Vacuum Component Labeling (Greenfield, Gonzales) 430a
  • Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a
  • Tiny magnet removals (Scott, Grames) 9a
  • PSS Kicker Magnet removal (SSG) 9a
  • Sample hold cables install, InjSB (Francis)
  • Remaining PSS Interface chassis removal (SSG)
  • Harp upgrade to PC104 (Dela Cruz)
  • Moser transfers CCOC phone @1430, to reach moving forward x5089
Thursday 10/1 Tasks (updated 0830 10/1)
  • Picoammeter Removal, InjSB (Francis) 5a
  • Sample hold cables install, IN02B24 (Francis)
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
  • Disconnecting water and air lines from apertures and cups (Adderley) 8a
  • Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
Friday 10/2 Tasks (updated 0900 10/2)
  • Viewer disconnects (Norris) 6a
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • PSS Kicker Cables tie-up (SSG)
  • Survey and Alignment control measure around gun (S&A)
  • Load suitcase with "bad" pucks (CIS)
  • Pump-down vacuum in front of tee for next week (CIS)
Tunnel Work
Time Mon 9/28 Tue 9/29 Wed 9/30 Thu 10/1 F 10/2
4a - 8a I&C; 5a: Francis: BPMs, Cups, Apertures I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps I&C: Norris: Viewer disconnects
8a - 10a CIS + SSG RadCon: rad probes SSG: Kicker magnet removal; CIS: Tiny magnet removals CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru S&A: Gun
10a - 12p CIS + SSG DC Power DC Power: Wire wrap-ups, junction box investigation S&A: Gun; SSG: Kicker cable tie-up
12p - 2p CIS + SSG DC Power DC Power: Wire wrap-ups, junction box investigation DC Power S&A: Gun
2p - 4p CIS + SSG DC Power 3p: Moser: Safety Warden checks S&A: Gun
4p - ??
Other Work Occurring When Convenient
  • Remove suitcase, Tunnel (CIS)
  • Harp upgrade, InjSB (I&C)
  • ODH Head Replacement, InjSB and Tunnel (SSG)
  • PSS Chassis Removals, InjSB (SSG)

Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network

Monday Oct 5
  • vacuum tests, disconnects, and pre-removal blank offs (CIS)
  • QCM->downstream Survey and Alignment
  • S&H cable work for iocinse4, InjSB (Francis)
Tuesday Oct 6
  • Survey and Alignment finishing up around 0L04 (S&A)
  • U-tube operations at 0L03 (Cryo)
  • S&H cable work for iocinse4, InjSB (Francis)
  • Stage/prepare for craning our girders (Mech Install)
  • Chopper SSA upgrade -- LCW line install, InjSB (Mech Install / RF)
Wednesday Oct 7
  • S&H cable work for iocinse4, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Wein PS Work, InjSB (Windham)
  • VIP UHV PS Work, InjSB (Windham)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
Thursday Oct 8
  • BPM work, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
Wednesday Oct 7 and Thursday Oct 8 -- Mechanical Install
  • Remove to test lab --
    • Laser outrigger table
    • 1st Wein girder and pedestals
    • 2nd Wein girder, apertures, and pedestals
    • Photocathode puck suitcase on cart
  • Remove to Brett Lewis grey oil tank
  • Penetration stone drops

Current list of Injector penetrations to be dropped: 57, 86, 108, possibly this one

Penetration drop distance e3854100:

  • 34ft from floor of InjSB to floor of Inj tunnel
  • 25ft from floor of InjSB to elevated Inj tunnel cable tray
Friday Oct 9
  • BPM Work, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
  • Penetration stone drop -- 57, 86, 108, Tunnel (Mech Install)
    • Penetration above laser hut already opened

Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild

  • Laser/Y-Chamber viewer for Y-chamber girder (Marcy)
  • Fiducializing Y-chamber girder (S&A)
  • Laser window under vacuum evaluations (Phil/Shukui/Caryn)
  • Documenting early InjSB racks (Scott)
  • Cable pulls through penetrations (EES)
  • Fire pipe demolition? (Facilities Contractor)
  • Wein upgrade (Carlos) --
    • Finish new Wien electrodes drawing and sign-offs
    • Vacuum chambers to machine shop for mods
    • Begin creating new screens
  • Injector Tunnel Photos from W 10/14


Monday Oct 12

Tunnel --

  • Hooking up VIPs to new 18V PS for load testing (Marcy/Scott)
  • Cable pulls through penetrations (EES)

InjSB --

  • BPM Cable Pulls through Penetration 86 (Francis)
  • Chopper SSA upgrade (Farrish)
  • Harp to PC104 upgrade (Dela Cruz)
  • Early rack documentation and space optimization (Scott)
  • PSS Upgrade work (IN02BNI, B29, B30) (SSG)


Tuesday Oct 13

Tunnel --

  • Cable pulls through penetrations (EES)
  • Resistor box evaluation (Coleman)

InjSB --

  • BPM Work, IN02B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)


Wednesday Oct 14

Tunnel --

  • Cable pulls through penetrations (EES)
  • Safety warden walk-through (Moser)

InjSB --

  • BPM Work, IN02B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • Determining rack location for Wien magnet PSs, IN02-middle (Coleman, Grames, Moser)
  • Safety warden walk-through (Moser)
  • Conduit in penetration 135 (Electricians)


Thursday Oct 15

Tunnel --

  • S&A Level surveys

InjSB --

  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
Friday Oct 16

Tunnel --

  • Cable pulls through penetrations (EES)
  • Mott cable removals (Scott/Riad, EES)

InjSB --

  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
  • IN02B26 Power Lock-Out, ~915a (DC Power)

Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation

Non-Tunnel Work
  • Build new Y-chamber viewer => Y-built w/test screen, Laser being built.
  • Use test screen + laser + S&A to verify position of first viewer => This week
  • Install + align + vacuum seal (2) viewers => target this week
  • Caryn will confirm but identified best ‘mushroom’ window, attach => done
  • ME provide ALL points to S&A for installation (gun table, 2I stand, Y-chamber, 2 peds for Wien, 2 peds A1/A2) => ???
  • Carlos' Wien-mania!
Tunnel Work
  • Complete remove old keV Mott cables => done
  • Complete remove old gun HV cables => done
  • Jim pulls Wien PS cables? => done
  • Does Wien HV cable pull start? => starting this week
  • Scott will finish tie back of cables on tunnel floor to cable tray => done
  • Refill 86? => no, not yet
Standing Injector Service Building Work
  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
Monday Oct 19

Tunnel --

  • Cryo u-tube pulls for 0L0{2,3,4}
Tuesday Oct 20

Tunnel --

  • Cable pulls and removals

InjSB --

  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, IN02B22, 2p - 4p (DC Power)
Wednesday Oct 21

Tunnel --

  • S&A Verify line with new control

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • M56 Hardware Removal from IN02B22, (I&C)


Thursday Oct 22

InjSB --

  • Wien Magnet PS Install, IN02B22, afternoon (DC Power)
  • Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)


Friday Oct 23

Tunnel --

  • Vacuum work clean room craned in 6a - 8a (Mech Install)
  • Clean room setup and prepping (Marcy)
  • Gun interlock checks in preparation of removal of old HV Interlock Chassis in IN01B02 (Windham, Grames)
  • Laser room work (Shukui)

InjSB --

  • Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • 20A PS Install, IN02B22 (DC Power)


Inj Service Building Work

InjSB Racks.png

Time Wed 10/21 Thu 10/22 Fri 10/23
5a - 9a Dela Cruz, Norris, Francis Dela Cruz, Norris, Francis Dela Cruz, Norris, Francis
9a - 12p Francis, SSG, Windham Francis, SSG Francis, SSG, Windham
12p - 4p DC Power, SSG, Windham, Francis DC Power, SSG, Windham, Francis DC Power, SSG, Windham, Francis

Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location

Tunnel work
  • Remove NEG filter from HV chamber ✅
  • Setup mobile cleanroom over HV chamber ✅
  • Vent Gun3 chamber to test Gun3 valve ✅
  • Vent Gun2 chamber to test Gun2 valve ✅
  • Remove 2I NEG beam line, remove NEG pedestal (temporarily) ✅
  • Replace 10” flange + SHV connector + blank off + pump down ✅
  • Prep Gun3 & Y-chamber for Install to remove ✅
  • Wrap up UHV ion pump power supply power tests ✅
  • INSTALL lift and move gun table off feet, & move Gun3 & Y-chamber back to TL-1137 ✅
  • S&A may start setting/checking points (gun feet, 2I ped, Y ped, Wien ped, A1/A2 ped) ✅
Non-Tunnel Work
  • Finish Y-chamber : add viewers, add laser vacuum window, add NEG towers, add gun valve on-going
  • Wien-mania! (high level schedule)
-Wien magnetic field mapping next couple weeks
-Bubba assembles the fixtures ✅


Injector Tunnel and Service Building Work

Location
Time
Mon 10/26 Tue 10/27 Wed 10/28 Thu 10/29 Fri 10/30
InjSB
5a - 9a
Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis
Tunnel
5a - 9a
Gun Vacuum Work Gun Vacuum Work Gun2 Table Move
Y-Chamber+Gun3 Removal
InjSB
9a - 12p
Francis, SSG Francis, Windham, SSG Francis, Windham, SSG Dela Cruz, Norris, Francis, SSG Francis, SSG
Tunnel
9a - 12p
Gun Vacuum Work Gun Vacuum Work 9a CIS+MechInstall Walk-Thru Wien Cable Pulls Cryo 0L02 L-tube pull
Fire pipe walk thru
S&A Point Layouts
InjSB
12p - 4p
SSG Windham, SSG Windham, SSG
Trim Rack Checks
SSG SSG
Tunnel
12p - 4p
Gun Vacuum Work Gun Vacuum Work
3p:Videographer Tour
S&A Point Layouts

InjSB Week6.png


Mon Oct 26

Tunnel --

  • Gun vacuum work, 9a - 4p (CIS)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • LLRF air temperature control system removal from IN01B13? (Plawski?)
Tues Oct 27

Tunnel --

  • Gun vacuum work, 9a - 3p (CIS)
  • Videographer Tour, 3p+ (K. Carter + two videographers)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • LLRF air temperature control system removal from IN01B13? (Plawski?)
Wed Oct 28

Tunnel --

  • CIS + MechInstall Walk-Through of Gun Table Move, Removal of Gun3 stub and Y-chamber, 9a

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
  • Trim Card Checks, IN02B{10+11+26} + IN04B10, 12p-1p (Richardson)

Other Possible Work....

  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)


Thur Oct 29

Tunnel --

  • Gun2 move, 5a - 8a (Mech Install)
  • Removal of Gun3 and Y-chamber to Test Lab, 5a - 8a (Mech Install)
  • Wien HV and control cable pulls, 9a - 1p (Dela Cruz)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
  • Viewer work, IN03B07, 6a - 1p (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)

Other possible work....

  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
All Hallows' Eve Eve 👻 (Fri 10/30)

Tunnel --

  • Cryo L-tube Removal from 0L02, 8a - 12p (Cryo)
  • Fire pipe demo job walk-through, 12p (Grames, Suhring, Renzo)
  • Point Layouts, after cryo (S&A)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
  • Viewer work, IN03B07, 6a - 1p (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)

Other possible work....

  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)

Week 7 (Nov 2 - Nov 6)

Fire pipe removal, viewer design, modify existing pedestals, Wien filter mapping

Tunnel work
Mon/Tue
  1. INSTALL crane support (move Y-girder, Gun3 chamber, anything else back to TL1137)
  2. CIS take opportunity to a) cover your stuff before fire pipe demo, b) clean up cabinets, toolbox
  3. EES-IC Cable Pulls, Termination, and Routing
Wed/Thu and maybe Fri
  1. Fire pipe demolition
Non-Tunnel Work
  • Complete Y-chamber: add viewers, add laser vacuum window, add NEG towers, add gun valve
  • Wien-mania! (high level schedule) => H/V-wien magnetic field mapping
InjSB Work
  • Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
    • Comm chassis to digiport server
  • PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
  • Viewer work, IN03B0{6+7} (Norris)
  • BPM Work, IN03B{05-08, 23} (Francis)
  • CIS Rack Work, IN01B{00-05} (Windham)

Other possible work...

