Difference between revisions of "Phase 1 Commissioning Schedule"

From Ciswikidb
Jump to navigation Jump to search
Line 905: Line 905:
 
'''Update 6/29:''' ILD HCO pending; sending beam there not expected until 7/9. However, the main machine is facing delays as well. There is understandable reluctance about staffing the MCC during the weekend (including Monday, observing πŸ‘½) if supporting the injector tasks is unnecessary in terms of being on time overall. We are therefore trying not to schedule anything for the weekend at this time.
 
'''Update 6/29:''' ILD HCO pending; sending beam there not expected until 7/9. However, the main machine is facing delays as well. There is understandable reluctance about staffing the MCC during the weekend (including Monday, observing πŸ‘½) if supporting the injector tasks is unnecessary in terms of being on time overall. We are therefore trying not to schedule anything for the weekend at this time.
  
βˆ’
{| class="wikitable" style="text-align:center; background-color:#DAEBE8;"
+
{| class="wikitable" style="text-align:center; vertical-align:middle; background-color:#DAEBE8;"
βˆ’
|- style="font-weight:bold; vertical-align:middle; background-color:#70AAAF;"
+
|- style="font-weight:bold; background-color:#70AAAF;"
 
! style="background-color:#70AAAF" | OWL Shift
 
! style="background-color:#70AAAF" | OWL Shift
 
! style="background-color:#70AAAF" | Monday<br />6/28
 
! style="background-color:#70AAAF" | Monday<br />6/28
Line 916: Line 916:
 
! style="background-color:#70AAAF" | Sunday<br />7/4 πŸ‡ΊπŸ‡Έ
 
! style="background-color:#70AAAF" | Sunday<br />7/4 πŸ‡ΊπŸ‡Έ
 
! style="background-color:#70AAAF" | Notes/Goals
 
! style="background-color:#70AAAF" | Notes/Goals
βˆ’
|- style="vertical-align:middle;"
+
|-
 
| style="font-weight:bold; background-color:#96CEB4;" | Beam Commissioning<br />Plan (ATLis)
 
| style="font-weight:bold; background-color:#96CEB4;" | Beam Commissioning<br />Plan (ATLis)
 
| Continue 90Β° HWien w/ good transmission and auto-steer
 
| Continue 90Β° HWien w/ good transmission and auto-steer
Line 922: Line 922:
 
| Spot move and Wien setup for Mott measurement
 
| Spot move and Wien setup for Mott measurement
 
| Wien setup
 
| Wien setup
βˆ’
| Mott measurement
+
| FC2 Setup (till ~715A)
βˆ’
| Tentatively no staffing
+
| No Beam
βˆ’
| Tentatively no staffing
+
| No Beam
 
| rowspan="17" style="background-color:#CFE0E8;" | ILD running<br />possible<br />once HCO<br />complete and<br />BA granted
 
| rowspan="17" style="background-color:#CFE0E8;" | ILD running<br />possible<br />once HCO<br />complete and<br />BA granted
βˆ’
|- style="vertical-align:middle;"
+
|-
 
| style="font-weight:bold; background-color:#96CEB4;" | Shift Leader
 
| style="font-weight:bold; background-color:#96CEB4;" | Shift Leader
 
| Law
 
| Law
Line 933: Line 933:
 
| Law
 
| Law
 
| Law
 
| Law
βˆ’
| /
+
| No Beam
βˆ’
| /
+
| No Beam
βˆ’
|- style="vertical-align:middle;"
+
|-
 
| style="font-weight:bold; background-color:#96CEB4;" | Scientist #2
 
| style="font-weight:bold; background-color:#96CEB4;" | Scientist #2
 
|  
 
|  
Line 941: Line 941:
 
|  
 
|  
 
|  
 
|  
βˆ’
| Suleiman
+
|  
βˆ’
| /
+
| No Beam
βˆ’
| /
+
| No Beam
βˆ’
|- style="vertical-align:middle;"
+
|-
 
| style="font-weight:bold; background-color:#96CEB4;" | Crew Chief
 
| style="font-weight:bold; background-color:#96CEB4;" | Crew Chief
 
| Law
 
| Law
Line 953: Line 953:
 
| Forman (?)
 
