Line 13: | Line 13: | ||
**Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30) | **Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30) | ||
**Goal is HCO/System readiness for everything up to FC#2 | **Goal is HCO/System readiness for everything up to FC#2 | ||
+ | |||
*Preliminary Songsheet | *Preliminary Songsheet | ||
** Most recent posted on Friday Feb 18 | ** Most recent posted on Friday Feb 18 | ||
** Search Layout area on the upgrade home page => [[CEBAF Injector Upgrade]] | ** Search Layout area on the upgrade home page => [[CEBAF Injector Upgrade]] | ||
+ | |||
; I&C Jobs | ; I&C Jobs | ||
* What to expect in tunnel? | * What to expect in tunnel? | ||
− | ** Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2) | + | ** Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2) |
− | ** Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable | + | ** There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory |
+ | ** Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable trays (above & on girder) + 3 cable bundle drops (Y, Laser, Chopper) | ||
+ | |||
+ | * BPMs | ||
+ | ** 10 total - all unrotated | ||
+ | ** 3 new style => NEG coated large bore (2.5" ID); mapped by Musson (Kx/Ky values available) | ||
+ | ** 7 old style => 5.5" long end tapped | ||
+ | |||
* Viewers | * Viewers | ||
** 8 total - all chromox except ITV0I02 (YAG) | ** 8 total - all chromox except ITV0I02 (YAG) | ||
** Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01 | ** Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01 | ||
** Crash inhibit #2 : ITV0I02 and Harp IHA0I02 | ** Crash inhibit #2 : ITV0I02 and Harp IHA0I02 | ||
+ | |||
+ | * Harps | ||
+ | ** 1 total - IHA0I02 (YAG), on same cross as viewer ITV0I02 (requires crash inhibit) | ||
+ | |||
+ | * Wien HV | ||
+ | ** Tony status update | ||
+ | |||
+ | * Current Monitoring | ||
+ | ** 3 total - same as before (PCUP, A1, A2) | ||
+ | ** PCUP identical as before, just a new location | ||
+ | ** A1 current monitoring as before, linear bellow motion now has STAC5 motor (so remote or manual; has 3 stop positions | ||
+ | ** A2 current monitoring as before, linear bellows manual as before; has 3 stop positions. Used by PSS group for kicker | ||
+ | |||
* Valves | * Valves | ||
** 3 total - all have in-line EPICS shut over ride capability (CIS installs this box) | ** 3 total - all have in-line EPICS shut over ride capability (CIS installs this box) | ||
Line 30: | Line 52: | ||
** Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07 | ** Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07 | ||
** All 3 valves tied to UHV vacuum fault (100 uA limit) | ** All 3 valves tied to UHV vacuum fault (100 uA limit) | ||
+ | |||
* Ion pumps | * Ion pumps | ||
** Marcy's final list [[media:210209_ion pump names.xlsx]] | ** Marcy's final list [[media:210209_ion pump names.xlsx]] | ||
− | + | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
; Software Jobs | ; Software Jobs | ||
* CED | * CED | ||
** Michele or Gary can gives us an update | ** Michele or Gary can gives us an update | ||
+ | |||
* Apps | * Apps | ||
** Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms | ** Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms | ||
** Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job | ** Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job | ||
+ | |||
* Screens | * Screens | ||
** I guess many screens auto-updated from CED, that's great | ** I guess many screens auto-updated from CED, that's great | ||
** Like with apps, will need name review; I guess system owners look at their own screens for oddities? | ** Like with apps, will need name review; I guess system owners look at their own screens for oddities? | ||
+ | |||
* What else for software? | * What else for software? | ||
+ | |||
; CIS Jobs | ; CIS Jobs | ||
* Let's quickly scan CIS jobs, see if we missed anything [[Phase 1 - HCO & Commissioning]] | * Let's quickly scan CIS jobs, see if we missed anything [[Phase 1 - HCO & Commissioning]] | ||
+ | |||
; Plans | ; Plans | ||
* Jobs list => Phase 1 area on the upgrade home page => [[CEBAF Injector Upgrade]] | * Jobs list => Phase 1 area on the upgrade home page => [[CEBAF Injector Upgrade]] |
Latest revision as of 12:33, 22 February 2021
Meeting Info =
We will meet Monday February 22 @ 1:30 pm via BlueJeans Meeting URL (for video and/or audio call in): https://bluejeans.com/7572697097 Phone number (for audio call in): 1-888-240-2560 Meeting ID: 7572697097#
Agenda
- Installation status
- Schedule
- Transition from vac/mech to girder hook-ups planned to begin April 5 (6 weeks from today)
- We may be ready early by 1 or 2 weeks (no sooner than mid-March)
- Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30)
- Goal is HCO/System readiness for everything up to FC#2
- Preliminary Songsheet
- Most recent posted on Friday Feb 18
- Search Layout area on the upgrade home page => CEBAF Injector Upgrade
- I&C Jobs
- What to expect in tunnel?
- Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2)
- There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory
- Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable trays (above & on girder) + 3 cable bundle drops (Y, Laser, Chopper)
- BPMs
- 10 total - all unrotated
- 3 new style => NEG coated large bore (2.5" ID); mapped by Musson (Kx/Ky values available)
- 7 old style => 5.5" long end tapped
- Viewers
- 8 total - all chromox except ITV0I02 (YAG)
- Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01
- Crash inhibit #2 : ITV0I02 and Harp IHA0I02
- Harps
- 1 total - IHA0I02 (YAG), on same cross as viewer ITV0I02 (requires crash inhibit)
- Wien HV
- Tony status update
- Current Monitoring
- 3 total - same as before (PCUP, A1, A2)
- PCUP identical as before, just a new location
- A1 current monitoring as before, linear bellow motion now has STAC5 motor (so remote or manual; has 3 stop positions
- A2 current monitoring as before, linear bellows manual as before; has 3 stop positions. Used by PSS group for kicker
- Valves
- 3 total - all have in-line EPICS shut over ride capability (CIS installs this box)
- Gun valve - VBV2I01A (new name), otherwise same all metal gate valve
- Beam line valve - VBV1I07 (same name), same all metal gate valve
- Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07
- All 3 valves tied to UHV vacuum fault (100 uA limit)
- Ion pumps
- Marcy's final list media:210209_ion pump names.xlsx
- Software Jobs
- CED
- Michele or Gary can gives us an update
- Apps
- Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
- Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
- Screens
- I guess many screens auto-updated from CED, that's great
- Like with apps, will need name review; I guess system owners look at their own screens for oddities?
- What else for software?
- CIS Jobs
- Let's quickly scan CIS jobs, see if we missed anything Phase 1 - HCO & Commissioning
- Plans
- Jobs list => Phase 1 area on the upgrade home page => CEBAF Injector Upgrade
- Will meet with Magnets, DC Power, Software next Monday Mar 4, you're welcome to join
- When should WE meet again and leading up to April 5?
- Then 8am and Toolbox meetings at 8:30
- Tally ho!