Difference between revisions of "GTS meeting 10 16 17"
Jump to navigation
Jump to search
Line 4: | Line 4: | ||
# Fix existing harp and install 20 µm tungsten wire | # Fix existing harp and install 20 µm tungsten wire | ||
# Add a new CEBAF-style harp with 10 µm tungsten wire (''i.e'', GTS will have two harps) | # Add a new CEBAF-style harp with 10 µm tungsten wire (''i.e'', GTS will have two harps) | ||
− | # | + | # Fix leaky vent valve |
− | |||
# Activate new photocathode (new puck) with full active area | # Activate new photocathode (new puck) with full active area | ||
Latest revision as of 10:46, 16 October 2017
- Shutdown Plan:
- Install new YAG screen at viewer 3
- Fix existing harp and install 20 µm tungsten wire
- Add a new CEBAF-style harp with 10 µm tungsten wire (i.e, GTS will have two harps)
- Fix leaky vent valve
- Activate new photocathode (new puck) with full active area
- Map RadiaBeam steerer and measure the electrical characteristics (e.g., time constant)
- Next Shutdown – January 2018:
- Install TE011 cavity
- High current runs: [1]