Difference between revisions of "Phase 1 Commissioning Schedule"
Jump to navigation
Jump to search
Line 457: | Line 457: | ||
|- style="vertical-align:middle; background-color:#CFE0E8;" | |- style="vertical-align:middle; background-color:#CFE0E8;" | ||
| style="font-weight:bold; background-color:#B7D7E8;" | Beam Commissioning <br /> Plan (ATLis) | | style="font-weight:bold; background-color:#B7D7E8;" | Beam Commissioning <br /> Plan (ATLis) | ||
− | | PSS Kicker Certification ( | + | | PSS Kicker Certification ([http://devweb.acc.jlab.org/CSUEApps/atlis/task/22061 22061]) |
| CW to FC1 Setup ([http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22182 22182])<br />''(float PSS Kicker)'' | | CW to FC1 Setup ([http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22182 22182])<br />''(float PSS Kicker)'' | ||
| CW to FC1 Setup ([http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22182 22182]) | | CW to FC1 Setup ([http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22182 22182]) |
Revision as of 17:42, 9 June 2021
Week 0, May 17th-23rd
DAY Shift | Monday 5/17 |
Tuesday 5/18 |
Wednesday 5/19 |
Thursday 5/20 |
Friday 5/21 |
Sat 5/22 |
Sun 5/23 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
Hot Checkout No Beam |
AM: Hot Checkout PM: PSS Certs |
830-9a: Cryo tour (3ppl) 0I02 harp repair PM: PSS Certs |
0I02 harp repair float: PSS certs |
AM: 0I02 reconnects PM: PSS Certs Begin Beam Commissioning! |
Beam Off | Beam Off | First beam of 2021 |
Shift Leader | Hot Checkout No Beam |
Suleiman | Grames | Poelker | Suleiman | Beam Off | Beam Off | |
Scientist #2 | Hot Checkout No Beam |
Bruker | Bruker | Hernandez-Garcia | Mamun | Beam Off | Beam Off | |
Ops Inj Support | Hot Checkout No Beam |
PSS TD: Forman | PSS TD: Moser | PSS TD: Forman Moser |
Beam Off | Beam Off | ||
SSO / AM Sweeper | Hot Checkout No Beam |
SSG / Forman / Moser | Beam Off | Beam Off | ||||
Other MCC Work, Group, +Persons in MCC | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | |||
SWING Shift | 5/17 | 5/18 | 5/19 | 5/20 | 5/21 | 5/22 | 5/23 | |
Beam Commissioning Plan / ATLis | Hot Checkout No Beam |
0I02 harp repair | 0I02 harp repair | 0I02 harp repair | Trickle Beam to first Viewer 60Hz Noise Snooping / Cable Shielding |
Beam Off | Beam Off | |
Shift Leader | Hot Checkout No Beam |
Beam Off | Beam Off | |||||
Scientist #2 | Hot Checkout No Beam |
Beam Off | Beam Off | |||||
Ops Inj Support | Hot Checkout No Beam |
Law | Beam Off | Beam Off | ||||
SSO | Hot Checkout No Beam |
Anthony | Beam Off | Beam Off | ||||
Other MCC Work, Group, +Persons in MCC | NL Lock-Up/Commissioning, SSG, +2 | NL Lock-Up/Commissioning, SSG, +2 | NL Lock-Up/Commissioning, SSG, +2 | NL Lock-Up/Commissioning, SSG, +2 | NL Lock-Up/Commissioning, SSG, +2 | |||
CCOC / PD | Merz / Aiken | Merz / Aiken | Merz / Frierson | Merz / Frierson | Merz / Frierson | Merz / Frierson | Merz / Frierson |
Week 1, May 24th-30th
CEBAF PSS Certifications Week 1/3
italics = less certain
DAY Shift | Monday 5/24 |
Tuesday 5/25 |
Wednesday 5/26 |
Thursday 5/27 |
Friday 5/28 |
Sat 5/29 |
Sun 5/30 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
Initial Beam Threading Gun->PCup, 130keV, TM (22180) PSS Kicker Cert (22061) |
Initial Beam Threading Gun->PCup, 130keV, CW (22180) PSS Kicker Cert (22061) |
Element Centering Gun->PCup, 130keV, CW (22180) Early Injector Orbit Data (22181) PSS Kicker Cert (22061) |
