Difference between revisions of "July 5, 2022 - Group meeting"
Jump to navigation
Jump to search
Line 17: | Line 17: | ||
; UITF | ; UITF | ||
+ | * this week (Jul 4th) => see if we can wrap up cave work, back to beam permit? | ||
+ | * next week (Jul 11th) => MeV HCO in AM, then beam for main jobs (beam FC, viewer shields, Wien E/B cal, beam Mott dump, Mott det/DAQ, prebuncher) | ||
+ | * following 2 weeks (July 18 - Aug 1) => MeV beam ops (prebuncher, booster, wastewater) | ||
; Your Projects | ; Your Projects | ||
+ | * Gabriel 500 kV insulator | ||
+ | * Marcy mini-Mott | ||
+ | * Mamun TE011 cavity & vacuum work | ||
+ | * Riad LDRD | ||
+ | * Shukui KL laser |
Revision as of 08:46, 5 July 2022
July 5
- NA-PAC
- Travel ready?
- Proceedings due Aug 2 (4 weeks)
- https://wiki.jlab.org/ciswiki/index.php/CIS_Conference_and_Workshop_Proceedings
- Papers and reports
- Valeria's - summer study report
- Matt's PV - graphics from Joe Wien, Marcy Molflow, Riad PV
- Sajini's and Mamun's and Riad's magnetized beams - peer review
- Josh's and Joe's biased anode - author review
- CEBAF and 200 KV gun
- Riad on-call - Wien SCE 60 Hz ~10% intensity after apertures, Tom says causes RF issues - https://logbooks.jlab.org/entry/4011183
- Gun2 lifetime getting better - https://logbooks.jlab.org/entry/4011198
- UITF
- this week (Jul 4th) => see if we can wrap up cave work, back to beam permit?
- next week (Jul 11th) => MeV HCO in AM, then beam for main jobs (beam FC, viewer shields, Wien E/B cal, beam Mott dump, Mott det/DAQ, prebuncher)
- following 2 weeks (July 18 - Aug 1) => MeV beam ops (prebuncher, booster, wastewater)
- Your Projects
- Gabriel 500 kV insulator
- Marcy mini-Mott
- Mamun TE011 cavity & vacuum work
- Riad LDRD
- Shukui KL laser