(Created page with "* '''Laser 10 W Fiber Amp will be moved to Hall A Compton on April 8, 2019''' * '''Laser 5 W Fiber Amp will be installed on April 22, 2019''' * '''Degas deflecting cavity'...") |
|||
Line 1: | Line 1: | ||
− | * | + | * Laser 10 W Fiber Amp will be moved to Hall A Compton on April 11, 2019 - '''completed''' |
− | * | + | * Laser 5 W Fiber Amp will be installed on April 11, 2019 - '''completed, but not functional yet''' |
− | * ''' | + | * Degas deflecting cavity with RF up to 300 W - '''completed''' |
Line 12: | Line 12: | ||
# Commission TE011 cavity | # Commission TE011 cavity | ||
# Radiation Surveys at 1 mA | # Radiation Surveys at 1 mA | ||
− | |||
# Ghost beam studies with P-Gun | # Ghost beam studies with P-Gun |
Revision as of 08:35, 15 April 2019
- Laser 10 W Fiber Amp will be moved to Hall A Compton on April 11, 2019 - completed
- Laser 5 W Fiber Amp will be installed on April 11, 2019 - completed, but not functional yet
- Degas deflecting cavity with RF up to 300 W - completed
- List of things to do:
- Transverse beam emittance measurement with 1D pepper-pot
- Commission TE011 cavity
- Radiation Surveys at 1 mA