Line 45: Line 45:
 
* Sample hold cables install, InjSB (Francis)  
 
* Sample hold cables install, InjSB (Francis)  
 
* Remaining PSS Interface chassis removal (SSG)
 
* Remaining PSS Interface chassis removal (SSG)
 +
* Harp upgrade to PC104 (Dela Cruz)
 
* Moser transfers CCOC phone @1430, to reach moving forward x5089  
 
* Moser transfers CCOC phone @1430, to reach moving forward x5089  
  
Line 50: Line 51:
 
; Thursday 10/1 Tasks (updated 0830 10/1)
 
; Thursday 10/1 Tasks (updated 0830 10/1)
 
* Picoammeter Removal, InjSB (Francis) 5a
 
* Picoammeter Removal, InjSB (Francis) 5a
* Sample hold cables install, InjSB (Francis)
+
* Sample hold cables install, IN02B24 (Francis)
* BPM Work in InjSB (Francis)
+
* BPM Work in IN02B2* (Francis)
 
* Chopper amplifier upgrade (Farrish)
 
* Chopper amplifier upgrade (Farrish)
* Viewer hardware disconnects (Norris) 6a
+
* Harp upgrade to PC104 (Dela Cruz)
 +
* Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
 
* Disconnecting water and air lines from apertures and cups (Adderley) 8a
 
* Disconnecting water and air lines from apertures and cups (Adderley) 8a
 
* Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
 
* Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
Line 59: Line 61:
  
 
; Friday 10/2 Tasks
 
; Friday 10/2 Tasks
*  
+
* BPM Work in IN02B2* (Francis)
 +
* Chopper amplifier upgrade (Farrish)
 +
* Harp upgrade to PC104 (Dela Cruz)
 +
* Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
 +
 
 +
 
  
 
; Tue 9/29 – Fri 10/1 (updated 0900 9/30)
 
; Tue 9/29 – Fri 10/1 (updated 0900 9/30)
Line 68: Line 75:
 
! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2  
 
! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2  
 
|-
 
|-
| 4a - 8a ||  || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher || I&C; 6a: Norris: Viewer Disconnects || I&C   
+
| 4a - 8a ||  || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher || I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps || I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps  
 
|-
 
|-
 
| 8a - 10a || CIS + SSG || RadCon: rad probes || SSG: Kicker magnet removal; CIS: Tiny magnet removals || CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru ||
 
| 8a - 10a || CIS + SSG || RadCon: rad probes || SSG: Kicker magnet removal; CIS: Tiny magnet removals || CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru ||

Revision as of 07:59, 1 October 2020

Week 1 (Sep 21 - Sep 27)

Week 2 (Sep 28 - Oct 4)

Fri 9/25 - Mon 9/28
  • CIS Gun Jobs
Wien electrode testing – 9am!!!
Gun HVPS lockout - DONE
Gun HV cable disconnect – DONE
Remove PIG – Coordinate w/ Neil for convenient time
Shukui - Laser outrigger table as-founds, remove components
Scott - Remove yellow box
Scott - Disconnect Decarad


Monday 9/28 Tasks (updated 0915 9/28)
  • Power down Wein system (Scott/Joe)
  • Power down and remove DecaRad system (Scott)
  • Return gun valve config to "normal" (Marcy)
  • Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
  • PSS Kickers and associated chassis removal (SSG)
  • Laser table disassembly (Shukui/Scott)


Tuesday 9/29 Tasks (updated 0930 9/29)
  • (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
  • (Done) Disconnect aperture and cup signal cables (Pete) 5a
  • Disconnect rad probes (Melvin) 8a
  • Tunnel magnet disconnects (Diggs, Delk) 10a
  • (Done) Removal of old chopper amps from rack (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • ODH Head Replacements (SSG)
  • Document existing Wein cabling and power off PS (Scott)


Wednesday 9/30 Tasks (updated 0900 9/30)
  • RF Prebuncher disconnects (Farrish) 6a
  • Vacuum Component Labeling (Greenfield, Gonzales) 430a
  • Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a
  • Tiny magnet removals (Scott, Grames) 9a
  • PSS Kicker Magnet removal (SSG) 9a
  • Sample hold cables install, InjSB (Francis)
  • Remaining PSS Interface chassis removal (SSG)
  • Harp upgrade to PC104 (Dela Cruz)
  • Moser transfers CCOC phone @1430, to reach moving forward x5089


Thursday 10/1 Tasks (updated 0830 10/1)
  • Picoammeter Removal, InjSB (Francis) 5a
  • Sample hold cables install, IN02B24 (Francis)
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
  • Disconnecting water and air lines from apertures and cups (Adderley) 8a
  • Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a


Friday 10/2 Tasks
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a


Tue 9/29 – Fri 10/1 (updated 0900 9/30)
Tunnel Work
Time Mon 9/28 Tue 9/29 Wed 9/30 Thu 10/1 F 10/2
4a - 8a I&C; 5a: Francis: BPMs, Cups, Apertures I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps
8a - 10a CIS + SSG RadCon: rad probes SSG: Kicker magnet removal; CIS: Tiny magnet removals CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru
10a - 12p CIS + SSG DC Power DC Power: Wire wrap-ups, junction box investigation
12p - 2p CIS + SSG DC Power DC Power: Wire wrap-ups, junction box investigation DC Power
2p - 4p CIS + SSG DC Power 3p: Moser: Safety Warden checks
4p - ??
Other Work Occurring When Convenient
  • Remove suitcase, Tunnel (CIS)
  • Harp upgrade, InjSB (I&C)
  • ODH Head Replacement, InjSB and Tunnel (SSG)
  • PSS Chassis Removals, InjSB (SSG)

Week 3 (Oct 5 - Oct 11)

  • Vacuum disconnects

Week 4 (Oct 12 - Oct 18)

Week 5 (Oct 19 - Oct 25)

  • Injector is now in restricted access all the time
  • LOTO and system disconnects

Week X