Difference between revisions of "GTS meeting 3 28 17"
Jump to navigation
Jump to search
Line 3: | Line 3: | ||
* Plan for this week (March 27, 2017): | * Plan for this week (March 27, 2017): | ||
− | # Monday, Tuesday and Wednesday: open in morning to install beamline but close in afternoon to run beam | + | # Monday, Tuesday and Wednesday: open in morning to install second part of beamline but close in afternoon to run beam |
# Thursday and Friday open all day for beamline bake. Turn ON the extractor gauge in Gun HV Chamber. Use GN2 heater to send 250 C hot gas through the water lines of the FCup to degas. | # Thursday and Friday open all day for beamline bake. Turn ON the extractor gauge in Gun HV Chamber. Use GN2 heater to send 250 C hot gas through the water lines of the FCup to degas. | ||
# Week of April 3rd: finish bake and instrument beamline | # Week of April 3rd: finish bake and instrument beamline | ||
Line 9: | Line 9: | ||
* What we are working on now: | * What we are working on now: | ||
# Put a laser Newport powermeter at the exit window side of the gun using a RS232 for controls | # Put a laser Newport powermeter at the exit window side of the gun using a RS232 for controls | ||
− | # Put | + | # Put cover around laser tables |
# Still trying to center the gun solenoid | # Still trying to center the gun solenoid | ||
# Do we want to keep the anode biased at +280 V all times (and while running beam)? | # Do we want to keep the anode biased at +280 V all times (and while running beam)? | ||
− | * Emittance vs Gun HV | + | * Emittance vs Gun HV: [[media:Emittance_GunHV_3468399.xlsx]] [https://logbooks/entry/3468399] |
* These are the simulation tasks that we should try: | * These are the simulation tasks that we should try: | ||
# simulate emittance vs Gun HV | # simulate emittance vs Gun HV | ||
# | # |
Revision as of 09:11, 27 March 2017
- Conditioned Gun at 300 kV with solenoid at 0 to 300 A, left to do it at: 325, 350, 375, and 400 A. Two currents, 350 and 400 A, we attempted before but we will repeat.
- Plan for this week (March 27, 2017):
- Monday, Tuesday and Wednesday: open in morning to install second part of beamline but close in afternoon to run beam
- Thursday and Friday open all day for beamline bake. Turn ON the extractor gauge in Gun HV Chamber. Use GN2 heater to send 250 C hot gas through the water lines of the FCup to degas.
- Week of April 3rd: finish bake and instrument beamline
- What we are working on now:
- Put a laser Newport powermeter at the exit window side of the gun using a RS232 for controls
- Put cover around laser tables
- Still trying to center the gun solenoid
- Do we want to keep the anode biased at +280 V all times (and while running beam)?
- Emittance vs Gun HV: media:Emittance_GunHV_3468399.xlsx [1]
- These are the simulation tasks that we should try:
- simulate emittance vs Gun HV