This area is related to Injector Upgrade Meetings | This area is related to Injector Upgrade Meetings | ||
+ | |||
+ | ==Injector upgrade calendar== | ||
+ | :: Run (now - May 6) | ||
+ | :: Phase 1 (May 6 - end of 2020) | ||
+ | :: Run (Jan 2021 - Sep 13 2021) | ||
+ | :: Phase 2 (Sep 13 - end of 2021) | ||
+ | |||
=== [[Injector Upgrade Meetings]] === | === [[Injector Upgrade Meetings]] === | ||
Line 29: | Line 36: | ||
* [https://jeffersonlab-my.sharepoint.com/:f:/g/personal/grames_jlab_org/EhXqNtq16CBNt4JzMmy4T1ABNsJ15YGBFTQkkMenD_ommQ Link to AIPINJ OneDrive folder] | * [https://jeffersonlab-my.sharepoint.com/:f:/g/personal/grames_jlab_org/EhXqNtq16CBNt4JzMmy4T1ABNsJ15YGBFTQkkMenD_ommQ Link to AIPINJ OneDrive folder] | ||
* [[AIPINJ Layouts]] | * [[AIPINJ Layouts]] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
=== [[Injector Upgrade Documents and Links]] === | === [[Injector Upgrade Documents and Links]] === |
Revision as of 12:26, 13 February 2020
This area is related to Injector Upgrade Meetings
Injector upgrade calendar
- Run (now - May 6)
- Phase 1 (May 6 - end of 2020)
- Run (Jan 2021 - Sep 13 2021)
- Phase 2 (Sep 13 - end of 2021)
Injector Upgrade Meetings
Link to AIPINJ OneDrive folder
AIPINJ Layouts
Components
ATLIS Tasks
AIPINJ
- Testing Wien HV Controls at UITF
- Accelerator network re-survey
- Remove and re-install BPM's Gun to chopper
- Install new IPM2I03
- Remove and calibrate current monitoring electronics
- Harp work
Non-AIPINJ
- New Gun2 loading chamber
- Placeholder for Tim Minga to test laser room smoke detector alarm to MCC/Guard