Difference between revisions of "MOLLER PQB Meeting September 18, 2024"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "In person in MCC Conference Room and with Zoom. https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam -- '''Agenda:''' * '''Injector Upgrade Progress:''' # Beam...")
 
 
(One intermediate revision by the same user not shown)
Line 12: Line 12:
  
 
# Beam tests showed excellent beam quality and good transmission at 100 μA: [https://logbooks.jlab.org/entry/4315868 ELOG #4315868]  
 
# Beam tests showed excellent beam quality and good transmission at 100 μA: [https://logbooks.jlab.org/entry/4315868 ELOG #4315868]  
# RTP new HV Driver full system is finally ready - to start bench testing today
+
# RTP new HV Driver full system is finally ready:
 
+
## Burn-in at 30 Hz started on Monday
 
+
## Installation Schedule: [[media:RTP_Installation_Schedule.pdf]]
* '''Beam Study Results:'''
 
 
 
# FFB/FF in Hall A: Ryan will prepare a plan
 

Latest revision as of 17:24, 17 September 2024

In person in MCC Conference Room and with Zoom.

https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam

--


Agenda:


  • Injector Upgrade Progress:
  1. Beam tests showed excellent beam quality and good transmission at 100 μA: ELOG #4315868
  2. RTP new HV Driver full system is finally ready:
    1. Burn-in at 30 Hz started on Monday
    2. Installation Schedule: media:RTP_Installation_Schedule.pdf