** Replace YAG screens on Viewers 1,2 and 3 | ** Replace YAG screens on Viewers 1,2 and 3 | ||
** Replace leaky right-angle valve | ** Replace leaky right-angle valve | ||
− | ** Remove Deflecting Cavity and move TE_011 Cavity in its place | + | ** Remove Deflecting Cavity and move TE_011 Cavity in its place |
Revision as of 08:16, 2 February 2021
- Upgrade Glassman Gun PSS interlock chassis (Carlos)
- Beamline - no bake of beamline: (Mamun and Bubba)
- Replace YAG screens on Viewers 1,2 and 3
- Replace leaky right-angle valve
- Remove Deflecting Cavity and move TE_011 Cavity in its place
- Prep Chamber: (Mamun)
- Fix Transverse Manipulator
- Fix Sb boat
- Clean Sb pellets off chamber
- Gun HV Chamber: (Carlos)
- Clean anode, cathode front
- Replace Anode
- Replace Pierce geometry
- Upgrade anode HV bias feed-through to 5 kV
- Laser: (Shukui)
- Re-install 500 MHz green fiber laser
- Install new pulse laser