AM: Polarity Checks AM: Solenoid, Quad Centering Gun->PCup, 130keV, CW (22180) Early Injector Orbit Data (22181) PM: Prebuncher RF Elements Setup, 130keV, CW (22190) |
Prebuncher setup -- 22190 RF Elements Setup /or\ 22184 Spot Move Knobs 2p: 22061 PSS Kicker Cert |
22084 AIPINJ: 130/200 keV E/B calibrations for V-Wien and H-Wien 22080 AIPINJ: 130/200 keV HVPS vs. PCUP current monitor calibration 22184 Efficacy of Knobs chosen for spot move correction 22441 Commissioning V-Wien, H-Wien, Spin Flipper Solenoids and Autosteer Knobs |
22084 AIPINJ: 130/200 keV E/B calibrations for V-Wien and H-Wien 22080 AIPINJ: 130/200 keV HVPS vs. PCUP current monitor calibration 22184 Efficacy of Knobs chosen for spot move correction 22441 Commissioning V-Wien, H-Wien, Spin Flipper Solenoids and Autosteer Knobs |
Weekday lock-ups at ~0645. Weekdays PSS Certs @330p, no Inj commissioning |
Shift Leader | <8a: Grames 8a-4p: Kazimi |
<8a: Grames 8a-4p: Wang |
<8a: Grames 8a-4p: Hofler |
<8a: Grames 8a-noon: Wang noon-4p: Kazimi |
<8a: Moser 8a-4p: Kazimi |
8a-4p Suleiman |
8a-4p Suleiman | |
Scientist #2 | 8a-4p: Wang | 8a-4p: Hofler | 8a-4p: Wang | 8a-4p: Hofler | 8a-4p: {Wang, Hofler} | Bruker Mamun |
Bruker Mamun | |
Ops Inj Support | Law | Law | Law | Law | Law | Law | ||
SSO / AM Sweeper | Garcia / Law | Garcia / Law | Garcia / Law | Garcia / Law | Law / Moser | Merz / Carlino | Deir / Carlino | |
Other MCC Work, Group, +Persons in MCC | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | |||
SWING Shift | 5/24 | 5/25 | 5/26 | 5/27 | 5/28 | 5/29 | 5/30 | |
Beam Commissioning Plan / ATLis | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | No Beam | No Beam | |
Shift Leader | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | |||
Scientist #2 | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | |||
Ops Inj Support | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | |||
SSO | PSS TD | Aiken | Aiken | Aiken | Aiken | Aiken | |||
Other MCC Work, Group, +Persons in MCC | SSG | SSG | SSG | SSG | SSG | |||
CCOC / PD | Merz / Frierson | Merz / Frierson | Carlino / Frierson | Carlino / Frierson | Carlino / Frierson | Carlino / Frierson | Carlino / Frierson |
Week 2, May 31st🇺🇸 - June 6th
CEBAF PSS Certifications Week 2/3
DAY Shift | Monday 5/31 Memorial Day 🇺🇸 |
Tuesday 6/1 |
Wednesday 6/2 |
Thursday 6/3 |
Friday 6/4 |
Sat 6/5 |
Sun 6/6 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
No Beam | AM: 22182 Set up beam from PCup to FC1 at 130keV, TM 22084 130keV Wien E/B cals PM: Prebuncher - 22190 RF Elements Setup 2p: 22061 PSS Kicker @130keV |
7a-9a: 22084 130keV Wien E/B cals 9a-noon: 22441 Wien Autosteer Knobs noon-2p: 22190 Prebuncher Characterization 2p-330p: 22061 PSS Kicker |
AM: 22441 Wien Autosteer Knobs PM: 22181 Early Injector FOPT Data |
0I02 Harp Install No Beam |
No Beam | No Beam | Weekday lock-ups at ~0645. Weekdays PSS Certs @330p, no Inj commissioning |
Shift Leader | No Beam | <8a: CIS 8a-noon: Wang noon-4p: Kazimi |
7a-9a: Suleiman 9a-noon: Law noon-4p: Kazimi |
<8a: Grames 8a-noon: Law noon-4p: Hofler |
No Beam | No Beam | No Beam | |
Scientist #2 | No Beam | 8a-noon: Law noon-4p: Hofler |
7a-9a: Bruker 9a-noon: Wang noon-4p: Hofler |
8a-noon: Wang noon-4p: Kazimi |
No Beam | No Beam | No Beam | |
Ops Inj Support | No Beam | Forman | Forman | Forman | No Beam | No Beam | No Beam | |
SSO / AM Sweeper | No Beam | Gauthier / Forman | Gauthier / Forman | Gauthier / Forman | No Beam | No Beam | No Beam | |
