(Created page with "=== Mar 10, 2023 == * (Steve, Jessica, Max, Marcy, Joe) * Max ** ...running final beam test, plans to wrap up today, latest Sunday ** ...coordinating w/ DC Power and I&C to de...") |
|||
Line 1: | Line 1: | ||
− | === Mar 10, 2023 == | + | === Mar 10, 2023 === |
* (Steve, Jessica, Max, Marcy, Joe) | * (Steve, Jessica, Max, Marcy, Joe) | ||
* Max | * Max |
Revision as of 09:29, 10 March 2023
Mar 10, 2023
- (Steve, Jessica, Max, Marcy, Joe)
- Max
- ...running final beam test, plans to wrap up today, latest Sunday
- ...coordinating w/ DC Power and I&C to de-energize and disconnect cables to magnets and bpm's
- Marcy
- ...polishing CEBAF install work plan gantt chart, will circulate and review on Monday
- ...coordinating w/ Vince for modification of "blue" HV chamber base plate next week
- Joe
- Found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517