  • 20A Wien Magnet PS Install (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)

Injector Tunnel and Service Building

Location
Time
Mon 11/2 Tue 11/3
Election Day 🇺🇸
Wed 11/4 Thu 11/5 Fri 11/6
InjSB
5a - 9a
BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work
Tunnel
5a - 9a
Wien + viewer cable pulls
INSTALL Crane Outs
Wien + viewer cable pulls Fire pipe demo Fire pipe demo F(riday)
InjSB
9a - 12p
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
Wien + viewer cable pulls Wien + viewer cable pulls Fire pipe demo Fire pipe demo F(loat)
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M T Fire pipe demo Fire pipe demo F

InjSB Week7.png

Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher

Tunnel work
  1. Tue - S&A is queued up to set new(er) gun foot pad points
  2. Tue/Wed - Shaun predicts 4 pedestals arrive, Jenord inspects them; other peds exist in tunnel - thank you Phil/Shaun!
  3. Wed/Thu/Fri - Install drills and drops anchors, prepare grout form?, maybe we return gun table (Tom, best guess for the fire pipe install?)
ME work
  • S&A drop revised points for table base pads. ECD 11/10. done
  • 2I solenoid – done
SG print full size drill template for Neil.
Check fit of template.
  • Neil – Drill holes into top of solenoid stand (existing item and is currently in place) using drill template provided by Shaun. done
  • Neil drill anchor holes in floor done
HVC table base pads. done
Wien Girder Pedestals. done
Aperture Girder Pedestals. done
Details have been provided to Neil. done
  • Y chamber girder
Design new v-block mounting for Y & ion pump due to angle change of Y.
Fabricate or modifications.
Non-Tunnel Work
  1. Wien-mania! (high level schedule) - Wien magnet mapping, HVPS system controls (ADC/DAC), Switchbox build
  2. Complete Y-chamber build : laser window + (2) viewers + NEG Tower + Valve (gun3!?)
  3. A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
  4. Prebuncher vacuum repair, leak check
  • Did the leak check braze joint happen?
  • Did a final probe port length get decided?
  • Can we resolve these question, repair the probe port, clean, ready for testing by Friday?
  1. Submit PR for PSS kicker
ISB Work
  1. Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
    • Wire HV PS
    • Install Comm chassis
  2. PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
  3. Viewer upgrades, IN03B07 (Norris)
  4. Harp upgrades, IN03B07 (Dela Cruz)
  5. BPM Work, IN03B{05-08, 23} (Francis) Phase I: ✅; jump-start on Phase II ✅
  6. CIS Rack Work, IN01B{00-05} (Windham)
  7. Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  8. First Aid Cabinet re-stocks, back wall behind IN02B22ish + bottom of access stairs, (Occ Med + vendor), date TBD

Injector Tunnel and Service Building

Location
Time
Mon 11/9 Tue 11/10 Wed 11/11 Thu 11/12 Fri 11/13
InjSB
5a - 9a
BPM, Viewer, Wien Work BPM, Viewer, Wien, Harp Work BPM, Viewer, Wien, Harp Work BPM, Viewer, Wien, Harp Work Viewer, Wien, Harp Work
Tunnel
5a - 9a
Viewer Cable Pulls T INSTALL Pedestals, base pads, solenoid stand drilling INSTALL work
Viewer Cable Pulls
S&A Survey Pedestals
InjSB
9a - 12p
PSS Upgrade
BPM, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Harp, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Harp, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
BPM, Harp, Viewer, Wien Work
CIS Rack Work
PSS Upgrade
Harp, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
Viewer cable pulls S&A Sets New(er) Points
DC Power Resistor Box Button-Up
INSTALL Pedestals, base pads, solenoid stand drilling Viewer Cable Pulls
11a: Laser Safety System Audit
S&A Survey Pedestals
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M S&A Sets New(er) Points Cable pulls? R S&A Survey Pedestals

InjSB Week8.png

Week 9 (Nov 16 - Nov 20)

Non-Tunnel Work
  1. Continue preparing new Y-chamber
  2. A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
  3. Prebuncher -- RF testing/tuning
  4. Wien-mania! (high level schedule) =>
    • Review V-wien magnetic field mapping results and determine any remaining desired measurements
    • Finish V-wien field mapping and move to horizontal
    • Wien quad hardware arrivals?
    • Install HV switcher chassis
  5. 200kV PSS kicker fabrication
Tunnel work
  1. INSTALL grouts in pedestals (Mon/Tue) done?
  2. Fire pipe demo (Wed/Thur/Fri)
ISB Work
  1. Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  2. PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer)
  3. Viewer upgrades, IN03B07 (Norris)
  4. Harp upgrades, IN03B07 (Dela Cruz)
  5. CIS Rack Work, IN01B{00-05} (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 11/16 Tue 11/17 Wed 11/18 Thu 11/19 Fri 11/20
InjSB
5a - 9a
Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work
Tunnel
5a - 9a
INSTALL Grout pedestals T Fire pipe demo Fire pipe demo Lifting Plate Load Test
InjSB
9a - 12p
Viewer, Harp, Wien Work
CIS Rack Work
Viewer, Harp, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
INSTALL Grout pedestals Laser room/table work
Ceiling Lifting Plate Install
Fire pipe demo Fire pipe demo F
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M Laser room/table work Fire pipe demo Fire pipe demo F

InjSB Week9.png


Week 10 (Nov 23 - Nov 25 🦃)

Non-Tunnel Work
  1. Complete assembly of new Y-chamber
  2. Magnetic mapping of spare aperture cube
  3. A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
  4. Prebuncher -- RF testing/tuning
  5. Wien-mania! (high level schedule) =>
    • Horizontal Wien magnetic assembly and field mapping
    • Bake V-wien electrode assembly with vacuum chamber
    • V-wien HV test at UITF
    • Resistor box testing at UITF?
Tunnel work
  1. Opportunistic cable pulls -- who wants to do some? Good week for it.
ISB Work
  1. Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  2. PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer)
  3. Viewer upgrades, IN03B07 (Norris)
  4. Harp upgrades, IN03B07 (Dela Cruz)
  5. CIS Rack Work, IN01B{00-05} (Windham)

Injector Tunnel and Service Building

Location
Time
Mon 11/23 Tue 11/24 Wed 11/25 Thu 🦃 11/26 Fri 11/27
InjSB
5a - 9a
Viewer, Harp, Wien Work Viewer, Harp, Wien Work Viewer, Harp, Wien Work
Tunnel
5a - 9a
M T W
InjSB
9a - 12p
Viewer, Harp, Wien Work
CIS Rack Work
Viewer, Harp, Wien Work
CIS Rack Work
Harp, Viewer, Wien Work
CIS Rack Work
Tunnel
9a - 12p
M T W
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M T W

InjSB Week9.png


Week 11 (Nov 30 - Dec 4)

Non-Tunnel Work
  • H-Wien
    • plate ready at shop, mic and test fit @ MMF
    • order (4) Ni plates
  • V-Wien
    • Start HV tests @ UITF
  • MHD
    • complete thermal test >2.5A
    • measure field profile and BL/I for CED
  • DR
    • measure DR per Jay's plan
  • A1/A2 cubes
    • complete assembly (coils + aperture), test motion and shorts
    • S&A fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes)
  • PSS kicker
    • vendor quotes?
    • place order
Tunnel work
  • Install
    • Y girder + 2I solenoid from 1137 to tunnel
    • Gun table to foot pads
  • S&A
    • Pre-align Y girder
    • Pre-align gun
  • PSS/CIS
    • Complete laser bypass
    • Align laser - test at window, viewer hole, cathode/flange
  • CIS/S&A
    • 2I solenoid on pedestal
    • 2I vacuum connection (valve to gun)
    • Final align
    • Final laser check
ISB Work
  • Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • Viewer upgrades, IN03B{06-07} (Norris)
  • Harp upgrades, IN03B07 (Dela Cruz)
  • CIS Rack Work, IN01B{00-05} (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 11/30 Tue 12/1 Wed 12/2 Thu 12/3 Fri 12/4
InjSB
5a - 9a
M T W R F
Tunnel
5a - 9a
M INSTALL: Y-chamber, solenoid PSS Laser Bypass Work S&A: Pre-align Gun-Y S&A: Pre-align Gun-Y
InjSB
9a - 12p
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
Tunnel
9a - 12p
M INSTALL: Y-chamber, solenoid CIS Laser Hut Work S&A: Pre-align Gun-Y S&A: Pre-align Gun-Y
CIS Laser Alignment Work
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
M T W S&A: Pre-align Gun-Y S&A: Pre-align Gun-Y
CIS Laser Alignment Work

InjSB Week11.png

Week 12 (Dec 7 - Dec 11)

Non-Tunnel Work
  • Wien (Test Lab)
    • Test voltage divider box, calibrating UITF Matsusada HV PSs done, opted to use FLUKE 1000:1 V-probe and RMS true-value multimeter
    • U-Wien electrode alignment -- install teflon spacer (CIS) first-pass done, after discussions, may refine
    • Improve V-wien electrode alignment? (S&A) deferred
    • Receive Nickel endplates received, returned after finish found scratched, received again?
  • A1/A2 cubes (Test Lab)
    • Assemble fixture mounting plates done
    • Test motion and shorts '
    • Fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) (S&A) awaiting cubes
  • Prebuncher - high power testing
  • PSS kicker
    • build bids received, choosing one done
    • 12/9: req submitted
  • MagTest
    • Wrapping up A2 measurements
    • Wrapping up A1 measurements


Tunnel work
  • Wien cable pulls (Dela Cruz)
  • Laser alignment work (CIS) complete for this week
  • Gun -> Y-chamber vacuum connections (CIS) Thursday/Friday
  • Viewer cable terminations (Norris)


ISB Work
  • Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • Viewer upgrades, IN03B{06-07} (Norris)
  • Harp upgrades, IN03B07 (Dela Cruz)
  • CIS Rack Work, IN01B{00-05} (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 12/7 Tue 12/8 Wed 12/9 Thu 12/10 Fri 12/11
InjSB
5a - 9a
M Viewer/Wien/Harp Work Viewer/Wien/Harp Work R Viewer Terminations
Tunnel
5a - 9a
CIS Laser Work CIS Laser Work CIS Laser Work S&A+CIS Drive Laser Alignment Locking in NEG-tube
BPM locations (CIS+S&A)
InjSB
9a - 12p
CIS Rack Work CIS Rack Work
Viewer/Wien/Harp Work
CIS Rack Work
Viewer/Wien/Harp Work
CIS Rack Work CIS Rack Work
Viewer Terminations
Wien Cabling Work
Tunnel
9a - 12p
CIS Laser Work CIS Laser Work-
temp Vacuum Window Install
Facilities HVAC Investigation
CIS Laser Work S&A+CIS Drive Laser Alignment CIS Pump Down Gun
S&A Gun/Y-Chamber
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
Viewer Terminations
Wien Cabling Work
Tunnel
12p - 4p
CIS Laser Work CIS Laser Work
Facilities HVAC Investigation
CIS Laser Work S&A+CIS Drive Laser Alignment CIS Pump Down Gun
S&A Gun/Y-Chamber


InjSB Week11.png


Week 13 (Dec 14 - Dec 18)

Non-Tunnel Work
  • Wien (Test Lab)
    • U-Wien electrode parallelism evaluation after assembly w/teflon spacer block, spacer for hangers added (S&A) done
    • Controls work continues yep
    • HV PS calibration measurements, second-pass Friday
    • Receive Nickel endplates? done
  • A1/A2 cubes (Test Lab)
    • Assembling A1/A2 cubes done
    • Test motion and shorts done
    • Fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) (S&A) A2 done, A1 completed today
  • MagTest
    • Measure DR per Jay's plan continues
    • QW (Wien quad) lead reinforcement and field mapping 4 done, 12 to go


Tunnel work
  • Wien cable pulls (Dela Cruz) (latter half of the week) done?
  • Viewer cable terminations? (Norris) near complete
  • Gun -> Y-chamber vacuum pumpdown and leak check (Stutzman, Adderley) done
  • CIS Check drive laser -> cathode -> retroreflection alignment w/assembly under vacuum done
  • SSG Backs out of Laser Bypass workaround in support of PSS upgrades Friday


ISB Work
  • Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • Viewer upgrades, IN03B{06-07} (Norris)
  • Harp upgrades, IN03B07 (Dela Cruz)
  • CIS Rack Work, IN01B{00-05} (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 12/14 Tue 12/15 Wed 12/16 Thu 12/17 Fri 12/18
InjSB
5a - 9a
Viewer Terminations Viewer Terminations W R F
Tunnel
5a - 9a
CIS Vacuum Work:
heating NEG chambers
CIS Vacuum Work:
Leak Checks
Wien HV Cable Pulls? Wien HV Cable Pulls? F
InjSB
9a - 12p
CIS Rack Work
Viewer Terminations
CIS Rack Work
Viewer Terminations
CIS Rack Work CIS Rack Work
PSS Upgrades:
Access Room and in Racks
CIS Rack Work
Tunnel
9a - 12p
CIS Vacuum Work:
heating NEG chambers
CIS Vacuum Work:
Leak Checks
CIS Laser/retroreflection checks
CIS Laser Hut Work
Viewer Terminations
Wien HV Cable Pulls?
CIS Laser Hut Work
Viewer Terminations
SSG Laser Bypass Backout
InjSB
12p - 4p
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrade
CIS Rack Work
PSS Upgrades:
Access Room and in Racks
CIS Rack Work
PSS Upgrade
CIS Rack Work
Tunnel
12p - 4p
CIS Vacuum Work CIS Vacuum Work
CIS Laser/retroreflection checks
CIS Laser Hut Work
Viewer Terminations
CIS Laser Hut Work
Viewer Terminations
F


InjSB Week11.png

Week 13.6 (Dec 21 - Dec 23)

830 toolbox meetings suspended.
Have a safe and restful winter break.