| Forman (?)
 
| Forman (?)
 
| Forman (?)
βˆ’
|- style="vertical-align:middle;"
+
|-
 
| style="font-weight:bold; background-color:#96CEB4;" | SSO
 
| style="font-weight:bold; background-color:#96CEB4;" | SSO
 
| Deir
 
| Deir
Line 962: Line 962:
 
| Garcia (?)
 
| Garcia (?)
 
| Garcia (?)
 
| Garcia (?)
βˆ’
|- style="font-weight:bold; vertical-align:middle; background-color:#87BDD8;"
+
|- style="font-weight:bold; background-color:#87BDD8;"
 
| DAY Shift
 
| DAY Shift
 
| 6/28
 
| 6/28
Line 971: Line 971:
 
| 7/3
 
| 7/3
 
| 7/4 πŸ‡ΊπŸ‡Έ
 
| 7/4 πŸ‡ΊπŸ‡Έ
βˆ’
|- style="vertical-align:middle; background-color:#CFE0E8;"
+
|- style="background-color:#CFE0E8;"
 
| style="font-weight:bold; background-color:#B7D7E8;" | Beam Commissioning <br /> Plan (ATLis)
 
| style="font-weight:bold; background-color:#B7D7E8;" | Beam Commissioning <br /> Plan (ATLis)
 
| morning TBD; 12-24 Bunch length system check and measurement
 
| morning TBD; 12-24 Bunch length system check and measurement
 
| Heat and activate cathode
 
| Heat and activate cathode
 
| 8-12 open; 12-16 beam recovery to FC2
 
| 8-12 open; 12-16 beam recovery to FC2
βˆ’
| Wien match
+
| Wien match<br />(500keV Limited until ~2P)
βˆ’
| Float or QCM characterization
+
| TBD<br />(500keV Limited until ~2P)
βˆ’
| Tentatively no staffing
+
| No Beam
βˆ’
| Tentatively no staffing
+
| No Beam
βˆ’
|- style="vertical-align:middle; background-color:#CFE0E8;"
+
|- style="background-color:#CFE0E8;"
 
| style="font-weight:bold; background-color:#B7D7E8;" | Shift Leader
 
| style="font-weight:bold; background-color:#B7D7E8;" | Shift Leader
 
| morning TBD; 12-24 Kazimi
 
| morning TBD; 12-24 Kazimi
Line 987: Line 987:
 
| Turner
 
| Turner
 
| Wang
 
| Wang
βˆ’
| /
+
| No Beam
βˆ’
| /
+
| No Beam
βˆ’
|- style="vertical-align:middle; background-color:#CFE0E8;"
+
|- style="background-color:#CFE0E8;"
 
| style="font-weight:bold; background-color:#B7D7E8;" | Scientist #2
 
| style="font-weight:bold; background-color:#B7D7E8;" | Scientist #2
 
| 12-24 Hofler; 12-16 Bruker
 
| 12-24 Hofler; 12-16 Bruker
Line 996: Line 996:
 
| Hofler
 
| Hofler
 
| Bruker?
 
| Bruker?
βˆ’
| /
+
| No Beam
βˆ’
| /
+
| No Beam
βˆ’
|- style="vertical-align:middle; background-color:#CFE0E8;"
+
|- style="background-color:#CFE0E8;"
 
| style="font-weight:bold; background-color:#B7D7E8;" | Crew Chief
 
| style="font-weight:bold; background-color:#B7D7E8;" | Crew Chief
 
| Aiken
 
| Aiken
Line 1,007: Line 1,007:
 
| Merz (?)
 
| Merz (?)
 
