Difference between revisions of "CIS Phase 1 work plans"
Jump to navigation
Jump to search
Line 238: | Line 238: | ||
* ME provide ALL points to S&A for installation (gun table, 2I stand, Y-chamber, 2 peds for Wien, 2 peds A1/A2) => '''???''' | * ME provide ALL points to S&A for installation (gun table, 2I stand, Y-chamber, 2 peds for Wien, 2 peds A1/A2) => '''???''' | ||
* Carlos' Wien-mania! | * Carlos' Wien-mania! | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
;Tunnel Work | ;Tunnel Work | ||
* Complete remove old keV Mott cables => '''done''' | * Complete remove old keV Mott cables => '''done''' | ||
− | * Complete remove old gun HV cables => ''' | + | * Complete remove old gun HV cables => '''done''' |
− | * Jim pulls Wien PS cables? => ''' | + | * Jim pulls Wien PS cables? => '''done???''' |
* Does Wien HV cable pull start? => '''starting this week''' | * Does Wien HV cable pull start? => '''starting this week''' | ||
* Scott will finish tie back of cables on tunnel floor to cable tray => '''done''' | * Scott will finish tie back of cables on tunnel floor to cable tray => '''done''' | ||
* Refill 86? => '''no, not yet''' | * Refill 86? => '''no, not yet''' | ||
− | |||
− | |||
− | |||
; Standing Injector Service Building Work | ; Standing Injector Service Building Work | ||
Line 263: | Line 254: | ||
* PSS Upgrade, IN02{BNI, B29, B30} (SSG) | * PSS Upgrade, IN02{BNI, B29, B30} (SSG) | ||
* 20A PS Install, Rack re-org, IN02B22 (DC Power) | * 20A PS Install, Rack re-org, IN02B22 (DC Power) | ||
− | |||
; Monday Oct 19 | ; Monday Oct 19 | ||
Line 336: | Line 326: | ||
<div class="mw-collapsible"> | <div class="mw-collapsible"> | ||
;Non-Tunnel Work | ;Non-Tunnel Work | ||
− | * Install NEG towers | + | * Install NEG towers |
− | * Attach new Gun2 or Gun3 valve ( | + | * Attach new Gun2 or Gun3 valve (If desired) |
+ | * Finish Y-chamber viewers, attach | ||
* Prep new Y-chamber for tunnel, can be under vacuum | * Prep new Y-chamber for tunnel, can be under vacuum | ||
* Wien-mania! | * Wien-mania! | ||
− | ::-Wien magnetic field mapping | + | ::-Wien magnetic field mapping |
+ | ::-Bubba assembles the fixtures | ||
;Tunnel work | ;Tunnel work | ||
Line 346: | Line 338: | ||
* Vent Gun2 chamber to test Gun2 valve | * Vent Gun2 chamber to test Gun2 valve | ||
::Remove NEG filter chamber before vent | ::Remove NEG filter chamber before vent | ||
− | :: | + | ::Setup mobile cleanroom for gun work => comes from TL (Bubba/Neil) |
* Remove 2I NEG beam line | * Remove 2I NEG beam line | ||
− | + | ::remove NEG pedestal (temporarily) | |
* Replace 10” flange + SHV connector + blank off + pump down | * Replace 10” flange + SHV connector + blank off + pump down | ||
* Pump down Blank off old Y-chamber + pinch off + removal | * Pump down Blank off old Y-chamber + pinch off + removal | ||
+ | * Wrap up in itial UHV ion pump power supply power tests | ||
* INSTALL lift and move gun table to move foot pads | * INSTALL lift and move gun table to move foot pads | ||
* S&A sets points | * S&A sets points | ||
− | |||
− | |||
− | |||
− | |||
<u>'''Injector Tunnel and Service Building Work'''</u> | <u>'''Injector Tunnel and Service Building Work'''</u> | ||
Line 378: | Line 367: | ||
</div> | </div> | ||
− | === Week 7 (Nov 2 - Oct 6) | + | === Week 7 (Nov 2 - Oct 6) and beyond... === |
<div class="mw-collapsible mw-collapsed"> | <div class="mw-collapsible mw-collapsed"> | ||
Tunnel work | Tunnel work | ||
+ | * INSTALL sets new foot pads, new anchor bolts if needed | ||
+ | * INSTALL lift and move gun table to new foot pads | ||
+ | * INSTALL move new y-chamber from TL-1137 to injector, and vice versa | ||
* S&A and CIS install and align Y-chamber + NEG tube + Gun table (CL cathode/anode) | * S&A and CIS install and align Y-chamber + NEG tube + Gun table (CL cathode/anode) | ||
* Pump down and leak check | * Pump down and leak check |
Revision as of 18:00, 22 October 2020
Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups
- Updated schedule media:200914_AIPINJ_Weeks_Sep_18_update.docx
- High voltage test slides media:200902_HV_Plans.pptx
- Gun and Wien tasks Media:High Voltage Work Gun2 & Wien filters.xlsx
Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- Fri 9/25 - Mon 9/28
- CIS Gun Jobs
- Wien electrode testing – 9am!!!
