* List of software and controls changes: | * List of software and controls changes: | ||
− | # Re-program SCAM to allow for 1 Hz and 50 ns pulses | + | # Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses |
# Add 5th solenoid to magnet screen | # Add 5th solenoid to magnet screen |
Revision as of 11:31, 4 January 2019
- List of beamline hardware modifications:
- Replace YAG screen on Viewer 1
- Replace Slit on Viewer 2 with holes assembly
- Replace two ion collectors with new ones
- Replace Harp fork (Tony)
- Remove modified DP can
- Remove Faraday Cup
- Remove bellow upstream of dump
- Install TE011 Cavity
- Install Deflecting Cavity
- Install new 5th solenoid
- Move DP can 1 to end of beamline
- All bellows at least 2.5 inch diameter
- List of software and controls changes:
- Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses
- Add 5th solenoid to magnet screen