*List of modifications:
+
* List of beamline hardware modifications:
 
# Replace YAG screen on Viewer 1
 
# Replace YAG screen on Viewer 1
 
# Replace Slit on Viewer 2 with holes assembly
 
# Replace Slit on Viewer 2 with holes assembly
Line 12: Line 12:
 
# Move DP can 1 to end of beamline
 
# Move DP can 1 to end of beamline
 
# All bellows at least 2.5 inch diameter
 
# All bellows at least 2.5 inch diameter
 +
 +
 +
* List of software and controls changes:
 +
# Re-program SCAM to allow for 1 Hz and 50 ns pulses
 +
# Add 5th solenoid to magnet screen

Revision as of 10:59, 4 January 2019

  • List of beamline hardware modifications:
  1. Replace YAG screen on Viewer 1
  2. Replace Slit on Viewer 2 with holes assembly
  3. Replace two ion collectors with new ones
  4. Replace Harp fork (Tony)
  5. Remove modified DP can
  6. Remove Faraday Cup
  7. Remove bellow upstream of dump
  8. Install TE011 Cavity
  9. Install Deflecting Cavity
  10. Install new 5th solenoid
  11. Move DP can 1 to end of beamline
  12. All bellows at least 2.5 inch diameter


  • List of software and controls changes:
  1. Re-program SCAM to allow for 1 Hz and 50 ns pulses
  2. Add 5th solenoid to magnet screen