- Gun HVPS lockout - DONE
- Gun HV cable disconnect – DONE
- Remove PIG – Coordinate w/ Neil for convenient time
- Shukui - Laser outrigger table as-founds, remove components
- Scott - Remove yellow box
- Scott - Disconnect Decarad
- Monday 9/28 Tasks (updated 0915 9/28)
- Power down Wein system (Scott/Joe)
- Power down and remove DecaRad system (Scott)
- Return gun valve config to "normal" (Marcy)
- Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
- PSS Kickers and associated chassis removal (SSG)
- Laser table disassembly (Shukui/Scott)
- Tuesday 9/29 Tasks (updated 0930 9/29)
- (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
- (Done) Disconnect aperture and cup signal cables (Pete) 5a
- Disconnect rad probes (Melvin) 8a
- Tunnel magnet disconnects (Diggs, Delk) 10a
- (Done) Removal of old chopper amps from rack (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- ODH Head Replacements (SSG)
- Document existing Wein cabling and power off PS (Scott)
- Wednesday 9/30 Tasks (updated 0900 9/30)
- RF Prebuncher disconnects (Farrish) 6a
- Vacuum Component Labeling (Greenfield, Gonzales) 430a
- Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a
- Tiny magnet removals (Scott, Grames) 9a
- PSS Kicker Magnet removal (SSG) 9a
- Sample hold cables install, InjSB (Francis)
- Remaining PSS Interface chassis removal (SSG)
- Harp upgrade to PC104 (Dela Cruz)
- Moser transfers CCOC phone @1430, to reach moving forward x5089
- Thursday 10/1 Tasks (updated 0830 10/1)
- Picoammeter Removal, InjSB (Francis) 5a
- Sample hold cables install, IN02B24 (Francis)
- BPM Work in IN02B2* (Francis)
- Chopper amplifier upgrade (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
- Disconnecting water and air lines from apertures and cups (Adderley) 8a
- Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
- Friday 10/2 Tasks (updated 0900 10/2)
- Viewer disconnects (Norris) 6a
- BPM Work in IN02B2* (Francis)
- Chopper amplifier upgrade (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- PSS Kicker Cables tie-up (SSG)
- Survey and Alignment control measure around gun (S&A)
- Load suitcase with "bad" pucks (CIS)
- Pump-down vacuum in front of tee for next week (CIS)
- Tunnel Work
Time | Mon 9/28 | Tue 9/29 | Wed 9/30 | Thu 10/1 | F 10/2 |
---|---|---|---|---|---|
4a - 8a | I&C; 5a: Francis: BPMs, Cups, Apertures | I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher | I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps | I&C: Norris: Viewer disconnects | |
8a - 10a | CIS + SSG | RadCon: rad probes | SSG: Kicker magnet removal; CIS: Tiny magnet removals | CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru | S&A: Gun |
10a - 12p | CIS + SSG | DC Power | DC Power: Wire wrap-ups, junction box investigation | S&A: Gun; SSG: Kicker cable tie-up | |
12p - 2p | CIS + SSG | DC Power | DC Power: Wire wrap-ups, junction box investigation | DC Power | S&A: Gun |
2p - 4p | CIS + SSG | DC Power | 3p: Moser: Safety Warden checks | S&A: Gun | |
4p - ?? |
- Other Work Occurring When Convenient
- Remove suitcase, Tunnel (CIS)
- Harp upgrade, InjSB (I&C)
- ODH Head Replacement, InjSB and Tunnel (SSG)
- PSS Chassis Removals, InjSB (SSG)
Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- Monday Oct 5
- vacuum tests, disconnects, and pre-removal blank offs (CIS)
- QCM->downstream Survey and Alignment
- S&H cable work for iocinse4, InjSB (Francis)
- Tuesday Oct 6
- Survey and Alignment finishing up around 0L04 (S&A)
- U-tube operations at 0L03 (Cryo)
- S&H cable work for iocinse4, InjSB (Francis)
- Stage/prepare for craning our girders (Mech Install)