Non-Tunnel Work

MagTest --

  • DR field mapping continues


Tunnel work
  • Neutron detector field cable runs, above 0L03 (Gonzales)
  • PSS upgrades -- equipment near Inj-NL gate (SSG)


ISB Work
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer terminations, IN03B{06, 07} (Norris)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere (SSG)
  • Neutron detector system work, IN03+4 (Gonzales, Mock)


InjSB Week13.5.png


Week 14 (Jan 4 - Jan 8)

Happy New Year!!! 🎉🎉🎉

  • AIPINJ Phase I Jobs for 2021


Non-Tunnel Work
  • Wien
    • V-Wien (Hernandez-Garcia)
      • remove from UITF test stand
      • re-assemble in Vertical orientation w/new spacers, Ni endplates, and magnet
      • ~Wed deliver to S&A
      • Survey of V-wien, evaluation of electrode parallelism
    • Picking up new Ni endplates from machine shop, cleaning and annealing before delivery to MagTest to be used in assembly of H-wien and evaluation during field mapping (Grames)
    • Fabrication of HV switcher chassis continues (Dela Cruz)
    • Controls work continues (Croke)
  • A1/A2 Apertures
    • Motor controls work continues (Windham)
    • A1/A2 girder build in TL continues (Adderley)
  • MagTest
    • DR field mapping
    • Complete QW coils lead reinforcement and mapping
    • Begin H-wien field mapping?


Tunnel work
  • Prepping for Gun2 bake (Stutzman)
  • Wien HV cable pulls? (Dela Cruz, Norris)
  • Laser hut opto-mechanical work (Zhang)
  • LCW walkthrough (CIS+I&C+MechInstall)


ISB Work
  • Wien HV cable pulls?, IN01B{00+01} (Dela Cruz, Norris)
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel install, IN01B11 (Windham)
  • iocin3 crate upgrade to VME, IN01B{04+14} (Dela Cruz)


Injector Tunnel and Service Building

Location
Time
Mon 1/4 Tue 1/5 Wed 1/6 Thu 1/7 Fri 1/8
InjSB
5a - 9a
M T W R F
Tunnel
5a - 9a
M Wien HV cable pulls? MechInstall Crane Work
Wien HV cable pulls?
Viewer Terminations
Wien HV cable pulls?
Viewer Terminations
Wien HV cable pulls?
Viewer Terminations
InjSB
9a - 12p
CIS Rack Work CIS Rack Work --
15deg Interlocks Panel
CIS Rack Work
iocin3 crate upgrade prep
15deg Interlocks Panel CIS Rack Work
Tunnel
9a - 12p
Gun2 Bake Preps 9a LCW Manifold WalkThru
Gun2 Bake Preps
Viewer Terminations
Gun2 Bake Preps
Viewer Terminations
Gun2 Bake Preps
Viewer Terminations
Gun2 Bake Preps
Viewer Terminations
InjSB
12p - 4p
CIS Rack Work
PSS Upgrades
CIS Rack Work --
15deg Interlocks Panel
PSS Upgrades
CIS Rack Work
iocin3 crate upgrade prep
PSS Upgrades
15deg Interlocks Panel
PSS Upgrades
CIS Rack Work
PSS Upgrades
Tunnel
12p - 4p
Gun2 Bake Preps Gun2 Bake Preps Gun2 Bake Preps Gun2 Bake Preps Gun2 Bake Preps


InjSB Week14.png

Week 15 (Jan 11 - Jan 15)

Non-Tunnel Work
  • Wien (Hernandez-Garcia)
    • Bake V-wien
    • V-wien HV soak
    • Fabrication of HV switcher chassis (Dela Cruz)
  • A1/A2 girder build (Adderley)
  • Rectify viewer air cylinder lengths? (Stutzman)
  • MagTest
    • DR field mapping
    • Complete QW coils lead reinforcement and mapping
    • Begin H-wien field mapping?


Tunnel work
  • Photocathode suitcase bake (Stutzman, Adderley)
  • Wien HV cable pulls? (Dela Cruz, Norris)
  • Laser hut work (Zhang)
  • iocin3 job Tuesday
Gun HV control => no problem
Some vacuum => no problem
Some FSD => no problem
Insertables (viewers etc.) => no problem
Some Pockels cell & RTP cell controls => i turned off RTP HV PS already
Chopping aperture (not sure how current this is) => no problem
Scraper (think this is redundant?) => do we remove now???
Maybe some old laser controls (ocelot?) => is this really a running app???
An application called pol_source, which has controls for a number of boards - IP Digital 24, BASIC stepper motor, IpOpto. => => what is this connected to???
Are the remaining 4-laser apps on iocin3b? Will that mini-crate be replaced or merged? Any other apps on iocin3?


ISB Work
  • ⚡⚡⚡Power Outage⚡⚡⚡ I-BT Breaker Panel Work -- adding 50A circuit for new chopper SSA along with 225A main breaker
    Details of what will lose power in ATLis 21696, Tunnel and SB racks affected
  • PSS Upgrades -- energizing new equipment, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel install, IN01B11 (Windham)
  • iocin3 crate upgrade to VME, IN01B{04 + 14} (Dela Cruz)
    • iocin3 will be down Monday 1/11 morning


Injector Tunnel and Service Building

Location
Time
Mon 1/11 Tue 1/12 Wed 1/13 Thu 1/14 Fri 1/15
InjSB
All Day
Safing out equipment for iocin3 work T W Breaker Panel Work Float for breaker panel work
InjSB
Morning
M iocin3 VME upgrade
15deg interlock work
W Breaker Panel Work F
InjSB
Afternoon
PSS Upgrades 15deg interlock work
PSS Upgrades
PSS Upgrades Breaker Panel Work
PSS Upgrades
PSS Upgrades
Tunnel
All Day
Suitcase bake
Safing out equipment for iocin3 work
Suitcase bake W Breaker Panel Work Float for breaker panel work
Tunnel
Morning
M T W Breaker Panel Work F
Tunnel
Afternoon
M T W Breaker Panel Work F

InjSB Week14.png


Week 16 (Jan 18 - Jan 22 +weekend)

Non-Tunnel Work
  • Wien (Hernandez-Garcia)
    • Moving V-wien from UITF test stand to vacuum lab, w/local vac PS Leaving on test stand until need to move
    • H-Wien
      • Preparing to receive Wed 1/20 Fri 1/22
      • Assemble with Ni end plates
      • UHV cleaning
  • A1/A2 girder build (Adderley, Stutzman)
    • Rectifying viewer air cylinder dimensions
  • Prebuncher testing/tuning (Wissman)
  • MagTest
    • H-wien field mapping (ETA Fri 1/22)
    • DR#2 coil lead reinforcement
    • DR#1 upper coil inspection


Tunnel work
  • Fire pipe install, pipe delivery 1/22, install begins Saturday 1/23
  • Wien HV cable pulls? (Dela Cruz, Norris)
  • Laser hut work (Zhang)
  • Vacuum bakes (Stutzman, Adderley)
  • FC#1 bellows replacement (Adderley, Stutzman, Grames)


ISB Work
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel install, IN01B11 (Windham)
  • Chopper SSA upgrade, back of IN01B{10-15} (Farrish)


Injector Tunnel and Service Building

Location
Time
Mon 1/18
MLK Jr Day
Tue 1/19 Wed 1/20 Thu 1/21 Fri 1/22 Weekend
Sa 23rd + Su 24th
InjSB
All Day
holiday CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work weekend
InjSB
Morning
M Beam Sync Cabling
Check (~IN01B04) Francis
15deg Interlock
Chopper SSA Cabling
W CIS Rack Work CIS Rack Work weekend
InjSB
Afternoon
M 15deg Interlock
PSS Upgrades
Laser chiller checkout
PSS Upgrades
CIS Rack Work
PSS Upgrades
CIS Rack Work
PSS Upgrades
weekend
Tunnel
All Day
holiday Laser Hut Work
Vacuum Bakes
FC#1 Bellows Replacement R Fire pipe install Fire pipe install
Tunnel
Morning
M T W FC#1 Vacuum Button-Up
Viewer Terminations
Fire pipe install Fire pipe install
Tunnel
Afternoon
M T Laser Hut Work FC#1 Vacuum Button-Up
Laser Hut Work
Fire pipe install Fire pipe install


InjSB Week16.png

Week 17 (Jan 25 - Jan 29)

Non-Tunnel Work
  • Wien (Hernandez-Garcia)
    • H-Wien
      • Receive from MagTest after field mapping
      • Assemble with Ni end plates
      • UHV cleaning
    • U-Wien newly fabricated Ni endplates
      • Pick-up after ultrasonic isopropanol clean 1/25
      • Deliver for annealing
    • V-Wien
      • Remove from UITF cave and begin assembling on girder?
  • A1/A2 girder build (Adderley, Stutzman)
  • Rectifying viewer air cylinder dimensions (Adderley, Machie, Gregory)
  • Prebuncher testing/tuning (Wissman)
  • Survey and Alignment
    • PCup survey and fiducialization
    • FC#1 survey and fiducialization
    • H-wien after UHV cleaning and assembly using teflon spacer method
    • Individual H-wien electrodes, and U-wien ones for comparison
  • MagTest
    • QW coil thermal tests
    • QW coil quality control checks


Tunnel work
  • Fire pipe (FML subcontractor)
    • Install
    • Pressurized air test
    • Pressurized water test (hydrotest)
  • Laser hut work (Zhang)
  • Preps for prep-chamber and HV chamber bakes next week (Stutzman, Adderley)
  • 120V front-end outlets walkthru (Windham, Stutzman, Adderley, Grames)
  • Cryo relief valve PM, behind 0L02 (Cryo)
  • Stowing photocathodes in suitcase for bakes (Grames)
  • Gate valve controller checkout/documentation (Windham)


ISB Work
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel, IN01B11 (Windham)
  • Utility chassis swaps, IN02B{10,11,26} + IN04B10 (Diggs, Kissinger)


Injector Tunnel and Service Building

Location
Time
Mon 1/25 Tue 1/26 Wed 1/27 Thu 1/28 Fri 1/29
InjSB
All Day
M Fire pipe install W Utility chassis swaps F
InjSB
Morning
M Fire pipe install W Utility chassis swaps F
InjSB
Afternoon
PSS Upgrades Fire pipe install
PSS Upgrades
PSS Upgrades Utility chassis swaps
PSS Upgrades
PSS Upgrades
Tunnel
All Day
Fire pipe install Fire pipe install Fire pipe install Cryo relief valve PM Fire pipe hydrotest
Tunnel
Morning
Fire pipe install Fire pipe install Fire pipe install 120V outlets walkthru
Fire pipe air test
Fire pipe hydrotest
Valve controller
Tunnel
Afternoon
Fire pipe install Fire pipe install Fire pipe install
Laser Hut Work
Laser Hut Work Preps for bakes?
Photocathodes->Suitcase?
Laser Hut Work


