− | + | 'Gun Test Stand Mode:' | |
+ | #HV commissioning and processing of the gun | ||
+ | #Determination of Operating Voltage for a low FE or FE free regime | ||
+ | |||
+ | keV mode: (VBVM101 locked in) | ||
+ | # Insert Faraday cups 1 & 2. | ||
+ | # Systematically insert all of the Viewers in the keV region. Verify they all insert, retract, and are focused and the the lights work. File PR if problem arises. | ||
+ | # Open and close each valve and makes sure it hits its limit switch on both sides. Leave all valves opened when completed. File PR if problem arises. | ||
+ | # Turn on gun to operating voltage. | ||
+ | # Insert ITVK201 | ||
+ | # MBHK101H & V, MBHK102H & V, and MFHK101 were all disconnected this down | ||
+ | #* Verify the MBHK101H & V correctors kick in the appropriate dimension and with the appropriate sign. File PR if problem arises. | ||
+ | #* Verify the MBHK102H & V correctors kick in the appropriate dimension and with the appropriate sign. File PR if problem arises. | ||
+ | #* Use MFHK101 to determine the magnetic field which approximately focus beam on the viewer; use correctors as necessary to keep beam on the viewer. | ||
+ | #* Using the ditherer, dither the solenoid by 10% and use the K101 corrector pair to center beam in the solenoid (i.e. where there is no horizontal/vertical displacement as the field changes) | ||
+ | #* Use the K102 corrector pair to center beam on the viewer. | ||
+ | # Continue to set up keV beam to FC#1 per normal operating procedure. | ||
+ | # Execute UITFList #### with Scott Windham and Weiwei Lu to map the Chopper Slit Encoder (Encoder motor was changed over the down) | ||
+ | # Once mapped, withdraw the chopper slit (it will not be used for this experiment) | ||
+ | # Continue beam setup to FC#2 per procedure | ||
+ | # Establish beam to the keV spectrometer | ||
+ | #* Take a harp scan | ||
+ | #* Calculate the beam energy based on the field and check that this matches what the gun voltage reports | ||
+ | #* Perform an emittance measurement using the K501 wire scanner | ||
+ | #* Perform an emittance measurement using the K501 viewer | ||
+ | #* Calculate beam emittance and twiss parameters per procedure and match beam to MFQK403 | ||
+ | |||
+ | MeV mode: |
Revision as of 14:41, 28 July 2021
'Gun Test Stand Mode:'
- HV commissioning and processing of the gun
- Determination of Operating Voltage for a low FE or FE free regime
keV mode: (VBVM101 locked in)
- Insert Faraday cups 1 & 2.
- Systematically insert all of the Viewers in the keV region. Verify they all insert, retract, and are focused and the the lights work. File PR if problem arises.
- Open and close each valve and makes sure it hits its limit switch on both sides. Leave all valves opened when completed. File PR if problem arises.
- Turn on gun to operating voltage.
- Insert ITVK201
- MBHK101H & V, MBHK102H & V, and MFHK101 were all disconnected this down
- Verify the MBHK101H & V correctors kick in the appropriate dimension and with the appropriate sign. File PR if problem arises.
- Verify the MBHK102H & V correctors kick in the appropriate dimension and with the appropriate sign. File PR if problem arises.
- Use MFHK101 to determine the magnetic field which approximately focus beam on the viewer; use correctors as necessary to keep beam on the viewer.
- Using the ditherer, dither the solenoid by 10% and use the K101 corrector pair to center beam in the solenoid (i.e. where there is no horizontal/vertical displacement as the field changes)
- Use the K102 corrector pair to center beam on the viewer.
- Continue to set up keV beam to FC#1 per normal operating procedure.
- Execute UITFList #### with Scott Windham and Weiwei Lu to map the Chopper Slit Encoder (Encoder motor was changed over the down)
- Once mapped, withdraw the chopper slit (it will not be used for this experiment)
- Continue beam setup to FC#2 per procedure
- Establish beam to the keV spectrometer
- Take a harp scan
- Calculate the beam energy based on the field and check that this matches what the gun voltage reports
- Perform an emittance measurement using the K501 wire scanner
- Perform an emittance measurement using the K501 viewer
- Calculate beam emittance and twiss parameters per procedure and match beam to MFQK403
MeV mode: