(Created page with "The final stretch: ;I&C * ion pumps along the MeV beamline, drop cables, junction boxes, epics screens for 14 more pumps * valves: per the song sheet, get them to work, air p...") |
|||
Line 6: | Line 6: | ||
* viewers, pneumatic actuators, video | * viewers, pneumatic actuators, video | ||
* BPMs, we need them now | * BPMs, we need them now | ||
+ | * the big BPMs on HDIce line, are they any good? | ||
* current monitoring at dumps, cups and apertures, water plumbing | * current monitoring at dumps, cups and apertures, water plumbing | ||
* harps | * harps | ||
* yao cavity, at least one needs to be installed, with electronics | * yao cavity, at least one needs to be installed, with electronics | ||
− | + | ||
; Magnets | ; Magnets | ||
+ | * install third rack | ||
+ | * cable up at least the waist height magnets | ||
+ | * inventory haimsons, purchase more? different sizes? | ||
+ | * check out the MAT correctors, will they work? 1.5" pipe? | ||
+ | * Grab the steering magnets from LERF for HDIce line, 3" pipe? | ||
+ | |||
+ | ;PSS BCM | ||
+ | * tables and documentation | ||
+ | * test with 200 keV beam | ||
+ | * interlock the chicane dipole? |
Latest revision as of 09:25, 11 February 2019
The final stretch:
- I&C
- ion pumps along the MeV beamline, drop cables, junction boxes, epics screens for 14 more pumps
- valves: per the song sheet, get them to work, air plumbing
- viewers, pneumatic actuators, video
- BPMs, we need them now
- the big BPMs on HDIce line, are they any good?
- current monitoring at dumps, cups and apertures, water plumbing
- harps
- yao cavity, at least one needs to be installed, with electronics
- Magnets
- install third rack
- cable up at least the waist height magnets
- inventory haimsons, purchase more? different sizes?
- check out the MAT correctors, will they work? 1.5" pipe?
- Grab the steering magnets from LERF for HDIce line, 3" pipe?
- PSS BCM
- tables and documentation
- test with 200 keV beam
- interlock the chicane dipole?