- Emittance Measurements with large laser size (rms=0.423mm) - Yan
- New plan:
- Finish emittance measurements, including a larger laser size (x4) – August 21-25
- Attempt 5 mA (non-magnetized, then magnetized) – August 28-31
- Shutdown – September 5:
- Install new YAG screen at viewer 3
- Fix existing harp and install 20 µm tungsten wire
- Add a new CEBAF-style harp with 10 µm tungsten wire (i.e, GTS will have two harps)
- Replace leaky vent valve
- Replace bad ion pump