Difference between revisions of "MOLLER PQB Meeting October 30, 2024"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "In person in MCC Conference Room and with Zoom. https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam -- '''Agenda:''' * '''Injector Upgrade Progress:''' # RTP n...")
 
Line 9: Line 9:
  
  
* '''Injector Upgrade Progress:'''
+
# JLAB Prototype HV Driver:
 
+
## Burn-in at 30 Hz on-going
# RTP new HV Driver full system is finally ready:
+
## RTP Driver Prototype Crosstalk tests - Jim Kortze: [[media:]]
## Burn-in at 30 Hz started last week
 
 
## Installation Schedule: [[media:RTP_Installation_Schedule.pdf]]
 
## Installation Schedule: [[media:RTP_Installation_Schedule.pdf]]
  
  
* '''MOLLER new rack in ISB - IN03B25''' - will be powered up on 10/3/2025, equipped with UPS: [[media:IMG_1910.jpg]]
+
* '''Injector Upgrade Progress:'''

Revision as of 03:16, 30 October 2024

In person in MCC Conference Room and with Zoom.

https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam

--


Agenda:


  1. JLAB Prototype HV Driver:
    1. Burn-in at 30 Hz on-going
    2. RTP Driver Prototype Crosstalk tests - Jim Kortze: [[media:]]
    3. Installation Schedule: media:RTP_Installation_Schedule.pdf


  • Injector Upgrade Progress: