(Created page with "= '''Run Plan''' = # Tue, August 11: Turn on gun, commission new lasers, beam to FC1 (Joe Grames). # Wed, August 12: Beam to FC2 and 5D dump (Yan, Riad). # Thursday, August 13...") |
|||
Line 1: | Line 1: | ||
= '''Run Plan''' = | = '''Run Plan''' = | ||
+ | |||
+ | This is a test of 5D line, the chamber is off. | ||
+ | |||
# Tue, August 11: Turn on gun, commission new lasers, beam to FC1 (Joe Grames). | # Tue, August 11: Turn on gun, commission new lasers, beam to FC1 (Joe Grames). | ||
# Wed, August 12: Beam to FC2 and 5D dump (Yan, Riad). | # Wed, August 12: Beam to FC2 and 5D dump (Yan, Riad). |
Revision as of 16:02, 5 August 2015
Run Plan
This is a test of 5D line, the chamber is off.
- Tue, August 11: Turn on gun, commission new lasers, beam to FC1 (Joe Grames).
- Wed, August 12: Beam to FC2 and 5D dump (Yan, Riad).
- Thursday, August 13: Check beam optics to 5D (Chris). Measure beam current (Riad).
- Friday, August 14: Mott and photocathode Analyzing power (Joe ,Riad).
- Saturday, August 15: Find maximum energy and measure beam energy (Jay, Riad).