− | + | # 8/23/21 Start commissioning (2 weeks) [In progress] | |
− | + | # 8/23 BNNT cooldown in CMTF (Allegedly) | |
− | |||
− | # 8/23/21 Start commissioning (2 weeks) | ||
− | # 8/23 BNNT cooldown in CMTF | ||
# 9/7/21 Perform experiment (3 weeks) | # 9/7/21 Perform experiment (3 weeks) | ||
# 10/18 C50R in CMTF | # 10/18 C50R in CMTF | ||
Line 30: | Line 27: | ||
'''[[E-beam_Irradiation_Experiment| Experiment]]:''' | '''[[E-beam_Irradiation_Experiment| Experiment]]:''' | ||
− | * | + | * Shift staffing schedule good for now; 2nd pass later. Li training as operator. |
− | |||
− | |||
'''Software''' | '''Software''' | ||
− | + | * [https://accweb.acc.jlab.org/hco/reports/overall-status?destinationId=50&destinationId=54&destinationId=55&categoryId=&systemId=®ionId=&groupId=&qualified= HCO complete to keV; underway in MeV] | |
− | * [https://accweb.acc.jlab.org/hco/reports/overall-status?destinationId=50&destinationId=54&destinationId=55&categoryId=&systemId=®ionId=&groupId=&qualified= HCO underway] | ||
'''CIS/EGG:''' | '''CIS/EGG:''' | ||
− | * | + | * Photocathode with 4% QE created by Max and behaving well! |
− | |||
− | |||
'''DC Power:''' | '''DC Power:''' | ||
− | * Trims: Complete - | + | * Trims: Complete - excluding M603H/V pair not appearing on trim rack |
* Solenoid [http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1672 UITFList Task]: Interlock checks completed. Diagnostics on box supply reading incorrectly, measured input voltage at supply to be 470VAC. Diagnostic repair and powering load to be completed at first opportunity. | * Solenoid [http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1672 UITFList Task]: Interlock checks completed. Diagnostics on box supply reading incorrectly, measured input voltage at supply to be 470VAC. Diagnostic repair and powering load to be completed at first opportunity. | ||
− | + | ||
'''Instrumentation and Controls:''' | '''Instrumentation and Controls:''' | ||
− | |||
* Target Motion Control - [https://logbooks.jlab.org/entry/3884440 Carriage remotely operable], step count needs some fine tuning. | * Target Motion Control - [https://logbooks.jlab.org/entry/3884440 Carriage remotely operable], step count needs some fine tuning. | ||
− | * Control Screen complete | + | * Control Screen complete and functional |
''Vacuum (Ketchum/Kortze)'' | ''Vacuum (Ketchum/Kortze)'' | ||
− | * VFVM401 Fast Valve [https://logbooks.jlab.org/entry/3890917 limit switches adjusted]; Kortze working firmware. | + | * VFVM401 Fast Valve [https://logbooks.jlab.org/entry/3890917 limit switches adjusted]; Kortze working firmware; valve open. |
− | |||
''BCM'' | ''BCM'' | ||
Line 61: | Line 51: | ||
'''SSG:''' | '''SSG:''' | ||
− | |||
''BLM installation underway:'' | ''BLM installation underway:'' | ||
* Replace those previously removed | * Replace those previously removed | ||
Line 74: | Line 63: | ||
'''ME / Installation:''' | '''ME / Installation:''' | ||
− | |||
* [[media:JL0029599-2000UITF_MeV_BEAMLINE07-JUN-21.pdf|Songsheet]] being updated by Shaun; be sure to let him know when changes are made! | * [[media:JL0029599-2000UITF_MeV_BEAMLINE07-JUN-21.pdf|Songsheet]] being updated by Shaun; be sure to let him know when changes are made! | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
'''Action items:''' | '''Action items:''' | ||
− | # | + | # Open Tasks: |
#* RCG Test (Keith) (Done) | #* RCG Test (Keith) (Done) | ||
#* Fast Valve Test (Leo/Jim) | #* Fast Valve Test (Leo/Jim) | ||
− | + | #* Target Encoder Interlock (Scott/Weiwei/Gary) [Complete] | |