| Merz (?)
 
| Merz (?)
βˆ’
|- style="vertical-align:middle; background-color:#CFE0E8;"
+
|- style="background-color:#CFE0E8;"
 
| style="font-weight:bold; background-color:#B7D7E8;" | SSO
 
| style="font-weight:bold; background-color:#B7D7E8;" | SSO
 
| Gauthier
 
| Gauthier
Line 1,016: Line 1,016:
 
| Aiken (?)
 
| Aiken (?)
 
| Aiken (?)
 
| Aiken (?)
βˆ’
|- style="font-weight:bold; vertical-align:middle; background-color:#70AAAF;"
+
|- style="font-weight:bold; background-color:#70AAAF;"
 
| SWING Shift
 
| SWING Shift
 
| 6/28
 
| 6/28
Line 1,025: Line 1,025:
 
| 7/3
 
| 7/3
 
| 7/4 πŸ‡ΊπŸ‡Έ
 
| 7/4 πŸ‡ΊπŸ‡Έ
βˆ’
|- style="vertical-align:middle;"
+
|-
 
| style="font-weight:bold; background-color:#96CEB4;" | Beam Commissioning<br />Plan (ATLis)
 
| style="font-weight:bold; background-color:#96CEB4;" | Beam Commissioning<br />Plan (ATLis)
 
| 12-24 Bunch length system check and measurement
 
| 12-24 Bunch length system check and measurement
 
| Heat and activate cathode (cont'd), no beam
 
| Heat and activate cathode (cont'd), no beam
βˆ’
| Bunch length setup
+
| Bunch length setup<br />Capture FE Characterization
βˆ’
| Float or PQB if things work well
+
| FC2 Setup
βˆ’
| PQB if things work well
+
| Mott Checkout / <br />FC2 Setup
βˆ’
| Tentatively no staffing
+
| No Beam
βˆ’
| Tentatively no staffing
+
| No Beam
βˆ’
|- style="vertical-align:middle;"
+
|-
 
| style="font-weight:bold; background-color:#96CEB4;" | Shift Leader
 
| style="font-weight:bold; background-color:#96CEB4;" | Shift Leader
 
| 12-24 Kazimi
 
| 12-24 Kazimi
 
| Grames
 
| Grames
 
| Kazimi
 
| Kazimi
βˆ’
| Amali?
+
| Wang
βˆ’
| Amali?
+
| Suleiman / Wang?
βˆ’
| /
+
| No Beam
βˆ’
| /
+
| No Beam
βˆ’
|- style="vertical-align:middle;"
+
|-
 
| style="font-weight:bold; background-color:#96CEB4;" | Scientist #2
 
| style="font-weight:bold; background-color:#96CEB4;" | Scientist #2
 
| 12-24 Hofler
 
| 12-24 Hofler
 
|  
 
|  
 
|  
 
|  
βˆ’
| Bruker?
+
|  
βˆ’
| Bruker?
+
|  
βˆ’
| /
+
| No Beam
βˆ’
| /
+
| No Beam
 
|-
 
|-
βˆ’
| style="vertical-align:middle; font-weight:bold; background-color:#96CEB4;" | Crew Chief
+
| style="font-weight:bold; background-color:#96CEB4;" | Crew Chief
βˆ’
| style="vertical-align:middle;" | McCaughan
+
| McCaughan
 
| McCaughan
 
| McCaughan
 
| Moser
 
| Moser
βˆ’
| style="vertical-align:middle;" | Moser
+
| Moser
βˆ’
| style="vertical-align:middle;" | Moser
+
| Moser
βˆ’
| style="vertical-align:middle;" | Carlino (?)
+
| Carlino (?)
βˆ’
| style="vertical-align:middle;" | Carlino (?)
+
| Carlino (?)
 
|-
 
|-
βˆ’
| style="vertical-align:middle; font-weight:bold; background-color:#96CEB4;" | SSO
+
| style="font-weight:bold; background-color:#96CEB4;" | SSO
βˆ’
| style="vertical-align:middle;" | Mock
+
| Mock
 +
| Mock
 +
| Mock
 
| Mock
 
| Mock
 
| Mock
 
| Mock
βˆ’
| style="vertical-align:middle;" | Mock
+
| Anthony (?)
βˆ’
| style="vertical-align:middle;" | Mock
+
| Anthony (?)
βˆ’
| style="vertical-align:middle;" | Anthony (?)
 
