=== Week 3 (Oct 5 - Oct 11) ===
 
=== Week 3 (Oct 5 - Oct 11) ===
 +
* Vacuum disconnects
  
 
=== Week 4 (Oct 12 - Oct 18) ===
 
=== Week 4 (Oct 12 - Oct 18) ===

Revision as of 08:32, 28 September 2020

Week 1 (Sep 21 - Sep 27)

Week 2 (Sep 28 - Oct 4)

Fri 9/25 - Mon 9/28
  • CIS Gun Jobs
Wien electrode testing – 9am!!!
Gun HVPS lockout - DONE
Gun HV cable disconnect – DONE
Remove PIG – Coordinate w/ Neil for convenient time
Shukui - Laser outrigger table as-founds, remove components
Scott - Remove yellow box
Scott - Disconnect Decarad
Monday 9/28 Tasks (updated 0915 9/28)
  • Power down Wein system (Scott/Joe)
  • Power down and remove DecaRad system (Scott)
  • Return gun valve config to "normal" (Marcy)
  • Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
  • PSS Kickers and associated chassis removal (SSG)
  • Laser table disassembly (Shukui/Scott)
Tue 9/29 – Fri 10/1
Tunnel Work
  • Remove suitcase
  • EES-IC Disconnects 5a - 8a, Tues-Fri
  • RadCon probe disconnects, 8a - 10a, Tues
  • DC Power magnet disconnects, 10a - 4p Tues, 10a-noon Wed+Thur
  • Prebuncher disconnects, 8a - 10a, Wed

Week 3 (Oct 5 - Oct 11)

  • Vacuum disconnects

Week 4 (Oct 12 - Oct 18)

Week 5 (Oct 19 - Oct 25)

  • Injector is now in restricted access all the time
  • LOTO and system disconnects

Week X