InjSB Week17.png


Week 18 (Feb 1 - Feb 5)

Non-Tunnel Work
  • Wien (Hernandez-Garcia)
    • H-Wien
      • MS fabricating new frame x4 and
        new 14mm-spacing teflon spacers for electrode assembly
      • Once MS done, towards end of the week, assemble H-wien w/new frame
      • Assembled H-wien -> S&A
    • HV Switcher Chassis (Dela Cruz)
      • 1st chassis hi-potted good
      • 2nd chassis getting overload faults, investigating
  • Viewer assembly (Adderley, Stutzman)
  • Wien girder assembly (Adderley, Stutzman)
    • Wien quads on crosses -- ETA T/W for QW coils from MagTest
  • Add pumps, vacuum leak check A1/A2 girder after S&A (Stutzman, Adderley)
  • Laser box build (Zhang, Gregory)
  • Build spare valve override blackbox, fourth in total (Windham)
  • Survey and Alignment
    • A1/A2 girder 1A pre-alignment
    • H-wien assembled on new frame
  • MagTest
    • Finish QC of QW coils -- Tuesday/Wednesday ETA
    • Thermal and current-limit tests on assembled spare QW-quad
    • Field mapping assembled spare QW-quad


Tunnel work
  • Laser hut work (Zhang)
  • Viewer upgrades (Norris)
  • Prep chamber bake forgoing for now, vacuum sufficiently good
    • Setup (in no particular order)
      • photocathodes->suitcase;
      • breakdown unistrut,
      • stow protective plastic barrier;
      • Configure IPs and valves
    • Bake for ~3 days @ 🔥🔥🔥C
    • Breakdown ~Friday
  • Opportunistic preps for HV chamber bake
  • 120V front-end outlets walkthru (Windham, Stutzman, Adderley, Grames)
  • Laser box enclosure design walkthru (Zhang, Gregory)
  • N2 manifold temporary move (Bullard)


ISB Work
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel, IN01B11 (Windham)
  • Install Wien HV Polarity Switcher Chassis, IN01B0{0,1} (Dela Cruz)
Other Service Buildings
  • Prebuncher testing/tuning in BSY SB (Wissman)


Injector Tunnel and Service Building

Location
Time
Mon 2/1 Tue 2/2 Wed 2/3 Thu 2/4 Fri 2/5
InjSB
All Day
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work F(loat)
InjSB
Morning
M 15deg dipole intlk tests
Viewer upgrades
15deg dipole intlk tests
Viewer upgrades
R Viewer Upgrades
InjSB
Afternoon
PSS Upgrades 15deg dipole intlk tests
PSS Upgrades
PSS Upgrades 15deg dipole intlk tests
PSS Upgrades
PSS Upgrades
Tunnel
All Day
Prep for Prep Chamber Bake Prep chamber bake
Preps for HV Chamber Bake
Prep Chamber Bake
Preps for HV Chamber Bake
Prep Chamber Bake
Preps for HV Chamber Bake
F(loast)
Tunnel
Morning
Valve controller Prep chamber vacuum tests/eval Viewer Upgrades
Engaging Prep RGA
N2 manifold move?
N2 manifold move
Laser enclosure walkthru
Viewer Upgrades
N2 manifold work
Tunnel
Afternoon
Photocathodes->Suitcase
Valve controller
Laser hut work Laser enclosure walkthru
Laser hut work
Laser hut work Laser hut work


InjSB Week18.png


Week 19 (Feb 8 - Feb 12)

Non-Tunnel Work
  • Weld Jobs: QW quads on crosses, Wien cube
  • A1/A2 Girder (Adderley, Stutzman)
    • Final leak check, prep for install in tunnel
  • Wien (Hernandez-Garcia)
    • H-wien
      • S&A, Monday
      • Bake
      • Vacuum pumpdown
      • HV testing?
    • V-wien
      • Unmount from test fixture in UITF
      • Prepare for girder install


Tunnel work
  • Viewer upgrades
  • A1/A2 girder install
    • Vacuum prep work (Stutzman, Adderley), Monday
    • Install (Mech Install), Tuesday
    • S&A, Tue-Thu
    • Associated vacuum work, Tue-Thu
  • FC#1 Re-install
    • Vacuum prep work (Stutzman, Adderley), Monday
    • Re-install + S&A, Tuesday
    • Vacuum space pumpdown (Stutzman, Adderley), Tue-Thu
  • Laser hut work (Zhang)
  • Laser enclosure design/fab (Zhang, Gregory)


ISB Work
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • Viewer upgrades, IN03B{06+07} (Norris)
  • 15deg dipole interlock panel, IN01B11 (Windham)
  • Install HV Polarity Switcher Chassis, IN01B0{0,1} (Dela Cruz)


Injector Tunnel and Service Building

Location
Time
Mon 2/8 Tue 2/9 Wed 2/10
1p: AIPINJ team photo (zoom)
Thu 2/11 🌨️ Fri 2/12
InjSB
All Day
15deg interlock CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
InjSB
Morning
M T Viewer Upgrades R F
InjSB
Afternoon
PSS Upgrades PSS Upgrades PSS Upgrades PSS Upgrades PSS Upgrades
Tunnel
All Day
Preps for FC1+A1/A2 Install Vent Gun->0I;
FC#1 + A1/A2 Girder
Install, Associated Vac Work, S&A
S&A of A1/A2 Girder,
after cartridge swap
Preps for
HV Chamber Bake
Prep NEG Activation
Preps for
HV Chamber Bake
Prep NEG Activation
Tunnel
Morning
Pump Cart Staging 7a: Vent Gun2->0I (CIS)
7a: FC#1 Re-Install (CIS)
~8a: FC#1 S&A, set yaw
A1/A2 Girder Install (Mech)
Cartridge Swap (MechInstall)
S&A of A1/A2 Girder
0L Viewer upgrades
S&A of A1/A2 Girder
A1/A2 Cartridge Layout
9a-11a: "Tour" (4people)
S&A of A1/A2?
Tunnel
Afternoon
Laser Hut Work A1/A2 Girder S&A
Laser hut work?
S&A of A1/A2 Girder
A1/A2 vac connections
Prep Chamber RGA v Heat
Cartridge Layout S&A of A1/A2?


InjSB Week18.png

Week 20 (Feb 15 - Feb 19)

Non-Tunnel Work
  • Wien girder assembly (Adderley, Stutzman)
  • H-wien HV testing at UITF (once bake complete) (Hernandez-Garcia, Bullard)
  • QW field mapping (MagTest)
  • PSS Kicker assembly once parts arrive


Tunnel work
  • HV Chamber and NEG tube bake (Adderley, Stutzman)
  • Prep chamber NEG activation (Adderley, Stutzman)
  • A1/A2 girder cartridge resolution?
  • Wien HV cable pulls? (Dela Cruz)
  • Viewer upgrades? (Norris)
  • UHV patch panel installation (Windham)
  • Valve black override box installation (Windham)


ISB Work
  • PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
  • CIS Rack Work, IN01B{00-12} (Windham)
  • Viewer upgrades, IN03B0{6,7} (Norris)
  • Install Wien HV Polarity Switcher Chassis, IN01B0{0,1} (Dela Cruz)
    • HV cable pulls?


Injector Tunnel and Service Building

Location
Time
🇺🇸 Monday 2/15 Tue 2/16 Wed 2/17 Thu 2/18 Fri 2/19
InjSB
All Day
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
InjSB
Morning
Switcher chassis install Switcher chassis install
Wien controls test
Switcher chassis install
Wien controls tests
R F
InjSB
Afternoon
PSS Upgrades PSS Upgrades PSS Upgrades PSS Upgrades
Lock-Up @ 1600
PSS Upgrades
Tunnel
All Day
HV Chamber +
NEG Tube Bake
HV Chamber +
NEG Tube Bake
HV Chamber +
NEG Tube Bake
HV Chamber +
NEG Tube Bake
HV Chamber Bake
NEG Tube Activation
Prep Chamber NEG Activation
Tunnel
Morning
M T W R 10a: Outlet relocation walkthru
Tunnel
Afternoon
M T W R F


InjSB Week20.png


Week 21 (Feb 22 - Feb 26)

Non-Tunnel Work
  • H-wien HV evaluation (Hernandez-Garcia, Bullard)
  • Wien girder modifications (Machine Shop)
  • QW field mapping (MagTest)
  • PSS Kicker assembly


Tunnel work
  • Breaking down activation and bake equipment (Stutzman, Adderley)
  • PSS Injector Segment Certification (SSG) Th+F Swing
  • A1/A2 Girder
    • Add SS adapter plates (CIS)
    • Re-fiducialize girder, MechInstall staging as needed (S&A)
    • Install on pedestals (MechInstall) Thursday
    • S&A of installed girder on pedestals Thursday
    • Vacuum hook-ups (CIS) Thursday
  • Laser hut work (Zhang)
  • Outlet Moves / Additions (FML) Friday
    • Move from floor to laser hut wall 120V outlets
    • ATLis 21922
  • Support Electrical Panel PM
    • Vacuum pump reconfigs from EM -> House power and back (CIS)
    • ATlis 21882


ISB Work
  • PSS Commissioning, IN02B{NI,29,30} +briefly elsewhere, swings (SSG)
  • PSS Injector Segment Certification (SSG) Th+F swing
  • CIS Rack Work, IN01* (Windham)
  • Viewer upgrades, IN03B0{6,7} (Norris)
  • Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)
  • Electrical panel PM, ATLis 21882 (FML) Friday
    • Work entails power outages in tunnel and SB
    • EM loop and normal power will not be off simultaneously
    • Facilities/Operability will coordinate -- see rough sched in table
  • Fan tray swap, ATLis 20311, IN02B23 (Greenfield) Friday 8a


Injector Tunnel and Service Building

Location
Time
Mon 2/22 Tue 2/23 Wed 2/24 Thu 2/25 Fri 2/26
InjSB
All Day
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work Electrical Work
some power outages
InjSB
Morning
M T W R 8a Fan Tray Swap
InjSB
Afternoon
M PSS Tests, Lock-Up W PSS Certification PSS Certification
Tunnel
All Day
Bake and Activation
Equipment Breakdown
A1/A2 re-fiducialization W A1/A2 Install Day Electrical Work
some power outages
Tunnel
Morning
Leak checks of
*HV Chamber
*Prep Chamber
*2I beamline
Re-fiducialization of A1/A2
Valve override box work
W MechInstall adds adapter plates
Mounts on pedestals
S&A & Vac Hook-Ups
Floor Outlet Relocation
Tunnel
Afternoon
M PSS Lock-Up W A1/A2 S&A
3p PSS Certs Lock-Up
Some Preps Beginning ~2p
~1p: House Circuits PM
~2p: Pump reconfig EM=>HOUSE
~230p: EM Circuits PM
~3p: PM done, Return pump config
~after: PSS Certs Lock-Up
(if needed)

InjSB Week21.png


Week 22 (Mar 1- Mar 5)

Non-Tunnel Work
  • Wien girder assembly (CIS)
    • Mounting modifications complete, returned from Hampton MS
    • Additional holes for mounting/anchoring needed? Template from Engineering. (Gregory)
    • CIS+S&A Walk-thru identifying which components need alignment during assembly stage
    • Add component, survey, align *repeat*
  • PSS Kicker (SSG)
    • Coil QA (MagTest)
    • Assembly (CIS)
    • Coils and fixture in. What other parts needed?
  • QW quad field mapping (MagTest)
  • Move PIG to InjSB


