Line 5: Line 5:
  
  
* Degas deflecting cavity with RF up to 300 W - '''completed'''
+
* Degas deflecting cavity with RF up to 300 W - '''completed''' [https://logbooks/entry/3679127]
  
  

Revision as of 11:32, 15 April 2019

  • Laser 10 W Fiber Amp will be moved to Hall A Compton on April 11, 2019 - completed


  • Laser 5 W Fiber Amp will be installed on April 11, 2019 - completed, but not functional yet


  • Degas deflecting cavity with RF up to 300 W - completed [1]


  • List of things to do:
  1. Transverse beam emittance measurement with 1D pepper-pot
  2. Commission TE011 cavity
  3. Radiation Surveys at 1 mA
  4. Ghost beam studies with P-Gun