Difference between revisions of "March 12, 2020 - ME/INJ/CIS"

From Ciswikidb
Jump to navigation Jump to search
Line 30: Line 30:
 
* DipoleEmerson backedb=>  out, Milhous quoting round/square, Lakshimi working on Jay's AT design
 
* DipoleEmerson backedb=>  out, Milhous quoting round/square, Lakshimi working on Jay's AT design
 
* Soleonids => Joe M. what is status?
 
* Soleonids => Joe M. what is status?
  First article complete ~April 20th:  After you receive, can you mount to the fixture plate, do your QC checks, field map it?....
+
  First article complete ~April 20th:  After you receive, can you mount to the fixture plate, do your QC checks, field map it?....then ASAP, a 2.5" spool goes through, flanges get welded on, cleaned, then Phil needs 100 hours to NEG coat the spool, then 4 weeks later on May 18th it goes into CEBAF,
....then ASAP, a 2.5" spool goes through, flanges get welded on, cleaned, then Phil needs 100 hours to NEG coat the spool,
 
....then 4 weeks later on May 18th it goes into CEBAF,
 
  
 
* Quads => Have 3 QW, Mike testing 2 spare QW quads (capture on welded cross)
 
* Quads => Have 3 QW, Mike testing 2 spare QW quads (capture on welded cross)

Revision as of 07:42, 11 March 2020

Mechanical
  • What is the bellows type count, how may 3" and 3.5"?
  • Chris, do you have all as-founds you need?
  • Use C channel everywhere and move pedestals ok?
Anthony says yes, do it
  • Carlos, send Shaun Wien feedthrough p/n
  • SS or Al brackets?
Use Al, now all 7-3/4" girder to beam line, girder holes whereever imagine support
  • NEG chambers
Detail Y- 10" flange, NEG's here
Flip DP for IP beam left, modify for new NEG's?
  • Laser vacuum window?
Caryn started evaluating
Show layout of laser room, outrigger box, laser table
Shukui, tight, how to fit optics, inside laser room?
  • 2I spools?
ME will order, need in time to a) weld capture solenoid, b) NEG coat
  • New BPM's
Design done, feedthroughs ordered, waiting on req to MDC
  • Solenoid fixtures?
  • What is p/n for the 25S IP?
  • Viewer top-hats
What is position when retracted for Y/Laser vs. crosses?
How many spares, do we need more or different?
  • Layout
Dennis can convert Elegant to S&A coordinates
Joe, map all the elements in an Excel file, punchlist CED & modifications
Magnets
  • DipoleEmerson backedb=> out, Milhous quoting round/square, Lakshimi working on Jay's AT design
  • Soleonids => Joe M. what is status?
First article complete ~April 20th:   After you receive, can you mount to the fixture plate, do your QC checks, field map it?....then ASAP, a 2.5" spool goes through, flanges get welded on, cleaned, then Phil needs 100 hours to NEG coat the spool, then 4 weeks later on May 18th it goes into CEBAF,
  • Quads => Have 3 QW, Mike testing 2 spare QW quads (capture on welded cross)
  • Correctors => Joe G tally
  • Wien => Technicoil getting ready to wind
  • PSS Kicker => Met w/ Jerry, Lakshimi working on upgraded kicker to move 200 keV beam 1cm @ 30 cm w < 200 mA (March 9 layout)
High Voltage
  • status of SS shed? (flange degased, ceramic welded, electrode cut, electrode polish, electrode mounted, fiducialize)
  • status of Wien high voltage?
Orders
  • Bellows - waiting on final count
  • Right angle valves - we have 5 or 6, should be ok?
  • Gun 10" flange - signed req for (2)
  • Order 10 kV feedthroughs
  • BPM feedthroughs - ordered
  • BPM cans - waiting on req to MDC
Controls
  • Chris, what cameras will you use, will they fit?
  • Mark/Dave, do you have a plan for 2500W solid state chopper amps?
  • Mark/Dave, do you have a plan for Brock prebuncher cavity/amp?
  • Omar, do you have BPM channel?
Yes!
  • Remove hall probe
  • Wien HV controls
status of prototype test at UITF?
layout in ISB racks?
drops/penetrations?
controls screens?
  • Wien PS
layout in ISB racks?
drops?
Modelers
  • Is the March 9th layout ok?
  • Is the harp location OK for solenoid scans?
  • Should a viewer remain at the harp location, should this be a YAG?
  • Where else should YAG's go?
  • Can a YAG go at the laser screen, I don't think so?
  • Is the beam envelope OK for ways we run spin rotators?
What are the currents and/or B's for the solenoids and quads?
  • What are the power levels for existing or Brock prebuncher cavities, for 130 or 200 keV locations?
  • Is distance from MFG1I04A to upstream corrector far enough? or move MFG1I04A downstream, how far?
Jay is running cases
  • Is the corrector/bpm downstream A1 useful?
Commissioning
  • Plan for May gun work?
  • BPM job
Receive can/feedthroughs
Clean
Degas
Coat
Check feedthroughs, assemble feedthroughs
Leak check cans
electrical measurement
serialize
report K's and center