Line 45: | Line 45: | ||
* Sample hold cables install, InjSB (Francis) | * Sample hold cables install, InjSB (Francis) | ||
* Remaining PSS Interface chassis removal (SSG) | * Remaining PSS Interface chassis removal (SSG) | ||
+ | * Harp upgrade to PC104 (Dela Cruz) | ||
* Moser transfers CCOC phone @1430, to reach moving forward x5089 | * Moser transfers CCOC phone @1430, to reach moving forward x5089 | ||
Line 50: | Line 51: | ||
; Thursday 10/1 Tasks (updated 0830 10/1) | ; Thursday 10/1 Tasks (updated 0830 10/1) | ||
* Picoammeter Removal, InjSB (Francis) 5a | * Picoammeter Removal, InjSB (Francis) 5a | ||
− | * Sample hold cables install, | + | * Sample hold cables install, IN02B24 (Francis) |
− | * BPM Work in | + | * BPM Work in IN02B2* (Francis) |
* Chopper amplifier upgrade (Farrish) | * Chopper amplifier upgrade (Farrish) | ||
− | * Viewer hardware disconnects (Norris) 6a | + | * Harp upgrade to PC104 (Dela Cruz) |
+ | * Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a | ||
* Disconnecting water and air lines from apertures and cups (Adderley) 8a | * Disconnecting water and air lines from apertures and cups (Adderley) 8a | ||
* Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a | * Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a | ||
Line 59: | Line 61: | ||
; Friday 10/2 Tasks | ; Friday 10/2 Tasks | ||
− | * | + | * BPM Work in IN02B2* (Francis) |
+ | * Chopper amplifier upgrade (Farrish) | ||
+ | * Harp upgrade to PC104 (Dela Cruz) | ||
+ | * Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a | ||
+ | |||
+ | |||
; Tue 9/29 – Fri 10/1 (updated 0900 9/30) | ; Tue 9/29 – Fri 10/1 (updated 0900 9/30) | ||
Line 68: | Line 75: | ||
! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2 | ! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2 | ||
|- | |- | ||
− | | 4a - 8a || || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher || I&C; 6a: Norris: Viewer | + | | 4a - 8a || || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher || I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps || I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps |
|- | |- | ||
| 8a - 10a || CIS + SSG || RadCon: rad probes || SSG: Kicker magnet removal; CIS: Tiny magnet removals || CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru || | | 8a - 10a || CIS + SSG || RadCon: rad probes || SSG: Kicker magnet removal; CIS: Tiny magnet removals || CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru || |
Revision as of 07:59, 1 October 2020
Week 1 (Sep 21 - Sep 27)
- Updated schedule media:200914_AIPINJ_Weeks_Sep_18_update.docx
- High voltage test slides media:200902_HV_Plans.pptx
- Gun and Wien tasks Media:High Voltage Work Gun2 & Wien filters.xlsx
Week 2 (Sep 28 - Oct 4)
- Fri 9/25 - Mon 9/28
- CIS Gun Jobs
- Wien electrode testing – 9am!!!
- Gun HVPS lockout - DONE
- Gun HV cable disconnect – DONE
- Remove PIG – Coordinate w/ Neil for convenient time
- Shukui - Laser outrigger table as-founds, remove components
- Scott - Remove yellow box
- Scott - Disconnect Decarad
- Monday 9/28 Tasks (updated 0915 9/28)
- Power down Wein system (Scott/Joe)
- Power down and remove DecaRad system (Scott)
- Return gun valve config to "normal" (Marcy)
- Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
- PSS Kickers and associated chassis removal (SSG)
- Laser table disassembly (Shukui/Scott)
- Tuesday 9/29 Tasks (updated 0930 9/29)
- (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
- (Done) Disconnect aperture and cup signal cables (Pete) 5a
- Disconnect rad probes (Melvin) 8a
- Tunnel magnet disconnects (Diggs, Delk) 10a
- (Done) Removal of old chopper amps from rack (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- ODH Head Replacements (SSG)
- Document existing Wein cabling and power off PS (Scott)
- Wednesday 9/30 Tasks (updated 0900 9/30)
- RF Prebuncher disconnects (Farrish) 6a
- Vacuum Component Labeling (Greenfield, Gonzales) 430a
- Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a
- Tiny magnet removals (Scott, Grames) 9a
- PSS Kicker Magnet removal (SSG) 9a
- Sample hold cables install, InjSB (Francis)
- Remaining PSS Interface chassis removal (SSG)
- Harp upgrade to PC104 (Dela Cruz)
- Moser transfers CCOC phone @1430, to reach moving forward x5089
- Thursday 10/1 Tasks (updated 0830 10/1)
- Picoammeter Removal, InjSB (Francis) 5a
- Sample hold cables install, IN02B24 (Francis)
- BPM Work in IN02B2* (Francis)
- Chopper amplifier upgrade (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
- Disconnecting water and air lines from apertures and cups (Adderley) 8a
- Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
- Friday 10/2 Tasks
- BPM Work in IN02B2* (Francis)
- Chopper amplifier upgrade (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
- Tue 9/29 – Fri 10/1 (updated 0900 9/30)
- Tunnel Work
Time | Mon 9/28 | Tue 9/29 | Wed 9/30 | Thu 10/1 | F 10/2 |
---|---|---|---|---|---|
4a - 8a | I&C; 5a: Francis: BPMs, Cups, Apertures | I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher | I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps | I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps | |
8a - 10a | CIS + SSG | RadCon: rad probes | SSG: Kicker magnet removal; CIS: Tiny magnet removals | CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru | |
10a - 12p | CIS + SSG | DC Power | DC Power: Wire wrap-ups, junction box investigation | ||
12p - 2p | CIS + SSG | DC Power | DC Power: Wire wrap-ups, junction box investigation | DC Power | |
2p - 4p | CIS + SSG | DC Power | 3p: Moser: Safety Warden checks | ||
4p - ?? |
- Other Work Occurring When Convenient
- Remove suitcase, Tunnel (CIS)
- Harp upgrade, InjSB (I&C)
- ODH Head Replacement, InjSB and Tunnel (SSG)
- PSS Chassis Removals, InjSB (SSG)
Week 3 (Oct 5 - Oct 11)
- Vacuum disconnects
Week 4 (Oct 12 - Oct 18)
Week 5 (Oct 19 - Oct 25)
- Injector is now in restricted access all the time
- LOTO and system disconnects
Week X
- Vacuum jobs Options for gun through y-chamber