- Chopper SSA upgrade -- LCW line install, InjSB (Mech Install / RF)
- Wednesday Oct 7
- S&H cable work for iocinse4, InjSB (Francis)
- Chopper SSA upgrade, InjSB (Farrish)
- Wein PS Work, InjSB (Windham)
- VIP UHV PS Work, InjSB (Windham)
- Harp PC104 upgrade, InjSB (Dela Cruz)
- Thursday Oct 8
- BPM work, InjSB (Francis)
- Chopper SSA upgrade, InjSB (Farrish)
- Harp PC104 upgrade, InjSB (Dela Cruz)
- Wednesday Oct 7 and Thursday Oct 8 -- Mechanical Install
- Remove to test lab --
- Laser outrigger table
1st Wein girder and pedestals- 2nd Wein girder, apertures, and pedestals
Photocathode puck suitcase on cart
- Remove to Brett Lewis grey oil tank
- Penetration stone drops
Current list of Injector penetrations to be dropped: 57, 86, 108, possibly this one
Penetration drop distance e3854100:
- 34ft from floor of InjSB to floor of Inj tunnel
- 25ft from floor of InjSB to elevated Inj tunnel cable tray
- Friday Oct 9
- BPM Work, InjSB (Francis)
- Chopper SSA upgrade, InjSB (Farrish)
- Harp PC104 upgrade, InjSB (Dela Cruz)
- Penetration stone drop -- 57, 86, 108, Tunnel (Mech Install)
- Penetration above laser hut already opened
Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- Laser/Y-Chamber viewer for Y-chamber girder (Marcy)
- Fiducializing Y-chamber girder (S&A)
- Laser window under vacuum evaluations (Phil/Shukui/Caryn)
- Documenting early InjSB racks (Scott)
- Cable pulls through penetrations (EES)
Fire pipe demolition?(Facilities Contractor)- Wein upgrade (Carlos) --
- Finish new Wien electrodes drawing and sign-offs
- Vacuum chambers to machine shop for mods
- Begin creating new screens
- Injector Tunnel Photos from W 10/14
- Monday Oct 12
Tunnel --
- Hooking up VIPs to new 18V PS for load testing (Marcy/Scott)
- Cable pulls through penetrations (EES)
InjSB --
- BPM Cable Pulls through Penetration 86 (Francis)
- Chopper SSA upgrade (Farrish)
- Harp to PC104 upgrade (Dela Cruz)
- Early rack documentation and space optimization (Scott)
- PSS Upgrade work (IN02BNI, B29, B30) (SSG)
- Tuesday Oct 13
Tunnel --
- Cable pulls through penetrations (EES)
- Resistor box evaluation (Coleman)
InjSB --
- BPM Work, IN02B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- Wednesday Oct 14
Tunnel --
- Cable pulls through penetrations (EES)
- Safety warden walk-through (Moser)
InjSB --
- BPM Work, IN02B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- Determining rack location for Wien magnet PSs, IN02-middle (Coleman, Grames, Moser)
- Safety warden walk-through (Moser)
- Conduit in penetration 135 (Electricians)
- Thursday Oct 15
Tunnel --
- S&A Level surveys
InjSB --
- BPM Work, IN0{2,3}B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, Rack re-org, IN02B22 (DC Power)
- Friday Oct 16
Tunnel --
- Cable pulls through penetrations (EES)
- Mott cable removals (Scott/Riad, EES)
InjSB --
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, Rack re-org, IN02B22 (DC Power)
- IN02B26 Power Lock-Out, ~915a (DC Power)
Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- Non-Tunnel Work
- Build new Y-chamber viewer => Y-built w/test screen, Laser being built.
- Use test screen + laser + S&A to verify position of first viewer => This week
- Install + align + vacuum seal (2) viewers => target this week
- Caryn will confirm but identified best ‘mushroom’ window, attach => done
- ME provide ALL points to S&A for installation (gun table, 2I stand, Y-chamber, 2 peds for Wien, 2 peds A1/A2) => ???
- Carlos' Wien-mania!
- Tunnel Work
- Complete remove old keV Mott cables => done
- Complete remove old gun HV cables => done
- Jim pulls Wien PS cables? => done???