− | #* Target Encoder Interlock (Scott/Weiwei/Gary) | ||
#* BLM test (Scott B.) | #* BLM test (Scott B.) | ||
− | #* Target Rail calibration | + | #* Target Rail calibration [Complete] |
− | + | # Snap file for design optics (Dennis/Xi) [Complete; loaded] | |
− | # Snap file for design optics (Dennis/Xi) | ||
# Daily Run Coordinator Meetings (Mike/Gigi) | # Daily Run Coordinator Meetings (Mike/Gigi) | ||
# Populate shift plans (Mike / Gigi) | # Populate shift plans (Mike / Gigi) | ||
− | # Shift taker instructions (Mike) | + | # Shift taker instructions (Mike) [Complete] |
− | # HCO | + | # HCO [Complete - keV] |
− | # Beam Authorization (Mike) | + | # Beam Authorization (Mike) [Complete] |
# Hazard analysis for Randy (Mike) | # Hazard analysis for Randy (Mike) | ||
+ | # Shielding package verified by RCG [Complete] | ||
+ | # Quick Reference Drawing; File transferred to Mike and updated. Final walk down needed. | ||
− | |||
− | |||
[[Meeting_minutes | Back to Main Meeting Minutes Page]] | [[Meeting_minutes | Back to Main Meeting Minutes Page]] |
Revision as of 22:07, 24 August 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/984025598.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 984025598.
- To join via phone, use one of the following numbers and the Conference ID: 984025598.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
- 8/23/21 Start commissioning (2 weeks) [In progress]
- 8/23 BNNT cooldown in CMTF (Allegedly)
- 9/7/21 Perform experiment (3 weeks)
- 10/18 C50R in CMTF
- Booster qualification following experiment until cryo trade to CMTF
New items for discussion:
General:
- Updated Ops Page
- Commissioning plan (basic)
- Commissioning plan (detailed, to break into shift plans)
Reports by Group:
- Shift staffing schedule good for now; 2nd pass later. Li training as operator.
Software
CIS/EGG:
- Photocathode with 4% QE created by Max and behaving well!
DC Power:
- Trims: Complete - excluding M603H/V pair not appearing on trim rack
- Solenoid UITFList Task: Interlock checks completed. Diagnostics on box supply reading incorrectly, measured input voltage at supply to be 470VAC. Diagnostic repair and powering load to be completed at first opportunity.
Instrumentation and Controls:
- Target Motion Control - Carriage remotely operable, step count needs some fine tuning.
- Control Screen complete and functional
Vacuum (Ketchum/Kortze)
- VFVM401 Fast Valve limit switches adjusted; Kortze working firmware; valve open.
BCM
- BCM project software integration under way between Musson/Seaton and Sue Witherspoon
SSG: BLM installation underway:
- Replace those previously removed
- Additions
- In crotch of MeV/Wastewater selecting dipole.
- Near 1st new diagnostic cross d.s. of solenoid
- Near 2nd new diagnostic cross by FC4
- D.S. of target after lead shielding
FSD inputs (original)
- BCM current clamp system
- Update gold masking
ME / Installation:
- Songsheet being updated by Shaun; be sure to let him know when changes are made!
Action items:
- Open Tasks:
- RCG Test (Keith) (Done)
- Fast Valve Test (Leo/Jim)
- Target Encoder Interlock (Scott/Weiwei/Gary) [Complete]
- BLM test (Scott B.)
- Target Rail calibration [Complete]
- Snap file for design optics (Dennis/Xi) [Complete; loaded]
- Daily Run Coordinator Meetings (Mike/Gigi)
- Populate shift plans (Mike / Gigi)
- Shift taker instructions (Mike) [Complete]
- HCO [Complete - keV]
- Beam Authorization (Mike) [Complete]
- Hazard analysis for Randy (Mike)
- Shielding package verified by RCG [Complete]
- Quick Reference Drawing; File transferred to Mike and updated. Final walk down needed.