Difference between revisions of "October 9, 2013"

From Ciswikidb
Jump to navigation Jump to search
 
(7 intermediate revisions by 2 users not shown)
Line 10: Line 10:
  
 
;Update on commissioning schedule.
 
;Update on commissioning schedule.
* November 9 - Start ACC-I
+
* ACC-I (Turn CEBAF back on 1-pass @ 2.2GeV)
* November 14 - (2 shifts) Mott commission 12am-4pm
+
** November 9 - Start (Mott under vacuum, controls, screens, DAQ ready)
* December 20 - End of ACC-I
+
** November 14 - (2 shifts) Mott commission 12am-4pm
 +
** December 20 - End (Next commissioning period ACC-II, early Feb)
  
 
;Tunnel work updates and plans (yes, includes target selection).
 
;Tunnel work updates and plans (yes, includes target selection).
* Bad IP replaced, both IP's on now
+
* Vacuum work
* As-founds of existing dump plate taken.  ME working, but slowly
+
** Bad IP replaced, both IP's on now
* EEL-118 Inventory [[Media:MeV_Mott_Foils.pdf]]
+
** As-founds of existing dump plate taken.  ME working, but slowly
* 500keV Mott Inventory
+
* Target Ladder
 +
** Survey completed (ladder positions vs. controller)
 +
** EEL-118 Inventory [[Media:MeV_Mott_Foils.pdf]]
 +
** 500keV Mott Inventory: 0.01; 0.03; 0.07; 0.1; 1.0 (mount type?)
  
 
;Marty tells Matt why Monte Carlo (Geant) is important.
 
;Marty tells Matt why Monte Carlo (Geant) is important.
 +
* Summary paper [[Media:GEANT4_Goals.pdf]]
  
 
;Tim tells us about Nobel gas polarimetry
 
;Tim tells us about Nobel gas polarimetry
 +
* [[Media:OEP_Schematic.pdf]]
 +
* [[Media:Gay_1983_JPB.pdf]]
 +
* [[Media:Furst_1993_PRA.pdf]]
 +
* [[Media:Gay_1996_PRA.pdf]]
 +
* [[Media:Pirbhai_RSI_2013.pdf]]

Latest revision as of 13:41, 9 October 2013

Mott Team Meeting

We will meet in TED 2561B on Wednesday October 9 at 3pm EST.

For those calling in we'll use the ReadyTalk audio conference system.

1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada)
2. Enter 7-digit access code 3441852, followed by “#”

Agenda

Update on commissioning schedule.
  • ACC-I (Turn CEBAF back on 1-pass @ 2.2GeV)
    • November 9 - Start (Mott under vacuum, controls, screens, DAQ ready)
    • November 14 - (2 shifts) Mott commission 12am-4pm
    • December 20 - End (Next commissioning period ACC-II, early Feb)
Tunnel work updates and plans (yes, includes target selection).
  • Vacuum work
    • Bad IP replaced, both IP's on now
    • As-founds of existing dump plate taken. ME working, but slowly
  • Target Ladder
    • Survey completed (ladder positions vs. controller)
    • EEL-118 Inventory Media:MeV_Mott_Foils.pdf
    • 500keV Mott Inventory: 0.01; 0.03; 0.07; 0.1; 1.0 (mount type?)
Marty tells Matt why Monte Carlo (Geant) is important.
Tim tells us about Nobel gas polarimetry