Tunnel work
  • A1/A2 girder anchoring (Adderley, Gregory)
    • S&A Alignment check before vacuum hook-ups
  • A1/A2 / Region 3 Vacuum Connections, Pumpdown, Leak check (CIS)
  • Wien girder pedestal re-positioning (MechInstall)
    • Remove pedestals, knock out existing grout
    • Pedestals to new positions, templates provided by Engineering
    • Grout in
  • Crane in PIG HV resistor tank (MechInstall)
  • Macropulse chassis checkout (Zhang, Windham)
  • Laser hut alignment / opto-mechanical work (Zhang)
  • Pockels cell alignment (Zhang, Amali)
  • Gun HV Conditioning preparations (Hernandez-Garcia)
  • Beam-left S&A monument install (x4), adding to control, ATLis 21991 (S&A) Thursday
  • Lead brick clean-up (Grames)


ISB Work
  • Wien HV Polarity Switcher Tests, Control Screens Checkouts, IN01B0{0-6} (Hernandez-Garcia, Windham, Dela Cruz, Croke)
  • CIS Rack Work, IN01* (Windham)
  • Viewer upgrades, IN03B0{6,7} (Norris)
  • Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)
  • SCAM Board Investigation, IN03B04 (Windham)


Injector Tunnel and Service Building

Location
Time
Mon 3/1 Tue 3/2 Wed 3/3 Thu 3/4 Fri 3/5
InjSB
All Day
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
InjSB
Morning
M T 930 Wien Switcher Tests SCAM Board T/S
Prebuncher Cable Pulls
F
InjSB
Afternoon
M T Macropulse Chassis Checkout R F
Tunnel
All Day
A1/A2 anchoring A1/A2 Vacuum hook-ups
pumpdown
Relocating Wien Pedestals A1/A2 Girder Bake Oven Setup A1/A2 Girder Bake Oven Setup
Tunnel
Morning
Wien stand demo
A1/A2 Anchoring
A1/A2 Vacuum Hook-Ups
0I02 Harp Re-Install
MechInstall: * Crane in PIG
* Set Wien Pedestals
S&A: Align
Prebuncher cable pulls
S&A Monuments
F
Tunnel
Afternoon
A1/A2 Anchoring
Alignment Check
Pockels Cell Alignment
A1/A2 Pumpdown
Pockels Cell Alignment
A1/A2 girder leak check Region 3 leak checks
Macropulse chassis checkout
Pockels cell alignment
Lead brick clean-up


InjSB Week22.png


Week 23 (Mar 8 - Mar 12)

Non-Tunnel Work
  • Wien girder assembly, interleaved with component S&A (Stutzman, Adderley)
  • PSS Kicker (SSG)
    • Coil QA (MagTest)
    • Assembly (CIS)


Tunnel work
  • A1/A2 Girder bake (Adderley, Bullard, Stutzman)
  • Gun HV Processing Setup (Hernandez-Garcia)
    • PIG connections
    • SF6 tests
    • Interlock jumpering/configuration (Grames, Windham)
    • PSS Certification of Gun HV (SSG, Forman) Wed 9a, lock-up
  • Wien pedestal grouting opportunistic
  • Pockels cell alignment (Zhang, Amali)
  • Macropulse chassis modification and checkout (Windham, Zhang)
  • Lead brick clean-up (Grames)


ISB Work
  • CIS Rack Work, IN01*
  • Viewer upgrades, IN03B0{6,7} (Norris)
  • Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)


Injector Tunnel and Service Building

Location
Time
Mon 3/8 Tue 3/9 Wed 3/10 Thu 3/11 Fri 3/12
InjSB
All Day
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
InjSB
Morning
M T W R F
InjSB
Afternoon
M T W R F
Tunnel
All Day
A1/A2 Girder Bake A1/A2 Girder Bake A1/A2 Girder Bake A1/A2 Girder Bake A1/A2 Girder Bake
Tunnel
Morning
Gun HV Processing Setup:
*Connect PIG
*SF6 Tests
Gun Interlocks Config
Jumpering
9a: Lock-Up for
Gun PSS Certs
R F
Tunnel
Afternoon
Pockels cell alignment Pockels cell alignment Macropulse chassis mods R F


InjSB Week22.png


Week 24 (Mar 15 - Mar 19)

Phase 1 - HCO & Commissioning


Non-Tunnel Work
  • Complete assembly of Wien girder (CIS)
    • Pumpdown and leak check
    • Add viewers with modified shafts
    • Component 1B alignment (S&A)
  • PSS Kicker Assembly (CIS)


Tunnel work
  • A1/A2 girder bake disassembly, leak checks (Adderley, Bullard, Stutzman)
  • PSS Kicker conduit, kapton insulation, install (SSG)
  • UHV system labelling, documentation (Windham)
  • Cable tray spec'ing, install, under A1/A2 girder (Windham)
  • Wien girder install (in approximate order) --
    • Install girder (MechInstall)
    • 2A alignment (S&A)
    • Vacuum connections, rough pumpdown, leak check (CIS)
    • Grout pedestals (MechInstall, S&A)
    • 2B alignment (S&A)
  • DC Power magnet hook-ups, as possible (Coleman, +1)
  • DC Power resistor box work (Coleman, +1)
  • Prep chamber activation check (Grames)
  • Laser hut work (Zhang)
  • Gun HV checkout (Hernandez-Garcia)
    • Lock-up on swings ??
    • DecaRad placement (Windham)
    • Anode picoammeter connection (Grames, Stutzman)
    • Backfill SF6 into gun, PIG (Bullard)
  • Pockels cell alignment (Amali, Zhang)


ISB Work
  • CIS Rack Work, IN01* (Windham)
  • Viewer upgrades, IN03B0{6,7} (Norris)
  • Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)


Injector Tunnel and Service Building

Location
Time
Mon 3/15 Tue 3/16 Wed 3/17 Thu 3/18 Fri 3/19
InjSB
All Day
CIS Rack Work
UHV Sys Doc
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
InjSB
Morning
M T W R F
InjSB
Afternoon
M T W R F
Tunnel
All Day
A1/A2 Bake Takedown
Leak Check
A1/A2 Bake Takedown
Leak Check
A1/A2 Bake Takedown
Cable Tray Work
R DC Power Inline Resistor Measurements
SRF CM Checkout
Tunnel
Morning
UHV Sys Doc Backfill SF6
DecaRad placement
Pockels cell alignment Wien Pedestal Anchor Hole Drilling
A1 controls/spacing work
~10a: Pockels cell alignment
until 10a: A1 aperture work
~9a: Pockels cell alignment
930-11a: Lead brick clean-up
10a DCP Inline Res
Tunnel
Afternoon
Pockels cell alignment
UHV Sys Doc
Pockels cell alignment
DecaRad Placement
Gun anode hook-up
Pockels cell alignment
130p: Resistor box work
A1 controls/spacing work
Pockels cell alignment
Pockels cell alignment
DCP Inline Res

InjSB Week24.png


Week 25 (Mar 22 - Mar 26)

Phase 1 - HCO & Commissioning


Non-Tunnel Work
  • PSS Kicker Assembly (CIS)


Tunnel work
  • PSS Kicker conduit, kapton insulation, install (SSG)
  • Cable tray install, under A1/A2 girder (Windham)
  • Wien girder install (in approximate order) --
    • Install girder (MechInstall)
    • 2A alignment (S&A)
    • Vacuum connections, rough pumpdown, leak check (CIS)
    • Grout pedestals (MechInstall, S&A)
    • 2B alignment (S&A)
  • Setting up for Wien girder bake (CIS)
  • DC Power magnet hook-ups, as possible (Coleman, +1)
  • Survey checks of Wien <=> A1/A2 girder (S&A)
  • Laser hut work, pockels/RTP cell alignment (Zhang)
  • Helicity board beam sync fiber T/S (Suleiman, Windham, Francis)
  • Gun HV Assessment, Injector->Power Permit (Hernandez-Garcia)
  • PSS Kicker mounting spool swap (Adderley, Stutzman)


ISB Work
  • CIS Rack Work, IN01* (Windham)
  • Viewer/Harp upgrades, IN03B0{6,7} (Norris/Dela Cruz)
  • Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)


Injector Tunnel and Service Building

Location
Time
Mon 3/22 Tue 3/23 Wed 3/24 Thu 3/25 Fri 3/26
InjSB
All Day
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
InjSB
Morning
Craning Wien Girder T W R F
InjSB
Afternoon
M T W R F
Tunnel
All Day
Wien girder install, S&A, vac hook-up Wien girder leak checks
Gun HV Assessment Preps
Kicker spool swap A1 Bake Setup A1 Bake
Tunnel
Morning
MechInstall Wien girder
and S&A
* Wien girder <=> A1/A2 Girder
Flange alignment assessment
* Wien girder leak checks
* Gun HVPS Lock -> FC#1 Air line
930a Swapping Kicker Spool
A1 Pumpdown
* PSS Kicker Fit Test
* A1 Bake Setup
* Yellow laser box removal
*
Helicity Board T/S
Tunnel
Afternoon
Wien girder S&A
and vacuum hook-ups, pumpdown
Pockels cell alignment
Wien girder leak checks
Laser hut work
5p: Lock-Up -> PP
A1 Pumpdown, Leak check
Laser hut work
4p: Lock-Up Gun HV assessment
A1 Bake Setup
Laser hut work
4p: Lock-Up Gun HV assessment
Laser hut work


InjSB Week25.png


Week 26 (Mar 29 - Apr 2)

Phase 1 - HCO & Commissioning


Non-Tunnel Work
  • Evaluation of prebuncher options for CEBAF (CIS, RF, Eng)
  • Laser enclosure build (Bullard, Machie)


Tunnel work
  • 0L02 U-tube installs (Cryo)
  • AIPINJ Phase-II As-Found survey (S&A)
  • Laser hut work (Zhang)
  • Pb brick clean-up (MechInstall, Grames)
  • Penetration re-fills (MechInstall)
    • Holding off on laser hut penetration until after Wien bake
  • Gun HV Assessment, Injector Lock-up (Hernandez-Garcia)
  • Prebuncher install, S&A, vacuum rough down (Stutzman, Adderley)
  • Craning out heavy equipment in tunnel (MechInstall)
  • Grout Wien pedestals (MechInstall)
  • Vacuum Bakes (Adderley, Stutzman)
    • Wrap up A1 bake
    • Disassemble A1 bake setup
    • Setup for Wien girder bake, after prebuncher install
    • Wien girder bake


ISB Work
  • CIS Rack Work, IN01* (Windham)
    • Laser seed lockout walkthru with ES&H (Windham)
  • Viewer CAMAC->VME upgrades, IN03B0{6,7} (Norris)
  • Harp -> PC104 upgrades, IN03B0{6,7} (Dela Cruz)
  • Penetration re-fills (MechInstall)
  • Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)
  • Helicity board beam sync troubleshooting (Suleiman)


Injector Tunnel and Service Building

Location
Time
Mon 3/29 Tue 3/30 Wed 3/31 Thu 4/1 Fri 4/2
InjSB
All Day
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
InjSB
Morning
M T Craning Out Heavy Equipment R Penetration Fills:
58, 86, 108
InjSB
Afternoon
M T W Laser seed lock-out walkthru 2p: Helicity Board Beam Sync T/S
Mott System Turn On
Tunnel
All Day
A1 Bake Takedown
5D Line removal
SS Prebuncher Install
Prebuncher S&A, Vacuum Work Wien girder bake setup
S&A Phase II As-Founds
Wien girder bake setup/begin Wien girder bake
Tunnel
Morning
0700: 5D line removal
Pb brick org walk-thru
9a: S&A of prebuncher
0L02 U-Tube Install
Penetration Closures
Craning Out Heavy Equipment
0L04 U-tube installs
Wien bake controls check
Wien bake insulation
Penetration Closures
Penetration Closures
Tunnel
Afternoon
A1-region leak check
Laser hut work
RTP Cell Documentation
Prebuncher leak checks
Wien girder bake setup
Laser hut work
1p: PSS Conduit WalkThru
Laser hut work
Begin Wien girder bake
Laser hut work
Laser hut work


InjSB Week24.png


Week 27 (Apr 5 - Apr 9)

