(Created page with "== (1) Get GTS back to operational == To Fix List (to get GTS running): * Glassman PSS Chassis (Service request to Omar - Carlos) * LCW Chassis (Sarin- Fay follow up) * Spel...") |
|||
Line 1: | Line 1: | ||
− | == (1) | + | '''Limit voltage to 135kV''' |
+ | |||
+ | == (1) Status == | ||
+ | |||
+ | * Gun assembled with ceramic and blank flange only. Pumping. | ||
+ | * RF cage complete | ||
+ | * Back plate modified and hot deck attached in 'run set-up' | ||
+ | * Electrode assembled and snow cleaned ready for installation | ||
+ | * GTS clean | ||
+ | |||
+ | == (2) Plans == | ||
+ | * PSS cert | ||
+ | * Run up Xelera spellman connected to gun to 135kV | ||
+ | * If corona test good... break vacuum and install electrodes | ||
To Fix List (to get GTS running): | To Fix List (to get GTS running): | ||
* Glassman PSS Chassis (Service request to Omar - Carlos) | * Glassman PSS Chassis (Service request to Omar - Carlos) | ||
− | * LCW Chassis ( | + | * LCW Chassis (Coleman today or tomorrow) |
− | * Spellman ( | + | * Spellman (needs further investigation) |
* Picoammeter x2? (Pete Francis in hand - sent for fix) | * Picoammeter x2? (Pete Francis in hand - sent for fix) | ||
* Viewers insertion boxes bad | * Viewers insertion boxes bad | ||
Line 14: | Line 27: | ||
* Cathode solenoid - power supply | * Cathode solenoid - power supply | ||
− | + | == (4) T-Gun Upgrades == | |
− | |||
− | |||
− | |||
− | |||
− | == ( | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
To Fix/Modify: | To Fix/Modify: | ||
* DC bias supply - set point fix (John Musson) | * DC bias supply - set point fix (John Musson) | ||
− | |||
− | |||
* Software issues (Karl to contact Spellman again) | * Software issues (Karl to contact Spellman again) | ||
* Install new fiber link & check (CW setting - Mark emailed company) | * Install new fiber link & check (CW setting - Mark emailed company) | ||
* Need RF fiber from Karl for reflected power | * Need RF fiber from Karl for reflected power | ||
− | == ( | + | == (5) Housekeeping== |
− | + | ||
− | |||
* Remove JLab spellman | * Remove JLab spellman | ||
* Sort out the air and nitrogen lines. | * Sort out the air and nitrogen lines. | ||
− |
Revision as of 07:31, 7 October 2019
Limit voltage to 135kV
(1) Status
- Gun assembled with ceramic and blank flange only. Pumping.
- RF cage complete
- Back plate modified and hot deck attached in 'run set-up'
- Electrode assembled and snow cleaned ready for installation
- GTS clean
(2) Plans
- PSS cert
- Run up Xelera spellman connected to gun to 135kV
- If corona test good... break vacuum and install electrodes
To Fix List (to get GTS running):
- Glassman PSS Chassis (Service request to Omar - Carlos)
- LCW Chassis (Coleman today or tomorrow)
- Spellman (needs further investigation)
- Picoammeter x2? (Pete Francis in hand - sent for fix)
- Viewers insertion boxes bad
To Check:
- Magnets (IOC check)
- Cathode solenoid - power supply
(4) T-Gun Upgrades
To Fix/Modify:
- DC bias supply - set point fix (John Musson)
- Software issues (Karl to contact Spellman again)
- Install new fiber link & check (CW setting - Mark emailed company)
- Need RF fiber from Karl for reflected power
(5) Housekeeping
- Remove JLab spellman
- Sort out the air and nitrogen lines.