Difference between revisions of "Mar 27 2024"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "==Updates== * Fabrication ** A new puck manipulator made out of Teflon and 24 inches long was designed and drawing submitted to the shop for fabrication. This manipulator wil...")
 
 
(12 intermediate revisions by the same user not shown)
Line 2: Line 2:
  
 
* Fabrication
 
* Fabrication
** A new puck manipulator made out of Teflon and 24 inches long was designed and drawing submitted to the shop for fabrication. This manipulator will be used to insert pucks into the spherical electrode while still mounted to the gun vacuum chamber during S&A and laser retro-reflection chess in the LERF Lab 3A clean room.
+
** A new puck manipulator made out of Teflon and 24 inches long was designed and drawing submitted to the shop for fabrication. This manipulator will be used to insert pucks into the spherical electrode while still mounted to the gun vacuum chamber during S&A and laser retro-reflection checks in the LERF Lab 3A clean room.
**  
+
** [[File:JL0163328, PUCK MANIPULATOR END ADAPTER TEFLON 24 in long.pdf|right|middle|thumb]]
 +
 
 +
* S&A checks of the R30-3 gun in LERF Lab 3A clean room took place on Tuesday March 26 2024. See details [[https://wiki.jlab.org/ciswiki/index.php/Mar_20_2024]]
 +
** The R30-3 gun vacuum chamber was mounted by Neil Wilson and Bern Johnson on a sturdy 80/20 frame table with optical breadboard top.
 +
** S&A surveyed the gun chamber to find the chamber z axis.
 +
** Then S&A established a laser launch coincidental with the gun chamber z-axis
 +
** As <u>'''''preliminary testing'''''</u>, we inserted a mirror puck. The retro-reflection indicates the plane of the mirror puck is ~ 0.8 degree w.r.t. the chamber axis.
 +
** We will do more retro-reflection testing with a molybdenum puck and GaAs wafer once the Teflon puck manipulator arrives from the shop.
 +
 
 +
 
 +
 
 +
 
 +
[[File:R30-3 gun in LERF Lab 3A cleanroom 01.jpg|left|middle|thumb]]
 +
 
 +
[[File:S&A established laser launch along chamber z-axis 02.jpg|left|middle|thumb]]
 +
 
 +
[[File:Back end with laser beam through HVC.jpg|left|middle|thumb]]
 +
 
 +
[[File:Preliminary retro-reflection with mirror puck electrode still mounted to HVC.jpg|left|middle|thumb]]
 +
 
  
  

Latest revision as of 16:10, 26 March 2024

Updates

  • Fabrication
    • A new puck manipulator made out of Teflon and 24 inches long was designed and drawing submitted to the shop for fabrication. This manipulator will be used to insert pucks into the spherical electrode while still mounted to the gun vacuum chamber during S&A and laser retro-reflection checks in the LERF Lab 3A clean room.
    • File:JL0163328, PUCK MANIPULATOR END ADAPTER TEFLON 24 in long.pdf
  • S&A checks of the R30-3 gun in LERF Lab 3A clean room took place on Tuesday March 26 2024. See details [[1]]
    • The R30-3 gun vacuum chamber was mounted by Neil Wilson and Bern Johnson on a sturdy 80/20 frame table with optical breadboard top.
    • S&A surveyed the gun chamber to find the chamber z axis.
    • Then S&A established a laser launch coincidental with the gun chamber z-axis
    • As preliminary testing, we inserted a mirror puck. The retro-reflection indicates the plane of the mirror puck is ~ 0.8 degree w.r.t. the chamber axis.
    • We will do more retro-reflection testing with a molybdenum puck and GaAs wafer once the Teflon puck manipulator arrives from the shop.



R30-3 gun in LERF Lab 3A cleanroom 01.jpg
S&A established laser launch along chamber z-axis 02.jpg
Back end with laser beam through HVC.jpg
Preliminary retro-reflection with mirror puck electrode still mounted to HVC.jpg




Return to 200 kV Gun page