(Created page with "*Update: ** Replaced thermionic cathode ** Added leak valve on mini-flange ** Started Kr processing *Talking Points: ** Equipment damage during HV processing: Radiation gam...") |
|||
Line 1: | Line 1: | ||
*Update: | *Update: | ||
− | ** | + | ** Kr processing attempted - not really successful. |
− | ** | + | ** 2 days under vacuum at 120kV, but with radiation increasing. |
− | ** | + | ** Spare cathode is dead |
− | |||
*Talking Points: | *Talking Points: | ||
** Equipment damage during HV processing: Radiation gamma probe (again), Cathode Solenoid LCW flowmeter chassis (again) | ** Equipment damage during HV processing: Radiation gamma probe (again), Cathode Solenoid LCW flowmeter chassis (again) | ||
+ | ** Magnetizing solenoid PS may be used in LERF for a while for isotopes. | ||
+ | |||
+ | *Suggested Actions: | ||
+ | ** Open up the gun - look for damage (take care with cathode) | ||
+ | ** Install the glassman supply as an alternative HVPS source | ||
+ | ** One final change to the grounding of the Spellman, where HVPS chassis is grounded in the vault |
Revision as of 08:58, 9 September 2019
- Update:
- Kr processing attempted - not really successful.
- 2 days under vacuum at 120kV, but with radiation increasing.
- Spare cathode is dead
- Talking Points:
- Equipment damage during HV processing: Radiation gamma probe (again), Cathode Solenoid LCW flowmeter chassis (again)
- Magnetizing solenoid PS may be used in LERF for a while for isotopes.
- Suggested Actions:
- Open up the gun - look for damage (take care with cathode)
- Install the glassman supply as an alternative HVPS source
- One final change to the grounding of the Spellman, where HVPS chassis is grounded in the vault