Line 27: | Line 27: | ||
===Geant4 Model=== | ===Geant4 Model=== | ||
* | * | ||
+ | |||
+ | ===Action Items=== | ||
+ | * Gary - extend spool and support two locations, relocate table further downstream, layout modifications for lead wall with hole, check stand status at mech. shop | ||
+ | * Sandesh/Probir - follow-up with EMC re-making coil, tally list of jobs once magnet on-site | ||
+ | * Joe - coordinate cable pulls with Nick and Nate, 20A/120VAC circuit in mech. room with FML, order spool flanges | ||
+ | * Chris - complete rack assembly for UITF, order triax connectors | ||
+ | * Bryan - work with Gary for soft ioc and Brad to activate network port | ||
+ | * Greg - compute integrated asymmetry, simulate 5 configurations, use slurm to run jobs on farm | ||
+ | * Riad - coordinate with Bryan/Hai for 4 usec integration testing, implement for Mott, forward detector studies | ||
===Documentation=== | ===Documentation=== | ||
* NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a | * NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a | ||
* Manual - Sharepoint | * Manual - Sharepoint |
Latest revision as of 18:28, 18 August 2022
- Thursday's @ 9am EDT by Zoom
- Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
- Zoom ID: 160 190 6056 and Passcode: 992019
DAQ
- DAQ install at UITF media:220817_DAQ_PREP.pptx
Beamline
- Layout for RadCon media:Compton Layout for Radcon Shielding 8-10-22-3.pptx
- Spool flanges media:Flanges and Reducer for Compton and RF Kicker-jmg.xlsx
- Radiator - (1) on-hand, (1) need for BNL thumb
- Stands PR Shop Job
- Lead for UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 thumb
Magnet
- Kepco PS - ship 8/31 2 day air => PR
- Magnet EMC PR#1PR#2 coil thumb
Detector
- Bases - due 9/15 - comes with Thi in September
- Collimator - (2) on-hand media:JL0015777_Cu_collimator.pdf thumb
- Absorbers - (6) on-hand media:Absorber - 240 D 001 14_V4.pdf thumb
- Boxes - (2) on hand thumb
- BGO - (2) on-hand thumb thumb thumb thumb thumb
- PMT and mu shields - (4) on-hand thumb
Geant4 Model
Action Items
- Gary - extend spool and support two locations, relocate table further downstream, layout modifications for lead wall with hole, check stand status at mech. shop
- Sandesh/Probir - follow-up with EMC re-making coil, tally list of jobs once magnet on-site
- Joe - coordinate cable pulls with Nick and Nate, 20A/120VAC circuit in mech. room with FML, order spool flanges
- Chris - complete rack assembly for UITF, order triax connectors
- Bryan - work with Gary for soft ioc and Brad to activate network port
- Greg - compute integrated asymmetry, simulate 5 configurations, use slurm to run jobs on farm
- Riad - coordinate with Bryan/Hai for 4 usec integration testing, implement for Mott, forward detector studies
Documentation
- NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
- Manual - Sharepoint