Line 23: | Line 23: | ||
** Replace Anode | ** Replace Anode | ||
** Replace Pierce geometry | ** Replace Pierce geometry | ||
− | ** Upgrade anode HV bias feed-through to | + | ** Upgrade anode HV bias feed-through to 10 kV |
Latest revision as of 09:47, 12 April 2021
- Upgrade Glassman Gun PSS interlock chassis (Carlos)
- Add vacuum interlock to HV supply (Scott)
- Beamline - no bake of beamline: (Mamun and Bubba)
- Replace YAG screens on Viewers 1,2 and 3
- Replace leaky right-angle valve
- Remove Deflecting Cavity and move TE_011 Cavity in its place
- Prep Chamber: (Mamun)- Completed [1]
- Fix Transverse Manipulator
- Fix Sb boat
- Clean Sb pellets off chamber
- Clean/check Bottom Heater
- Add Cs for Robust Photocathode research
- Clean/replace windows
- Add pucks with Moly and GaAs (Robust Photocathode) substrates
- Gun HV Chamber: (Carlos)
- Clean anode, cathode front
- Replace Anode
- Replace Pierce geometry
- Upgrade anode HV bias feed-through to 10 kV
- Laser: (Shukui)
- Re-install 500 MHz green fiber laser
- Install new pulse laser