Phase 1 - HCO & Commissioning


Non-Tunnel Work
  • Laser box build (Bullard) ✅


Tunnel work
  • Wien girder bake, bake takedown, leak check (Stutzman, Adderley) : Tuesday
  • A1 cable terminations (Windham) Tuesday
  • NEG activations (nine in total) (Stutzman, Adderley) : Monday
  • Install under-girder cable trays (Electricians, Windham) : Thur
    • Job WalkThru Tuesday
  • Bond girders (Electricians, Windham) : Thur
  • Move/attach HV patch box for UHV pumps (Adderley) : Fri
  • Install PSS Kicker conduit (Bruhwel) : Fri
  • Grout Wien pedestals (MechInstall) : Fri
  • Laser box install (Bullard, Zhang) : next Monday
  • Attach 15deg (DR) Dipole (CIS) : next Monday
  • Re-attach Haimson (BH) corrector pairs (Adderley, Grames) : next Monday
  • Re-attach Wien-quad (QW) fixtures (Adderley, Grames) : next Monday
  • Install second air manifold (Bullard, Adderley) : Wed
  • Complete LCW manifold install work (MechInstall) : Tues
  • Laser hut penetration closure, sealing (no stone), Pb brick shielding (MechInstall) Fri
  • Install Wien filter magnets Fri


ISB Work
  • CIS Rack Work, IN01* (Windham)
  • Penetration re-fills, see Penetration Work below (MechInstall) ✅
  • Preps for penetration fills -- as needed, making space for chute to drop stones, IN02B10, IN02B23, IN03B04 (Moser) ✅
  • Wien HV cables pulls, IN01B0{0-8} (Dela Cruz)
  • Mott DAQ VME crate power T/S, IN02B21 (Suleiman) ✅
  • Laser seed chassis safe-operation-lock-up work, IN01B05 (Zhang, Windham) ✅


Injector Tunnel and Service Building

Location
Time
Mon 4/5 Tue 4/6 Wed 4/7 Thu 4/8 Fri 4/9
InjSB
All Day
CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work CIS Rack Work
InjSB
Morning
Moving heavy items near crane -> TL T Preps for Penetration fills Preps for Penetration fills Penetration stone fills
(58, 86, 108)
InjSB
Afternoon
M T W R Penetration stone fills
(58, 86, 108)
Tunnel
All Day
Wien girder bake Wien bake takedown CIS Mech Jobs CIS Mech Jobs
Electrician Jobs
MechInstall Jobs
SSG Jobs
CIS Mech Jobs
Tunnel
Morning
NEG Activations Wien/Y Leak Checks
A1 Cable Terminations
Cable Tray Job WalkThru
HV Patch Box Move
Install 2nd air manifold
BH, QW re-attachments
Cable tray install
Bond girders
BH, QW re-attachments
Laser box install
Laser hut pene
Grout Wien Pedestals
9a: Kicker Conduit Install
Install Wien Magnets
Mount HV Patch Box
Tunnel
Afternoon
Laser hut work Laser hut work Laser hut work Laser hut work Laser hut work


InjSB Week24.png


Week 28 (Apr 12 - Apr 16)

Phase 1 - HCO & Commissioning


Tunnel work
  • System Reconnects and HCO
  • Attach 15deg (DR) Dipole (Grames) Mon
  • Re-attach Haimson (BH) corrector pairs (Grames) Mon
  • Re-attach Wien-quad (QW) fixtures (CIS) Mon
  • UHV HV patch box relocation (Adderley) Tues
  • Wien pedestals wrap-up -- remove grout forms, cut all threads (MechInstall) Tues
  • Under-girder cable tray lowering (Adderley) Tues
  • Install laser box (Bullard) T+W
  • Remove SS prebuncher bracket interfering with BH corrector placement (CIS?) Tues
  • Valve controls work (Ketchum, Windham)
  • Vacuum work (Stutzman)
    • Ion pump cabling / controls checks Mon
    • Activating NEGs Mon
    • Hi-potting VIP1I07 Mon
    • Hi-potting VIP1I02 Wed
    • T/S VIP2I00 noise
    • De-gas stalk heater (Grames) Thur
  • Magnet hook-ups (DC Power -- Coleman, Delk, Kumar)
  • LCW hook-ups (Adderley, Francis)
  • 5D Line vacuum disconnects (CIS)
  • A1 EPICS controls (Windham, Higgins)
  • Gun HV evaluation (Hernandez-Garcia) Swings: W+Th
    • Rapid Access probe placement (Washington) Wed
    • Clean off gun table (CIS) Wed
    • DecaRad placement verification (Hernandez-Garcia) Wed
    • Disconnect and remove PIG (SF6 resistor tank) Thur
    • Install ceiling plate for HV cable strain relief Thur
    • Connect Gun directly to HVPS Thur
  • Prebuncher and chopper LCW connections (Wissman) Thur
  • Prebuncher cabling (Wissman) Thur
  • 60Hz electrical noise snooping (Suleiman)


ISB Work
  • System re-connects / associated rack work
  • Wien HV cables pulls, IN01B0{0-8} (Dela Cruz) Wed
  • A1 EPICS controls work (Windham, Higgins)


Injector Tunnel and Service Building

Location
Time
Mon 4/12 Tue 4/13 Wed 4/14 Thu 4/15 Fri 4/16 Sa 4/17 Su 4/18
InjSB
All Day
System Reconnects
CIS Rack Work
System Reconnects
CIS Rack Work
System Reconnects
CIS Rack Work
System Reconnects
CIS Rack Work
System Reconnects
CIS Rack Work
Drone Elevation Survey Su
InjSB
Early Morning (<9a)
Associated Rack Work Associated Rack Work 6a: Wien HV Cable Pulls
Associated Rack Work
Associated Rack Work
Terminating Wien HV Cables
Associated Rack Work Sa Su
InjSB
Morning
A1 EPICS controls
Associated Rack Work
Associated Rack Work Associated Rack Work Associated Rack Work
Terminating Wien HV Cables
Associated Rack Work Sa Su
InjSB
Afternoon
Associated Rack Work Associated Rack Work Associated Rack Work
A1 EPICS controls
Associated Rack Work Associated Rack Work Sa Su
Tunnel
All Day
CIS Vacuum Checkout CIS Vacuum Checkout CIS Vacuum Checkout Air Manifold Plumbing/Install
CIS Vacuum Checkout
CIS Vacuum Checkout Sa Su
Tunnel
Early Morning (<9a)
Wien pedestal wrap-up Wien pedestal wrap-up Wien HV Cable Pulls
Air Manifold Install
Viewer/Valve Solenoid Layout
LCW Hook-ups
Viewer/Valve Connections Viewer/Valve Connections
Terminating Wien HV Cables?
LCW Hook-ups
Sa Su
Tunnel
Morning
Laser box fit-test
11a: Re-attach DR, BH magnets
Re-attach QW fixtures
Vacuum work
LCW Hook-ups
A1 EPICS controls
Cable Tray Lowering
Vacuum+Valve work
LCW Hook-ups
HV patch box remount
Laser box install
Prebuncher bracket removal
Rapid Access probe
Air Manifold Install
VIP2I00 T/S
Valve controls
Finishing laser box install
Laser hut work
9a: Viewer/valve Solenoid Layout
Remove PIG
De-gas stalk heater
Prebuncher LCW and Cabling
Valve controls
LCW Interlock Checkout
Valve controls
Viewer reconnects
LCW Hook-ups
Laser box sealing
Sa 9a: Magnet Hook-Ups
60Hz Snooping
Tunnel
Afternoon
Vacuum Work
Laser Hut Work
Magnet Hook-Ups
Laser Hut Work
De-gas stalk heater
Gun HV Eval Preps
Magnet Hook-Ups
Laser Hut Work
430p: Lock-up to Power Permit
Gun HV Eval
Magnet Hook-Ups
Laser Hut Work
4p: Neilson WalkThru
430p: Lock-up to Power Permit
Gun HV Eval
Magnet Hook-Ups
Laser Hut Work
Sa Magnet Hook-Ups
60Hz Snooping


4/16: Weekend work plans in the Injector?


  • BPM = Francis
  • Valve Controls = Ketchum
  • ItoV, Picoammeters, Gun FSD Interlocks = Francis
  • Viewers = Norris
  • Harps = Dela Cruz
  • Magnet / DC Power = Coleman, others in group
  • 2B Alignment = S&A, Gould
  • PSS = Kowal


InjSB Racks no pene.png

Week 29 (Apr 19 - Apr 23)

Phase 1 - HCO & Commissioning


Tunnel work
  • System Reconnects and HCO
  • Laser->photocathode alignment, retro-reflection measurement (Zhang, Grames, Windham)
  • Vacuum work (Stutzman)
    • T/S VIP2I00 noise
    • Relocating VCG5D01 to main beamline, ATLis 22270 (Stutzman) Tues
    • Pumping down 5D "stub" (i.e. remaining 5D beamline) (Stutzman) Tues
  • Plumbing air lines to viewers (CIS, Norris)
  • Air line system-segmentation (viewer, beamline valves) (Stutzman, Bullard)
  • Magnet hook-ups (DC Power -- Coleman, Delk, Kumar) Afternoons
    • MDR1I02 attachment (Grames) Tues
  • Diagnostics reconnects Mornings
    • Viewers (Norris)
    • Harps (Dela Cruz)
    • BPMs, Picoammeters, ItoV (Francis)
  • LCW Flow measurement through flow meters that interlock cups and apertures (Francis) Mon
  • PCup flowmeter enhanced testing (Francis)
  • 2I BPM hook-ups (Francis) Tues
  • LCW hook-ups (Adderley, Francis)
  • Wien HV cable terminations (Dela Cruz)
  • A1 EPICS controls (Windham, Higgins) Tues
  • Warm RF Work (Wissman, Farrish)
    • Chopper, prebuncher, amplifier hook-ups Mon
    • Chopper water line leak repair Mon
    • LLRF testing and adjustments for prebuncher Tues
    • Powering on prebuncher, choppers W-F
    • Prebuncher tuning Wed
    • Chopper tuning
  • Mech bracket walkthru (Gregory, Grames) Mon
  • 60Hz electrical noise snooping (Suleiman) Evenings (after 4p)
  • PSS Kicker removal (SSG) Thur
  • Unlocking FC1, locking in A3/A4 apertures (SSG) Thur
  • PCup-A1 Region (VBV1I07->0I02) & A2-FC1 Region (VBV0I02->0I07) Bake Prep
    • Remove PSS kicker, push back conduit (SSG)
    • Remove instrument solenoids from girders (Dela Cruz)
    • Move back non-bakable cables, air lines (CIS)
    • Staging insulation, oven equipment (Bullard)
    • Leak checks (Stutzman)
    • Ion pump evaluations
    • Gasket swaps Fri


ISB Work
  • System re-connects / associated rack work
  • A1 EPICS controls work (Windham, Higgins)
  • iocin1 VME crate swap, IN03B04 (Dela Cruz), Mon 9a
  • Wien HV System, IN01B0{0,1} (Dela Cruz)
  • Safety WalkThru (Moser, Fanning, Johnson, Williams) Tues 230p
  • Magnet Cabling, IN02B{10,11,22,26}, IN04B10 (DC Power, Coleman)
  • Bunchlength amp re-install, IN02B23 (Musson)


Injector Tunnel and Service Building

Location
Time
Mon 4/19 Tue 4/20 Wed 4/21 Thu 4/22 Fri 4/23
InjSB
All Day
System Reconnects
CIS Rack Work
System Reconnects
CIS Rack Work
System Reconnects
CIS Rack Work
System ~Reconnects
CIS Rack Work
System ~Reconnects
CIS Rack Work
InjSB
Early
Morning
(<9a)
Associated Rack Work Associated Rack Work Associated Rack Work Wien HV System Wien HV System
InjSB
Morning
Associated Rack Work 9a: iocin1 VME Crate Swap
Wien HV Cable Termination
Prebuncher LLRF
Associated Rack Work
Wien HV Cable Terminations
Associated Rack Work
Wien HV System
Warm RF Cabling
Wien HV System
Bunchlength amp re-install
InjSB
Afternoon
Associated Rack Work Prebuncher LLRF
Associated Rack Work
Associated Rack Work Magnet Cabling Magnet Cabling
Tunnel
All Day
CIS Vacuum Work --
VBV2I01A Solenoid
CIS Vacuum Work --
*Relocating VCG5D01
*5D stub pumpdown
CIS Vacuum Work --
*Valving in CCG
to main beamline
VBV1I07->0I07 Leak Checks
Bake Prep
PCup-A1 / A2-FC1 regions
Bake Prep - Gasket Swaps
Tunnel
Early
Morning
(<9a)
Viewer Reconnects
Viewer Reconnects
PCup Flowmeter
Viewer Reconnects
Wien HV cable terminations?
Wien HV cable terminations Wien HV cable terminations
Tunnel
Morning
915a Mech Bracket Walkthru
2I BPM Connections
Viewer air lines
Flowmeter flow measurement
Viewer Reconnects
2I BPM Hook-ups
Air line system segmentation
Viewer Reconnects
Wien HV cable terminations?
Air line system segmentation
Prebuncher Tuning/Controls
Laser hut work
Leak Checks
VBV2I01A T/S, Repair
Unlock FC1, Lock-In A3/A4
Bake Prep:
PSS Kicker Removal
Instrument Solenoid Dismounts
Oven/insulation staging
Bake Prep - Gasket Swaps
Tunnel
Afternoon
Magnet hook-ups
Laser Hut Work
Magnet hook-ups
A1 EPICS Controls
230p: Safety WalkThru
Laser Hut Work
MDR1I02 attachment
2p: Laser->cathode alignment

Vacuum Recovery
Bake Prep
Prebuncher testing/tuning
5D-VCG cabling
Bake prep - Gasket Swaps

WEEKEND WORK PLANS??

