Difference between revisions of "Running Daily Phase 2 Minutes"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "=== Mar 10, 2023 === * Max :: ...running final beam test, plans to wrap up today, latest Sunday :: ...coordinating w/ DC Power and I&C to de-energize and disconnect cables to...")
 
Line 1: Line 1:
 
=== Mar 10, 2023 ===
 
=== Mar 10, 2023 ===
 +
* Joe
 +
:: ...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517
 +
:: ...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room
 +
:: ...Carlos' ATLIS here => * ATLIS => https://tasklists.jlab.org/atlis/tasks/108541
 
* Max
 
* Max
 
:: ...running final beam test, plans to wrap up today, latest Sunday
 
:: ...running final beam test, plans to wrap up today, latest Sunday
Line 6: Line 10:
 
:: ...polishing CEBAF install work plan gantt chart, will circulate and review on Monday
 
:: ...polishing CEBAF install work plan gantt chart, will circulate and review on Monday
 
:: ...coordinating w/ Vince for modification of "blue" HV chamber base plate next week
 
:: ...coordinating w/ Vince for modification of "blue" HV chamber base plate next week
* Joe
 
:: ...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517
 
:: ...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room
 
 
* Steve
 
* Steve
 
:: ...has plan to work with Scott and to document racks/controls during SAD
 
:: ...has plan to work with Scott and to document racks/controls during SAD
 
:: ...let's review laser plan with Shukui (replace Hall A mode-lock with temp regulating seed, continue developing/testing new board for later upgrade)
 
:: ...let's review laser plan with Shukui (replace Hall A mode-lock with temp regulating seed, continue developing/testing new board for later upgrade)

Revision as of 09:41, 10 March 2023

Mar 10, 2023

  • Joe
...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517
...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room
...Carlos' ATLIS here => * ATLIS => https://tasklists.jlab.org/atlis/tasks/108541
  • Max
...running final beam test, plans to wrap up today, latest Sunday
...coordinating w/ DC Power and I&C to de-energize and disconnect cables to magnets and bpm's
  • Marcy
...polishing CEBAF install work plan gantt chart, will circulate and review on Monday
...coordinating w/ Vince for modification of "blue" HV chamber base plate next week
  • Steve
...has plan to work with Scott and to document racks/controls during SAD
...let's review laser plan with Shukui (replace Hall A mode-lock with temp regulating seed, continue developing/testing new board for later upgrade)