βˆ’
| style="vertical-align:middle;" | Anthony (?)
 
 
|}
 
|}
  

Revision as of 17:10, 30 June 2021

Week 0, May 17th-23rd

Week 1, May 24th-30th

Week 2, May 31stπŸ‡ΊπŸ‡Έ - June 6th

Week 3, June 7th-13th

Week 4, June 14th-20th

Week 5, June 21st-27th

Week 6, June 28th-July 4th

Collapse

Yan: tentatively available every day, DAY or SWING as needed.
Update 6/29: ILD HCO pending; sending beam there not expected until 7/9. However, the main machine is facing delays as well. There is understandable reluctance about staffing the MCC during the weekend (including Monday, observing πŸ‘½) if supporting the injector tasks is unnecessary in terms of being on time overall. We are therefore trying not to schedule anything for the weekend at this time.

OWL Shift Monday
6/28
Tuesday
6/29
Wednesday
6/30
Thursday
7/1
Friday
7/2
Saturday
7/3
Sunday
7/4 πŸ‡ΊπŸ‡Έ
Notes/Goals
Beam Commissioning
Plan (ATLis)
Continue 90Β° HWien w/ good transmission and auto-steer Mott Spot move and Wien setup for Mott measurement Wien setup FC2 Setup (till ~715A) No Beam No Beam ILD running
possible
once HCO
complete and
BA granted
Shift Leader Law Suleiman Law Law Law No Beam No Beam
Scientist #2 No Beam No Beam
Crew Chief Law Law Law Law Forman Forman (?) Forman (?)
SSO Deir Deir Deir Deir Deir Garcia (?) Garcia (?)
DAY Shift 6/28 6/29 6/30 7/1 7/2 7/3 7/4 πŸ‡ΊπŸ‡Έ
Beam Commissioning
Plan (ATLis)
morning TBD; 12-24 Bunch length system check and measurement Heat and activate cathode 8-12 open; 12-16 beam recovery to FC2 Wien match
(500keV Limited until ~2P)
TBD
(500keV Limited until ~2P)
No Beam No Beam
Shift Leader morning TBD; 12-24 Kazimi Grames Kazimi Turner Wang No Beam No Beam
Scientist #2 12-24 Hofler; 12-16 Bruker Bruker Hofler Bruker? No Beam No Beam
Crew Chief Aiken Aiken Freeman Frierson Merz Merz (?) Merz (?)
SSO Gauthier Gauthier Gauthier Jones Jones Aiken (?) Aiken (?)
SWING Shift 6/28 6/29 6/30 7/1 7/2 7/3 7/4 πŸ‡ΊπŸ‡Έ
Beam Commissioning
Plan (ATLis)
12-24 Bunch length system check and measurement Heat and activate cathode (cont'd), no beam Bunch length setup
Capture FE Characterization
FC2 Setup Mott Checkout /
FC2 Setup
No Beam No Beam
Shift Leader 12-24 Kazimi Grames Kazimi Wang Suleiman / Wang? No Beam No Beam
Scientist #2 12-24 Hofler No Beam No Beam
Crew Chief McCaughan McCaughan Moser Moser Moser Carlino (?) Carlino (?)
SSO Mock Mock Mock Mock Mock Anthony (?) Anthony (?)

Week 7, July 5th-July 11th

Week 8, July 12th-July 18th

High-Level View June 7th-July16th