Tunnel Personnel Loading Limits: Injector, upstream of plastic curtain, total=8 -> 4 upstream of laser hut, 4 downstream of laser hut

InjSB Racks no pene.png


Week 30 (Apr 26 - Apr 30)

Phase 1 - HCO & Commissioning


Screen Shot 2021-04-23 at 8.33.33 AM.png


Tunnel work
  • Re-Bake Work
    • As-found surveys of A1, A2 (S&A) Mon
    • Continue ion pump evaluations
    • Vent VBV1I07->0I07 and swap gaskets Mon
      • Decided NOT to swap A2 gaskets at this time
    • Re-align A1 (S&A) Mon
    • Rough pumpdown of VBV1I07->0I02 region (A1-region) Mon
    • Leak checks VBV1I07->0I07 Mon/Tues
    • Bake setup Tues-Wed
    • Begin A1-region (VBV1I07->0I02) re-bake Wed+
    • NEG activations --
      • Unbaked region, A2 (0I02) and 0I07 DP Can Tues
      • Baked A1-region, 0I00 DP Can and A1 (0I01A)
  • VBV2I01A Position Indication and Solenoid T/S, Documentation, Verification (Windham) Mon
  • Laser->photocathode alignment, retro-reflection measurement (Zhang, Grames, Windham) Tues
  • Wien HV cable terminations (Dela Cruz)
  • Viewer reconnects and HCO (Norris)
  • Magnet Connections and HCO (Coleman)
    • Layout terminal blocks
    • Magnet lead reinforcement
    • Magnet wiring
    • Install MDR1I02 (CIS, Grames)
  • Warm RF Work (Wissman, Farrish)
    • Prebuncher conditioning
    • Prebuncher readback calibrations
    • Chopper tune-check/tuning
  • 60Hz electrical noise snooping (Suleiman) Evenings (after 4p)
  • System re-connects and HCO (EES, CIS, Ops)


ISB Work
  • System re-connects / associated rack work
  • CIS Rack Work, IN01* (Windham)
  • Viewer Terminations, IN01B04 (Norris, Mock) Mon-Tues
  • Harp cabling, terminations, IN01B03, IN03B0{6,7} (Dela Cruz) Tues
  • Magnet Cabling, IN02B{10,11,22,26}, IN04B10 (DC Power, Coleman)
  • Wien HV System, IN01B0{0,1} (Dela Cruz)


Injector Tunnel and Service Building

Location
Time
Mon 4/26 Tue 4/27 Wed 4/28 Thu 4/29 Fri 4/30 Sat 5/1 Sun 5/2
InjSB
All Day
Systems HCO
CIS Rack Work
Systems HCO
CIS Rack Work
Systems HCO
CIS Rack Work
Systems HCO
CIS Rack Work
Systems HCO
CIS Rack Work
InjSB
Early
Morning
<9a
Viewer Terminations Viewer Terminations
Harp Cabling/Terminations
Associated Rack Work Associated Rack Work Associated Rack Work
InjSB
Morning
Viewer Terminations Viewer Terminations
Harp Cabling/Terminations
Associated Rack Work Associated Rack Work Associated Rack Work Chopper Hook-Ups
InjSB
Afternoon
Magnet Cabling, HCO Magnet Cabling, HCO Magnet Cabling, HCO Magnet Cabling, HCO Magnet Cabling, HCO Magnet Cabling, HCO
Tunnel
All Day
A1/A2 gasket swaps VBV1I07->0I02 = A1-region
Bake Setup
A1-region Re-Bake A1-region Re-Bake A1-region Re-Bake A1-region Re-Bake
Rampdown
A1-region Re-Bake
Rampdown
Tunnel
Early
Morning
<9a
As-found surveys A1, A2
Diagnostics HCO/Reconnects
as possible
Wien HV Cable Terminations
Diagnostics HCO/Reconnects
as possible
0I02 Anti-collision/harp
Viewer Reconnects
Wien HV terminations
Viewer Reconnects
Wien HV terminations
Viewer Reconnects
7-8a: LCW Tests
Tunnel
Morning
A1 Gasket Swaps
Re-Alignment
Rough Pumpdown

Wien HV Cable Terminations
Ion pump checkout
VBV2I01A Work
Final A1-region leak check
VIP0I0{0,1,1A,2} FE Hunt
A1-region Bake Setup
0I02 NEG Activation
Prebuncher conditioning
930-10a: Hoey Safety WalkThru
Viewer Reconnects
Wien HV terminations
Prebuncher conditioning
Cable Org/Vert Tray
Viewer Reconnects
Prebuncher conditioning

Viewer Reconnects
Prebuncher conditioning
0I07 NEG Activation
0I0{0,1A} NEG Activations
Chopper Hook-Ups
11a: Magnet reconnects and HCO
Tunnel
Afternoon
A1 rough pumpdown
Leak checks VBV1I07->0I07
VBV2I01A Work
Begin A1-region Bake
Laser alignment/retroreflection
Prebuncher conditioning < ~2p
Magnet HCO/Reconnects
as possible
Prebuncher conditioning
Cable Org/Vert Tray
Magnet HCO/Reconnects
as possible
Laser Hut Work
1p: PD WalkThru
Prebuncher conditioning
Magnet HCO/Reconnects
as possible
Laser Hut Work
Prebuncher Conditioning
Magnet HCO/Reconnects
as possible
Laser Hut Work
Magnet reconnects and HCO

Tunnel Personnel Loading Limits: Injector, upstream of plastic curtain, total=8 -> 4 upstream of laser hut, 4 downstream of laser hut


InjSB Week30 1.png


Week 31 (May 3 - May 7)

Tunnel work
  • System re-connects and HCO (EES, CIS, Ops)


  • A1-region bake takedown (Stutzman, Bullard) Mon
  • VBV2I01A Solenoid Air Leak T/S (Windham) Mon
  • Laser hut work (Zhang)
  • Photocathode shuffle (Grames)
    • Remove bulk GaAs
    • Load in SSL cathodes
    • Activate cathode
  • Ion pump checkout (Stutzman)
    • Set operational voltages
    • Hi-pot FE'ing pumps
    • Configure system for EPICS


  • Main airline leaky valve swap (pics) (MechInstall) Thurs
  • Viewer reconnects and HCO (Norris)
  • Harp reconnects and HCO (Dela Cruz)
  • Magnet Connections and HCO (Coleman)
    • Layout terminal blocks
    • Magnet lead reinforcement
    • Magnet wiring
    • Install MDR1I02 (CIS, Grames)
  • Warm RF HCO (Wissman, Farrish)
    • Chopper turn-on, conditioning
    • Buncher turn-on, conditioning
    • Capture turn-on, conditioning
    • Prebuncher readback calibrations, GDR operation (Plawski)
  • 60Hz electrical noise snooping (Suleiman) Sat
  • Helicity magnet HCO (Suleiman) Sat
ISB Work
  • System re-connects / associated rack work
  • CIS Rack Work, IN01* (Windham)
  • Magnet Cabling, IN02B{10,11,22,26}, IN04B10 (DC Power, Coleman)
  • Wien HV System, IN01B0{0,1} (Dela Cruz)
  • Penetration 78 (IN02B18) and 86 (IN02B23) Stone Top-Off (MechInstall) Tues early AM
  • VEPCO Automatic Voltage Regulators Test, ATLis 22392 Friday
    • Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
    • Incoming power voltage variation < +/- 10%
    • "Be prepared for a power interruption"

Injector Tunnel and Service Building

Location
Time
Mon 5/3 Tue 5/4 Wed 5/5 Thu 5/6 Fri 5/7 Sa 5/8 Su 5/9
InjSB
All Day
Systems HCO
CIS Rack Work
Systems HCO
CIS Rack Work
Systems HCO
CIS Rack Work
Systems HCO
CIS Rack Work
⚡VEPCO Voltage Tests
Systems HCO
CIS Rack Work
InjSB
Early
Morning
<9a
Associated Rack Work Chopper/Buncher HCO Chopper/Buncher HCO Buncher/Chopper HCO Viewer/harp HCO
InjSB
Morning
Chopper/Buncher HCO
Prebuncher Rdbk Cals
Chopper/Buncher HCO
Wien Sys Walkthru
Pene 78 & 86 Top-Off
Chopper/Buncher HCO
Wien HV Cable Chkout
Buncher/Chopper HCO Chopper Vac Intlk Testing
9-11a: Wien HV Calibrations
VBV0I02 UHV Interlocks
Magnet HCO Magnet HCO
InjSB
Afternoon
Chopper/Buncher HCO
Prebuncher Rdbk Cals
Magnet re-connects, HCO
Chopper/Buncher HCO
Magnet re-connects, HCO
Chopper/Buncher HCO
Magnet re-connects, HCO
Magnet re-connects, HCO
4p: Capture HCO, Conditioning
Magnet re-connects, HCO
VBV0I02 UHV Interlocks
Magnet HCO Magnet HCO
Tunnel
All Day
CIS Reconnects
A1-region Bake Takedown
CIS Vacuum Work
Ion pump checkout
VIP0I01/1A HiPot
Device/line labeling
Other CIS Jobs
PCup, A1, A2 LCW
PCup, A1 Current Pigtails
Photocathode shuffle
CIS Laser Hut Work:
*Laser checks
*1/2 waveplate T/S
System Reconnects & HCO
⚡VEPCO Voltage Tests
System Reconnects & HCO
Tunnel
Early
Morning
<9a
Viewers (1 ppl) (away from A1)
A1-region bake takedown
Viewers (1 ppl)
Wien Interlock Cables (1 ppl)
CIS Jobs (1-2 ppl)
Viewers (1 ppl)
Harp / Wien (1 ppl)
BPM (1 ppl)
Buncher, Capture hook-ups (1 ppl)
7a: Main Airline Valve Swap (2ppl)
Harp / Wien (1ppl)
Waterflow Interlocks /
ItoV System HCO (1 ppl)
* Craning in cage/suitcase
for equipment removal (1-2ppl)
* Viewers (1 ppl)
* Harp (1ppl)
Tunnel
Morning
Viewers (1 ppl) (away from A1)

