Difference between revisions of "MOLLER PQB Meeting September 25, 2024"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "In person in MCC Conference Room and with Zoom. https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam -- '''Agenda:''' * '''Injector Upgrade Progress:''' # Beam...")
 
 
(One intermediate revision by the same user not shown)
Line 11: Line 11:
 
* '''Injector Upgrade Progress:'''  
 
* '''Injector Upgrade Progress:'''  
  
# Beam tests showed excellent beam quality and good transmission at 100 μA: [https://logbooks.jlab.org/entry/4315868 ELOG #4315868]
 
 
# RTP new HV Driver full system is finally ready:
 
# RTP new HV Driver full system is finally ready:
## Burn-in at 30 Hz started on Monday
+
## Burn-in at 30 Hz started last week
 
## Installation Schedule: [[media:RTP_Installation_Schedule.pdf]]
 
## Installation Schedule: [[media:RTP_Installation_Schedule.pdf]]

Latest revision as of 18:09, 25 September 2024

In person in MCC Conference Room and with Zoom.

https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam

--


Agenda:


  • Injector Upgrade Progress:
  1. RTP new HV Driver full system is finally ready:
    1. Burn-in at 30 Hz started last week
    2. Installation Schedule: media:RTP_Installation_Schedule.pdf