Line 8: | Line 8: | ||
1. Further analysis of June data | 1. Further analysis of June data | ||
+ | |||
2. Realistic PMT response | 2. Realistic PMT response | ||
+ | |||
3. Surveying scattering chamber, prepping for removal | 3. Surveying scattering chamber, prepping for removal | ||
+ | |||
4. Run time estimates | 4. Run time estimates | ||
− | 5. Dump simulations | + | |
+ | 5. Dump simulations | ||
+ | * [[Media:130501_G4report.pdf]] | ||
+ | |||
6. Direction & schedule forward | 6. Direction & schedule forward | ||
+ | * Arne: come back mid-June after director's review | ||
+ | * Spata: unlikely prior to 10/5; bring plans to B-Team for review in 2 weeks; January 2014? |
Revision as of 13:45, 1 May 2013
We will meet in ARC 428 on Wednesday May 1 at 3pm EST.
For those calling in we'll use the ReadyTalk audio conference system.
1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada) 2. Enter 7-digit access code 3441852, followed by “#”
Topics that I believe we'll discuss are...
1. Further analysis of June data
2. Realistic PMT response
3. Surveying scattering chamber, prepping for removal
4. Run time estimates
5. Dump simulations * Media:130501_G4report.pdf
6. Direction & schedule forward * Arne: come back mid-June after director's review * Spata: unlikely prior to 10/5; bring plans to B-Team for review in 2 weeks; January 2014?