Difference between revisions of "GTS meeting 8 28 17"
Jump to navigation
Jump to search
Line 11: | Line 11: | ||
## Replace leaky vent valve | ## Replace leaky vent valve | ||
## Replace bad ion pump | ## Replace bad ion pump | ||
+ | # Next Shutdown – December: | ||
+ | ## Install TE011 cavity |
Revision as of 08:14, 28 August 2017
- Emittance Measurements with large laser size (rms=0.423mm) - Yan
- New plan:
- Finish emittance measurements, including a larger laser size (x4) – August 21-25
- Attempt 5 mA (non-magnetized, then magnetized) – August 28-31
- Shutdown – September 5:
- Install new YAG screen at viewer 3
- Fix existing harp and install 20 µm tungsten wire
- Add a new CEBAF-style harp with 10 µm tungsten wire (i.e, GTS will have two harps)
- Replace leaky vent valve
- Replace bad ion pump
- Next Shutdown – December:
- Install TE011 cavity