Line 12: | Line 12: | ||
# Move DP can 1 to end of beamline | # Move DP can 1 to end of beamline | ||
# All bellows at least 2.5 inch diameter | # All bellows at least 2.5 inch diameter | ||
+ | # Both gate valves are 2.5 inch-bore and will remain on beamline | ||
+ | |||
+ | |||
+ | * Remove gain-switched laser from GTS to LERF | ||
Revision as of 12:19, 7 January 2019
- List of beamline hardware modifications:
- Replace YAG screen on Viewer 1
- Replace Slit on Viewer 2 with holes assembly
- Replace two ion collectors with new ones
- Replace Harp fork (Tony)
- Remove modified DP can
- Remove Faraday Cup
- Remove bellow upstream of dump
- Install TE011 Cavity
- Install Deflecting Cavity
- Install new 5th solenoid
- Move DP can 1 to end of beamline
- All bellows at least 2.5 inch diameter
- Both gate valves are 2.5 inch-bore and will remain on beamline
- Remove gain-switched laser from GTS to LERF
- List of software and controls changes:
- Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses
- Add 5th solenoid to magnet screen