A1-region Leak Checks
Viewers (1 ppl)
11-1130a: Wien Sys Walkthru (2 ppl)
CIS Vac Work (1-2 ppl)
Viewers (1 ppl)
9a-noon: Wien HV Cable Chkout (2ppl)
BPM (1 ppl)
A1, A2, PCup LCW (1 ppl)
Wien HV T/S (1-2 ppl)
Waterflow Interlocks /
ItoV System HCO (1 ppl)
Ion pump T/S (1ppl)
MDR1I02 Cabling (1ppl)
1/2 waveplate T/S
Viewers (1 ppl)
9a: Wien HV Cals (1-2 ppl)
10a: IPM1I02 Connect/HCO (1-2ppl)
NEG Terminations (1ppl)
1/2 waveplate T/S
Magnet Resistances, Inductances, Mapping (1-2ppl) Magnet Resistances, Inductances, Mapping (1-2ppl)
Tunnel
Afternoon
A1-region reattachments --
air/water lines, pickups,
control boxes/solenoids
Magnet (2-4 ppl)
Magnet (3 ppl)
Swings (4p): Lock-up, 0L02 HPA PSS Cert
After: PSS Kicker Install
Magnet (2-4 ppl)
Laser hut work
4p: Lock-up for Capture HCO
Magnet (2-4 ppl)
Laser hut work
4p: PSS Kicker install (1-2ppl)
Magnet Resistances, Inductances, Mapping (1-2ppl)
60Hz Snooping (1ppl)
Helicity Mag HCO (1ppl)
Magnet Resistances, Inductances, Mapping (1-2ppl)

Tunnel Personnel Loading Limits: Injector, upstream of plastic curtain, total=8 -> 4 upstream of laser hut, 4 downstream of laser hut

InjSB Week30 1.png

Points of Contact by system --

  • BPM = Francis
  • Valve Controls = Ketchum
  • ItoV, Picoammeters, Gun FSD Interlocks = Francis
  • Viewers = Norris
  • Harps = Dela Cruz
  • Wien = Dela Cruz
  • Magnet / DC Power = Coleman
  • Warm RF -- prebuncher, buncher, chopper, capture = Wissman
  • 2B Alignment = S&A, Gould
  • PSS = Kowal

Week 32 (May 10 - May 14)

Tunnel work
  • Finish HCO ====> Beam Commissioning!
    • First CEBAF beam of 2021
    • First ~4m of Injector newly upgraded


  • Equipment crane-out (MechInstall)
  • Viewer HCO (Norris)
  • Harp 0I02 electronics install and HCO (Dela Cruz)
  • Magnet HCO (Coleman)
  • CIS HCO
    • Laser alignment optimization (Zhang)
    • 1/2 Waveplate T/S (Windham)
    • Photocathode activation (Grames)
    • Wien system HCO (Hernandez-Garcia, Dela Cruz)
    • Ion pump noise investigation (Stutzman)


  • 60Hz electrical noise snooping (Suleiman) evenings


ISB Work
  • CIS Rack Work, IN01* (Windham)
  • Wien System HCO, IN01B0{0,1} (Dela Cruz, Hernandez-Garcia)
  • ItoV System Checkout, FC2 unlock (Francis) Mon
  • Magnet HCO, IN02B{10,11,26}+IN04B10 (Coleman)
  • Viewer HCO, IN01B04+IN03B0{6,7} (Norris)
  • Harp HCO, IN01B03+IN03B06 (Dela Cruz)


  • VEPCO Automatic Voltage Regulators Test, ATLis 22392 Tuesday, 1030a - noon (if all goes well)
    • Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
    • Incoming power voltage variation < +/- 10%
    • "Be prepared for a power interruption"


Injector Tunnel and Service Building

italics = timing less certain
Location
Time
Mon 5/10 Tue 5/11 Wed 5/12 Thu 5/13 Fri 5/14 Sa
5/15
Su
5/16
InjSB
All Day
Hot Checkout Hot Checkout ⚡VEPCO Voltage Tests
9-11a

Hot Checkout
Hot Checkout Hot Checkout
Service Building Clean-Up
Site Phone Outages
8a - 5p
InjSB
Early
Morning
<9a
Viewer HCO
ItoV/Picoam. HCO
Viewer HCO
Harp HCO
Viewer HCO
Harp Cross-Connect Wiring, HCO
ItoV System HCO
InjSB
Morning
V-Wien Comm Conn Remedying Magnet HCO ItoV HCO
Magnet HCO
Wien HV Interlock
Testing and HV Soak
Wien HV Soak (+B-field?)
InjSB
Afternoon
Magnet HCO Magnet HCO Magnet HCO Wien HV Soak
Magnet HCO
Wien HV Soak
Magnet HCO
Tunnel
All Day
Hot Checkout Hot Checkout
CIS Work --
* Airline->metal
* IP Noise T/S
⚡VEPCO Voltage Tests
9-11a

Hot Checkout
CIS Work
2B Alignment
Hot Checkout
2B Alignment
Hot Checkout
CIS Jobs = Gun Valve T/S
TMG shutter T/S
Wien HV Soak
Site Phone Outages
8a - 5p
Wien HV Soak
Tunnel
Early
Morning
<9a
Equipment crane-out (1-2 ppl)
Viewer HCO (1 ppl)
0I02 harp electronics (1ppl)
Photocathode activation (1ppl)
Viewer HCO (1ppl)
Harp HCO (1ppl)
Viewer HCO (1 ppl)
0I02 anti-collision testing (1 ppl)
ItoV/Picoam. HCO (1ppl)
2B Alignment (2 ppl) 2B Alignment (2 ppl)
0I02 Anti-collision (1 ppl)
CIS Jobs (1-2ppl)
Tunnel
Morning
Viewer HCO (1 ppl)
Wien interlock (1-2ppl)
Ion pump noise (1 ppl)
1/2 waveplate T/S
Viewer HCO (1 ppl)
Harp HCO (1 ppl)
CIS Work (1-2ppl)
1/2 waveplate T/S
830-9a: Cryo tour (3ppl)
Viewer HCO (1 ppl)
0I02 anti-collision testing (1 ppl)
ItoV/Picoam. HCO (1ppl)
CIS Work (1-2ppl)
2B Alignment (2 ppl) 2B Alignment (2ppl)
0I02 Anti-collision (1 ppl)
CIS Jobs (1-2ppl)
Laser Hut Work
FML HVAC Reconfig (2 ppl)?
60 Hz Snooping (1ppl)
Tunnel
Afternoon
Laser hut work
Magnet HCO (2-4ppl)
Laser hut work
Magnet HCO (2-4ppl)
Photocathode activation (1 ppl)
Laser hut work
Magnet HCO (2-4ppl)
4p Lock-Up: PSS Certs -> BP
Laser hut work
Magnet HCO (2-4ppl)
4p Lock-Up: PSS Certs -> BP
Laser hut work
Magnet HCO (2-4ppl)
QE Scan? (2 ppl)
60 Hz Snooping (1ppl)

Tunnel Personnel Loading Limits: Injector, upstream of plastic curtain, total=8 -> 4 upstream of laser hut, 4 downstream of laser hut


InjSB Week30 1.png


Points of Contact by system --

  • BPM = Francis
  • Valve Controls = Ketchum
  • ItoV, Picoammeters, Gun FSD Interlocks = Francis
  • Viewers = Norris
  • Harps = Dela Cruz
  • Wien = Dela Cruz
  • Magnet / DC Power = Coleman
  • Warm RF -- prebuncher, buncher, chopper, capture = Wissman
  • 2B Alignment = S&A, Gould
  • PSS = Kowal


Week 33 (May 17 - May 21)


HCO to 500keV completed 5/21
Beam Authorization granted 5/21


  • 22462 0I02 Harp Repair
    • Wednesday: beamline component disconnects and vent, begin harp swap
    • Thursday: complete harp swap, pumpdown, leak check, verify harp operation, setup and begin overnight bake
    • Friday: Bake cool by 8AM. Re-install beamline components, re-HCO components


  • VEPCO Automatic Voltage Regulators Test, ATLis 22392
    • Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
    • Incoming power voltage variation < +/- 10%
    • "Be prepared for a power interruption"


Injector Tunnel and Service Building

Location
Time
Mon 5/17 Tue 5/18 Wed 5/19 Thu 5/20 Fri 5/21
InjSB
All Day
Service Building Clean-Up
Hot Checkout
Service Building Clean-Up
Hot Checkout
Service Building Clean-Up
Hot Checkout
⚡VEPCO Voltage Tests
1030a-noon (4th attempt?)
Service Building Clean-Up
Hot Checkout
Service Building Clean-Up
Hot Checkout
InjSB
Early
Morning
<9a
InjSB
Morning
Magnet HCO Magnet HCO Magnet Rack HCO Magnet Rack HCO
InjSB
Afternoon
Magnet HCO Magnet HCO Magnet Rack HCO Magnet Rack HCO
Tunnel
All Day
Wrapping up HCO
Wien HV Soak
Wrapping up HCO
Wien HV Soak
Beam Commissioning
0I02 Harp Repair
⚡VEPCO Voltage Tests
1030a-noon (4th attempt?)
Wrapping up Magnet HCO 0I02-"region" Reconnects
Beam Commissioning?
Tunnel
Early
Morning
<9a
0I02 anti-collision (1 ppl)
Turbopump hook-up at 0I06 (1ppl) 0I02-"region" reconnects
Wien Resistor LCW Fittings
Tunnel
Morning
Magnet HCO (2-5ppl) Magnet HCO
11a: HCO Committee tour (3ppl)
830-9a: Cryo tour (3ppl)
0I02 Harp Repair (3ppl)
Laser mirror work
0I02 NEG Activation
Bake Takedown (2ppl)
Magnet HCO (2-5ppl)
Wien resistor cooling
0I02-"region" Reconnects --
Magnets
YAG, A2, BPM, Harp
PSS Kicker

Wien resistor cooling
Tunnel
Afternoon
Laser hut work?
Magnet HCO (2-5ppl)
Evening: 60Hz snooping
0I02 Harp Repair (3ppl) Magnet HCO (2-5ppl)
Wien resistor cooling
12p Lock-up: M0 PSS Certs
Beam Auth
Transitioning to Beam Ops

Tunnel Personnel Loading Limits: Injector, upstream of plastic curtain, total=8 -> 4 upstream of laser hut, 4 downstream of laser hut

InjSB Week30 1.png

Penetration Work

4/9 Update:
All five penetrations that had been opened are now closed, sealed, and appropriate stone/Pb-brick shielding returned. {58, 86, 108, 135} - re-filled with stone and levels verified by RadCon. Laser hut penetration closed, sealed, and Pb brick shielding re-installed.


4/2 Update:
Laser hut penetration remains open until conclusion of Wien/Y-chamber bake, early next week. (only gets closed and sealed, no stone)
58, 86, and 108 closed and sealed. May be filled with stones at this point.
135 remains open. To be closed, sealed, and filled next week.


InjSB Penetrations that are open (click for pictures, last updated 2/18/21): above laser hut, 58, 86, 108, 135

  • 34ft from floor of InjSB to floor of Inj tunnel
  • 25ft from floor of InjSB to elevated Inj tunnel cable tray

Penetration Cable Pulls/Removals --

  • (C. Jones) Dehumidifier wire pull, penetration 135, ETA: end of week of 3/1
  • (Wissman) Pulling Prebuncher heater control cables, laser hut penetration, ETA: ~3/4 or 5
  • (FML) Add/pull flex conduit to laser hut, 86, and 108 penetrations
    • 86 and 108 too full for 2" flex pull
    • Laser hut deemed too full as well
  • (Dela Cruz) Pulling new Wien E-field HV cables, through flex conduit, laser hut penetration may be re-filled
  • Norris removing old Cat5 viewer cables
  • Norris pulling new viewer cables
  • Riad/Scott removing old Mott HV cables
  • Coleman pulling new Wien B-field magnet cables
  • Cole pulling new neutron detector cables (above 0L03)
  • Scott pulling motor control cables for A1++

InjSB Racks.png


Fire System Work

Description of Task: Replacement of tunnel sprinkler piping, fire alarm control panels in B85 & B98, replacement of detection devices.

update 11/9: 25% of demo completed
update 11/23: demo completed
update 12/8: fire pipe installation in Injector slated for Winter break ~12/21 - 1/3
"The drawings needed prior to fabrication of the INJ fire pipe have not gone through the system." No fire pipe install work over winter break.
update 1/7/21: Tentative fire pipe install to occur week of 1/18 in tunnel. Should take 3-4 days, so with the holiday on Monday, likely the rest of the week.
Further fire pipe work upstairs in the service will also need 3-4 days, but won't be constant (i.e. contractor will be in and out).
update 1/18/21: New pipe arriving Fri 1/22. No install work week of 1/18.
update 1/20/21: fire pipe installation to begin 1/22 and continue over weekend 1/23+24.
update 2/1/21: fire pipe installation, air pressure and hydro tests complete.