- Does Wien HV cable pull start? => starting this week
- Scott will finish tie back of cables on tunnel floor to cable tray => done
- Refill 86? => no, not yet
- Standing Injector Service Building Work
- BPM Work, IN0{2,3}B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, Rack re-org, IN02B22 (DC Power)
- Monday Oct 19
Tunnel --
- Cryo u-tube pulls for 0L0{2,3,4}
- Tuesday Oct 20
Tunnel --
- Cable pulls and removals
InjSB --
- BPM Work, IN0{2,3}B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, IN02B22, 2p - 4p (DC Power)
- Wednesday Oct 21
Tunnel --
- S&A Verify line with new control
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
- Viewer work, IN03B07, 6a - 9a (Norris)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- M56 Hardware Removal from IN02B22, (I&C)
- Thursday Oct 22
Tunnel --
InjSB --
- Wien Magnet PS Install, IN02B22, afternoon (DC Power)
- Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
- Viewer work, IN03B07, 6a - 9a (Norris)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- Friday Oct 23
Tunnel --
InjSB --
- BPM Work, IN03B{{05-08}, 23}, 5a - 2p (Francis)
- Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Scott)
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
- Viewer work, IN03B07, 6a - 9a (Norris)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
Inj Service Building Work
Time | Wed 10/21 | Thu 10/22 | Fri 10/23 |
---|---|---|---|
5a - 9a | Dela Cruz, Norris, |
Dela Cruz, Norris, |
Dela Cruz, Norris, Francis |
9a - 12p | Francis, SSG, Windham | ||
12p - 4p | DC Power, SSG, |
DC Power, SSG, Windham, |
DC Power, SSG, Windham, Francis |
Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- Non-Tunnel Work
- Install NEG towers
- Attach new Gun2 or Gun3 valve (If desired)
- Finish Y-chamber viewers, attach
- Prep new Y-chamber for tunnel, can be under vacuum
- Wien-mania!
- -Wien magnetic field mapping
- -Bubba assembles the fixtures
- Tunnel work
- Vent Gun3 chamber to test Gun3 valve
- Vent Gun2 chamber to test Gun2 valve
- Remove NEG filter chamber before vent
- Setup mobile cleanroom for gun work => comes from TL (Bubba/Neil)
- Remove 2I NEG beam line
- remove NEG pedestal (temporarily)
- Replace 10” flange + SHV connector + blank off + pump down
- Pump down Blank off old Y-chamber + pinch off + removal
- Wrap up in itial UHV ion pump power supply power tests
- INSTALL lift and move gun table to move foot pads
- S&A sets points
Injector Tunnel and Service Building Work
Location Time |
Mon 10/26 | Tue 10/27 | Wed 10/28 | Thu 10/29 | Fri 10/30 |
---|---|---|---|---|---|
InjSB 5a - 9a |
Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis |
Tunnel 5a - 9a |
Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis |
InjSB 9a - 12p |
Francis, Windham, SSG | Francis, Windham, SSG | Francis, Windham, SSG | Francis, Windham, SSG | Francis, Windham, SSG |
Tunnel 9a - 12p |
Gun Vacuum (CIS) | Gun Vacuum (CIS) | Gun Vacuum (CIS) | ||
InjSB 12p - 4p |
Windham, SSG | Windham, SSG | Windham, SSG | Windham, SSG | Windham, SSG |
Tunnel 12p - 4p |
Gun Vacuum Work (CIS) | Gun Vacuum (CIS) | Gun Vacuum (CIS) |
Week 7 (Nov 2 - Oct 6) and beyond...
Tunnel work
- INSTALL sets new foot pads, new anchor bolts if needed
- INSTALL lift and move gun table to new foot pads
- INSTALL move new y-chamber from TL-1137 to injector, and vice versa
- S&A and CIS install and align Y-chamber + NEG tube + Gun table (CL cathode/anode)
- Pump down and leak check
- Check laser align/retro : back fill N2 + test retro from GaAs + test alignment to viewer
- Iterate as needed
- End week with laser + Y + Gun + NEG aligned (pre-bake)
- Prep for new suitcase (i.e. prep work to safe photocathodes during eventual gun bake)
Penetration Work
InjSB Penetrations that are open (click for pictures): above laser hut, 58, 86, 108, 135
- 34ft from floor of InjSB to floor of Inj tunnel
- 25ft from floor of InjSB to elevated Inj tunnel cable tray
Penetration Cable Pulls/Removals --
- Tony pulling new Wien E-field HV cables
- Norris (possibly) removing old Cat5 cable
- Norris pulling new viewer cables
Riad/Scott removing old Mott HV cablesColeman pulling new Wien B-field magnet cables- Cole pulling new neutron detector cables (above 0L03)
Scott pulling motor control cables for A1++
Fire System Work
Description of Task: Replacement of tunnel sprinkler piping, fire alarm control panels in B85 & B98, replacement of detection devices.
Latest construction schedule has contractor in Injector between 11/24/20 and 1/4/21.