Line 66: Line 66:
  
 
; [[Tue 9/29 – Fri 10/1 Table]]
 
; [[Tue 9/29 – Fri 10/1 Table]]
; <u>'''Tunnel Work'''</u>
 
 
{| class="wikitable"
 
|-
 
! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2
 
|-
 
| 4a - 8a ||  || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher || I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps || I&C: Norris: Viewer disconnects
 
|-
 
| 8a - 10a || CIS + SSG || RadCon: rad probes || SSG: Kicker magnet removal; CIS: Tiny magnet removals || CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru || S&A: Gun
 
|-
 
| 10a - 12p || CIS + SSG || DC Power || DC Power: Wire wrap-ups, junction box investigation  ||  || S&A: Gun; SSG: Kicker cable tie-up
 
|-
 
| 12p - 2p || CIS + SSG || DC Power || DC Power: Wire wrap-ups, junction box investigation || DC Power || S&A: Gun
 
|-
 
| 2p - 4p || CIS + SSG || DC Power || 3p: Moser: Safety Warden checks  ||  || S&A: Gun
 
|-
 
| 4p - ?? ||  ||  ||  ||  ||
 
|}
 
 
; <u>'''Other Work Occurring When Convenient'''</u>
 
* Remove suitcase, Tunnel (CIS)
 
* Harp upgrade, InjSB (I&C)
 
* ODH Head Replacement, InjSB and Tunnel (SSG)
 
* PSS Chassis Removals, InjSB (SSG)
 
  
 
=== Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network ===
 
=== Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network ===

Revision as of 07:05, 5 October 2020

Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups

Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects

Fri 9/25 - Mon 9/28
  • CIS Gun Jobs
Wien electrode testing – 9am!!!
Gun HVPS lockout - DONE
Gun HV cable disconnect – DONE
Remove PIG – Coordinate w/ Neil for convenient time
Shukui - Laser outrigger table as-founds, remove components
Scott - Remove yellow box
Scott - Disconnect Decarad
Monday 9/28 Tasks (updated 0915 9/28)
  • Power down Wein system (Scott/Joe)
  • Power down and remove DecaRad system (Scott)
  • Return gun valve config to "normal" (Marcy)
  • Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
  • PSS Kickers and associated chassis removal (SSG)
  • Laser table disassembly (Shukui/Scott)
Tuesday 9/29 Tasks (updated 0930 9/29)
  • (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
  • (Done) Disconnect aperture and cup signal cables (Pete) 5a
  • Disconnect rad probes (Melvin) 8a
  • Tunnel magnet disconnects (Diggs, Delk) 10a
  • (Done) Removal of old chopper amps from rack (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • ODH Head Replacements (SSG)
  • Document existing Wein cabling and power off PS (Scott)
Wednesday 9/30 Tasks (updated 0900 9/30)
  • RF Prebuncher disconnects (Farrish) 6a
  • Vacuum Component Labeling (Greenfield, Gonzales) 430a
  • Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a
  • Tiny magnet removals (Scott, Grames) 9a
  • PSS Kicker Magnet removal (SSG) 9a
  • Sample hold cables install, InjSB (Francis)
  • Remaining PSS Interface chassis removal (SSG)
  • Harp upgrade to PC104 (Dela Cruz)
  • Moser transfers CCOC phone @1430, to reach moving forward x5089
Thursday 10/1 Tasks (updated 0830 10/1)
  • Picoammeter Removal, InjSB (Francis) 5a
  • Sample hold cables install, IN02B24 (Francis)
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
  • Disconnecting water and air lines from apertures and cups (Adderley) 8a
  • Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
Friday 10/2 Tasks (updated 0900 10/2)
  • Viewer disconnects (Norris) 6a
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • PSS Kicker Cables tie-up (SSG)
  • Survey and Alignment control measure around gun (S&A)
  • Load suitcase with "bad" pucks (CIS)
  • Pump-down vacuum in front of tee for next week (CIS)
Tue 9/29 – Fri 10/1 Table

Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network

  • Oct 5-6 CIS vacuum tests, disconnects, and pre-removal blank offs
  • Oct 7-8 INSTALL remove laser table, girders to Test Lab, oil tank to Brett Lewis
  • Oct 8-12 S&A network

Week 4 (Oct 12 - Oct 18)