Other MCC Work, Group, +Persons in MCC | 1230-230p: JLab Video Tour Filming w/Satogata (Satogata, Robbins, Camera Guy) |
|||||||
SWING Shift | 5/31 🇺🇸 | 6/1 | 6/2 | 6/3 | 6/4 | 6/5 | 6/6 | |
Beam Commissioning Plan / ATLis | PSS Certification | PSS Certification | PSS Certification | Disconnects for 0I02 Harp PSS Certification |
PSS Certification | No Beam | No Beam | |
Shift Leader | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | No Beam | No Beam | |
Scientist #2 | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | No Beam | No Beam | |
Ops Inj Support | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | No Beam | No Beam | |
SSO | PSS TD | Aiken | Aiken | Aiken | Aiken | Aiken | No Beam | No Beam | |
Other MCC Work, Group, +Persons in MCC | SSG | SSG | SSG | SSG | SSG | |||
CCOC / PD | Carlino / Frierson | Carlino / Frierson | Carlino / Merz | Carlino / Merz | Carlino / Merz | Carlino / Merz | Carlino / Merz |
Week 3, June 7th-13th
- 6/7 - 6/11: CEBAF PSS Certifications Week 3/3
- Days and Swings running 6/11,12,13. No Owls.
DAY Shift | Thursday 6/10 |
Friday 6/11 |
Sat 6/12 |
Sun 6/13 |
Notes/Goals |
---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
PSS Kicker Certification (22061) | CW to FC1 Setup (22182) (float PSS Kicker) |
CW to FC1 Setup (22182) | CW to FC1 Setup (22182) | High current CW setup to FC1, Choppers Off. Prebuncher, Buncher, characterization |
Shift Leader | Wang | Wang | Wang | Wang | |
Scientist #2 | Bruker | Law | |||
Ops Inj Support | CC: Forman | CC: Forman | CC: Forman | CC: Forman | |
SSO / AM Sweeper | Garcia / SSG | Garcia / Forman | Gauthier / Forman | Gauthier / Forman | |
Other MCC Work, Group, +Persons in MCC | SSG | SSG | |||
SWING Shift | 6/10 | 6/11 | 6/12 | 6/13 | |
Beam Commissioning Plan (ATLis) |
PSS Functional Tests | Prebuncher, Buncher Characterization (22190) (float PSS Functional Tests) |
Prebuncher, Buncher Characterization (22190) | Prebuncher, Buncher Characterization (22190) | |
Shift Leader | No Beam | Kazimi | Kazimi | Kazimi | |
Scientist #2 | No Beam | Hofler | Hofler | Hofler | |
Ops Inj Support | No Beam | CC: McCaughan | CC: McCaughan | CC: McCaughan | |
SSO | PSS TD: Aiken | Anthony | Mock | Mock | |
Other MCC Work, Group, +Persons in MCC | SSG | SSG | |||
CCOC / PD | Moser / Carlino | Moser / Carlino | Moser / Carlino | Moser / Carlino |
Week 4, June 14th-20th
- PSS Certs complete
- 6/14 -> 0L02 at 2K (est from 6/7 M1330)
DAY Shift | Monday 6/14 |
Tuesday 6/15 |
Wednesday 6/16 |
Thursday 6/17 |
Friday 6/18 |
Sat 6/19 |
Sun 6/20 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | TBD | TBD | TBD |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Ops Inj Support | TBD: {Forman, Law} | TBD: {Forman, Law} | TBD: {Forman, Law} | TBD: {Forman, Law} | TBD: {Forman, Law} | |||
SSO / AM Sweeper | TBD | TBD | TBD | TBD | TBD | |||
Other MCC Work, Group, +Persons in MCC | ||||||||
SWING Shift | 6/14 | 6/15 | 6/16 | 6/17 | 6/18 | 6/19 | 6/20 | |
Beam Commissioning Plan / ATLis | TBD | TBD | TBD | TBD | TBD | TBD | TBD | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Ops Inj Support | TBD: {Forman, Law} | TBD: {Forman, Law} | TBD: {Forman, Law} | TBD: {Moser, Forman, Law} | TBD: {Moser, Forman, Law} | |||
SSO | TBD | TBD | TBD | TBD | TBD | |||
Other MCC Work, Group, +Persons in MCC | ||||||||
CCOC / PD | Moser / Merz | Moser / Merz | Moser / Carlino | Moser / Carlino | Moser / Carlino | Moser / Carlino | Moser / Carlino |
Week 5, June 21st-27th
FC#2 Running Possible. 24/7 Running Possible.
