Difference between revisions of "GTS meeting 2 07 17"
Jump to navigation
Jump to search
(Created page with "* Soaked gun at 300 kV and magnet at 400 A for about 20 hours - vacuum was about 7 nA.") |
|||
Line 1: | Line 1: | ||
* Soaked gun at 300 kV and magnet at 400 A for about 20 hours - vacuum was about 7 nA. | * Soaked gun at 300 kV and magnet at 400 A for about 20 hours - vacuum was about 7 nA. | ||
+ | |||
+ | * Survey and Alignment finished the beamline (slits, solenoids) this afternoon. Next, will put beamline under vacuum and prep for a bake). |
Revision as of 08:46, 7 February 2017
- Soaked gun at 300 kV and magnet at 400 A for about 20 hours - vacuum was about 7 nA.
- Survey and Alignment finished the beamline (slits, solenoids) this afternoon. Next, will put beamline under vacuum and prep for a bake).