DAY Shift | Monday 6/21 |
Tuesday 6/22 |
Wednesday 6/23 |
Thursday 6/24 |
Friday 6/25 |
Sat 6/26 |
Sun 6/27 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | TBD | TBD | TBD |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Ops Inj Support | TBD: {Forman, Law} | TBD: {Forman, Law} | TBD: {Forman, Law} | TBD: {Moser, Forman, Law} | TBD: {Moser, Forman, Law} | |||
SSO / AM Sweeper | TBD | TBD | TBD | TBD | TBD | |||
Other MCC Work, Group, +Persons in MCC | ||||||||
SWING Shift | 6/21 | 6/22 | 6/23 | 6/24 | 6/25 | 6/26 | 6/27 | |
Beam Commissioning Plan / ATLis | TBD | TBD | TBD | TBD | TBD | TBD | TBD | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Ops Inj Support | TBD: {Forman, Law} | TBD: {Forman, Law} | TBD: {Forman, Law} | TBD: {Moser, Forman, Law} | TBD: {Moser, Forman, Law} | |||
SSO | TBD | TBD | TBD | TBD | TBD | |||
Other MCC Work, Group, +Persons in MCC | ||||||||
CCOC / PD | Moser / Carlino | Moser / Carlino | TBD / Carlino | TBD / Carlino | TBD / Carlino | TBD / Carlino | TBD / Carlino |
Week 6, June 28th-July 4th
FC#2 running possible. 24/7 running possible.
DAY Shift | Monday 6/28 |
Tuesday 6/29 |
Wednesday 6/30 |
Thursday 7/1 |
Friday 7/2 |
Sat 7/3 |
Sun 7/4 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | TBD | TBD | TBD |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Ops Inj Support | TBD: {Moser, Forman, Law} | TBD: {Moser, Forman, Law} | TBD: {Moser, Forman, Law} | TBD: {Moser, Forman, Law} | TBD: {Moser, Forman, Law} | |||
SSO / AM Sweeper | TBD | TBD | TBD | TBD | TBD | |||
Other MCC Work, Group, +Persons in MCC | ||||||||
SWING Shift | 6/28 | 6/29 | 6/30 | 7/1 | 7/2 | 7/3 | 7/4 | |
Beam Commissioning Plan / ATLis | TBD | TBD | TBD | TBD | TBD | TBD | TBD | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Ops Inj Support | TBD: {Moser, Forman, Law} | TBD: {Moser, Forman, Law} | TBD: {Moser, Forman, Law} | TBD: {Moser, Forman, Law} | TBD: {Moser, Forman, Law} | |||
SSO | TBD | TBD | TBD | TBD | TBD | |||
Other MCC Work, Group, +Persons in MCC | ||||||||
CCOC / PD | TBD / Carlino | TBD / Carlino | TBD / TBD | TBD / TBD | TBD / TBD | TBD / TBD | TBD / TBD |
Week 7, July 5th-July 11th
Week 8, July 12th-July 16th